Significant Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Governing section
Terrebonne Parish Code § 12-6
Permit name
Coastal Impact Certificate
Fee range
$100.00 to $5,000.00 by value/acreage
Cure period
5 to 30 days before misdemeanor charge
Enforcing office
TPCG Coastal Restoration Department

Summary

Terrebonne Parish doesn't have a separate boat-dock ordinance; instead, section 12-6 requires a Coastal Impact Certificate before building bulkheads or any other structure, including a dock, that needs a Louisiana coastal zone permit or a federal Section 10/404 permit from the Army Corps of Engineers.

These county ordinances apply to unincorporated areas of Terrebonne Parish. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

(a)A coastal impact certificate from the Terrebonne Parish Consolidated Government shall be required prior to the performing of any of the following: soil regrading as defined in article II of this chapter; seismographic survey; or the construction of any well, well site, well platform, other mining operation, pipeline, canal; or for the dredging of canals, bayous, borrow pits, wetlands, ponds, lakes, bays, slips, shells or other excavation; or the construction of bulkheads, drainage control structures, flood control structures, landfills, spoil areas, platforms, board roads, levees, battures; or the construction of non-residential facilities requiring a coastal zone permit from the Louisiana Department of Energy and Natural Resources or a Section 10/404 permit from the United States Army Corps of Engineers; or the construction of single-family residential structures requiring a coastal zone permit from the Louisiana Department of Energy and Natural Resources or a Section 10/404 permit from the United States Army Corps of Engineers.

Full Breakdown

There's no ordinance in the Terrebonne Parish Code that names 'boat docks' specifically. Waterfront construction, including bulkheads and any structure requiring a state or federal wetlands permit, is captured instead by Chapter 12's Coastal Impact Certificate, adopted under Ordinance No. 9663 in October 2024. Section 12-6(a) requires the certificate before performing soil regrading, seismographic survey work, construction of wells or pipelines, dredging of canals or wetlands, and the construction of bulkheads, drainage control structures, flood control structures, landfills, spoil areas, platforms, board roads, levees and battures.

It goes further with catch-all clauses covering construction of single-family residential structures requiring a coastal zone permit from the Louisiana Department of Energy and Natural Resources or a Section 10/404 permit from the Army Corps of Engineers, and, separately, any other structure or facility in the parish requiring one of those same two permits. Because a private dock, pier, or boathouse built over water or wetlands in coastal Terrebonne Parish typically needs a Section 10/404 permit from the Corps, or a state coastal use permit, that construction falls inside this catch-all and triggers the parish certificate requirement.

Section 12-2 makes the chapter apply parish-wide, and section 12-4 directs that its provisions be liberally construed in the parish's favor and read as not limiting any other state-granted powers. 00 for larger commercial or high-acreage work.

Violations & Fines

Building without a coastal impact certificate isn't an automatic misdemeanor: section 12-66(a) requires the parish to notify the violator and give five to thirty days to fix it, by getting a certificate, removing the obstruction, or bringing the work into compliance. Only if the violation can't be cured that way, or the owner refuses to comply, does it become a misdemeanor under section 12-66(b), with each day a separate offense and falsified applications drawing the maximum penalty state law allows.

Frequently Asked Questions

Do I need a permit to build a boat dock in Terrebonne Parish?
The parish code doesn't mention docks by name, but section 12-6 requires a Coastal Impact Certificate before building bulkheads or any structure needing a Louisiana coastal zone permit or a federal Section 10/404 permit, which covers most dock and pier construction over parish waters or wetlands.
How much does the Coastal Impact Certificate cost?
Section 12-8 scales the fee to project value and wetland or water-bottom acreage impacted, from $100.00 for a small single-family project under one acre up to $5,000.00 for larger or higher-acreage commercial work.
What happens if I build without the certificate?
Section 12-66(a) requires the parish to notify you first and give five to thirty days to fix the problem by getting a certificate or removing the structure. Only uncorrectable violations, or refusal to comply, become a misdemeanor under section 12-66(b).
Who handles coastal construction permits in Terrebonne Parish?
The Terrebonne Parish Consolidated Government issues Coastal Impact Certificates, and the Director of the TPCG Coastal Restoration Department can pursue injunctions or other legal action against uncorrected violations under section 12-66(c).

Sources & Official References

Other rules in Terrebonne Parish

All Terrebonne Parish rules

Compare Terrebonne Parish to another location·View the Louisiana environmental rules overview

Get notified when Boat Dock Permits in Terrebonne Parish, LA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.