Terrebonne Parish, LA Environmental Rules: Erosion Control (2026)

Significant Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Applies to
All land disturbing activities in the parish
Exempt
Agricultural land disturbing activities
Required before disturbance
Erosion control measures installed
Enforcement tool
Cease-and-desist order halting construction
Penalty
Minimum $500 fine, up to 90 days jail
Permit hold
Occupational permits withheld until corrected

Summary

Terrebonne Parish Code § 22-354 requires erosion and sediment control measures on every land-disturbing site in the parish, from silt fencing to stabilized construction entrances, before ground is disturbed. Violators face a notice of violation, a mandatory cease-and-desist halting all work, and a criminal fine of at least $500 plus up to 90 days in jail per violation.

These county ordinances apply to unincorporated areas of Terrebonne Parish. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

(a)Purpose/intent. ... it is the intent of this article to control soil erosion and sedimentation caused by land disturbing activities in Terrebonne Parish. ... (d)Design requirements. The following requirements shall be met on all sites:(1)Appropriate erosion control measures shall be installed prior to any land disturbing activity and thereafter whenever necessary. ... (3)Water shall not be discharged from the site in a manner that causes erosion at or downstream of the point of discharge. ... (g)Enforcement and penalties. ... (3)Civil and criminal penalties. In addition to or as an alternative to any penalty provided herein or by law, any person who violates the provisions of this article shall be punished by a fine of not less than five hundred dollars ($500.00) or by imprisonment for a period not to exceed ninety (90) days, or both such fine and imprisonment. Such person shall be guilty of a separate offense for each day during which the violation occurs or continues.

Full Breakdown

Section 22-354 governs erosion and sediment control for land disturbing activities across Terrebonne Parish, defined broadly as any manmade change to the land surface including clearing, excavating, filling, transporting and grading. Before disturbing a site, an owner must install appropriate erosion control measures, and keep them in place afterward whenever necessary; sediment-laden water leaving the site must be detained so it does not cause erosion at or downstream of the discharge point. The ordinance sets specific site rules: any crossing of a natural watercourse, ditch, drainage easement or swale by site access must use a properly sized culvert or low-water crossing that does not block water flow; storm drain inlets must be protected against sedimentation; streets must be kept clean, with a stone construction entrance installed to keep mud from being tracked and washed into storm drains; and erosion control measures must stay in place for the entire disturbance period until the site is fully stabilized.

Agricultural land disturbing activities, defined to exclude farm buildings like dwellings, barns and sheds, are exempt. The Terrebonne Parish Consolidated Government inspects sites for compliance and, when it finds a violation, issues a written notice specifying the remedial measures and a compliance schedule; the notice can be appealed to the parish's Appeal Authority within 15 days. A cited property owner must halt all construction under a cease-and-desist order until the parish confirms compliance, and the parish will not release an occupational permit until stormwater practices are corrected and accepted.

If a violator fails to restore disturbed land, the parish can do the work itself and place a lien on the property for the cost.

Violations & Fines

Failing to install or maintain required erosion control measures triggers a written notice of violation and a mandatory cease-and-desist order halting all construction until the parish confirms compliance. Under section 22-354(g)(3), a violator faces a fine of not less than $500, up to 90 days in jail, or both, with each day of continued violation a separate offense, and occupational permits are withheld until stormwater practices are corrected.

Frequently Asked Questions

Does erosion control apply to my farm in Terrebonne Parish?
No. Section 22-354 exempts agricultural land disturbing activities, defined as disturbing land for growing crops, forestry or pasturing livestock. That exemption does not cover building farm structures like dwellings, barns or sheds, which still need erosion control measures like any other construction site.
What happens if I get a cease-and-desist order for erosion control in Terrebonne Parish?
All construction activity must stop immediately and stays stopped until Terrebonne Parish Consolidated Government confirms the site is back in compliance and the erosion or sediment violation has been addressed. Ignoring the order can add civil, criminal or monetary penalties on top of the fine already tied to the underlying violation.
Can I get my occupational permit before fixing an erosion violation?
No. Section 22-354(g)(5) specifically withholds occupational permits until corrections to all stormwater practices have been made and accepted by Terrebonne Parish Consolidated Government, so the underlying erosion violation must be resolved before that permit is issued.

Sources & Official References

Other rules in Terrebonne Parish

All Terrebonne Parish rules

Compare Terrebonne Parish to another location·View the Louisiana environmental rules overview

Get notified when Erosion Control in Terrebonne Parish, LA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.