Key Facts
- Riparian buffer
- 50 feet from top-of-bank each side
- Reduced buffer floor
- 10 feet minimum if setback under 50 ft
- E&S plan trigger
- Required before earth disturbance
- Detention design storm
- 2-year, 24-hour event to 1-year flow
- Max fine
- $200 per violation, per day
- Appeal window
- 30 days to Montgomery County court
Summary
Abington Township's Stormwater Management Ordinance requires an approved erosion and sediment control plan for regulated earth disturbance and a 50-foot riparian buffer around any perennial or intermittent stream on a development site, enforced with fines up to $200 per day under Chapter 142.
§ 142-403. Erosion and sediment control during regulated earth disturbance activities. ... Evidence of any necessary permit(s) for regulated earth disturbance activities from the appropriate DEP regional office or County Conservation District must be provided to the Municipality. ... ... § 142-408. Stream bank erosion requirements (channel protection). A. If a perennial or intermittent stream passes through the site, the applicant shall create a riparian buffer extending a minimum of 50 feet to either side of the top-of-bank of the channel. The buffer area shall be established and maintained in an undisturbed state. This buffer area may be maintained as a meadow with minimal mowing of the grassed area, or as a forested buffer, being planted with appropriate native vegetation. ... If the applicable rear or side yard setback is less than 50 feet, the buffer width may be reduced to 25% of the setback to a minimum of 10 feet. ... ... § 142-905. Violations and penalties. A. Anyone violating the provisions of this chapter shall be guilty of a summary offense and, upon conviction, shall be subject to a fine of not more than $200 for each violation, recoverable with costs.
Full Breakdown
Chapter 142, adopted by Ord. No. 2100 to implement the Pennypack Creek, Tookany/Tacony-Frankford and Wissahickon Creek Act 167 watershed plans, governs earth disturbance in Abington. Section 142-403 requires evidence of any necessary DEP or County Conservation District permit for regulated earth disturbance before work proceeds, and requires infiltration BMP areas to be protected from sedimentation and compaction during construction so they retain infiltration capacity; an infiltration BMP may not be built or receive runoff until its whole contributing drainage area has reached final stabilization. Section 142-408 targets stream bank erosion directly: where a perennial or intermittent stream crosses a site, the applicant must create a riparian buffer extending at least 50 feet to either side of the top-of-bank, kept undisturbed as a mown meadow or a forested buffer of native vegetation.
Where the rear or side yard setback is under 50 feet, the buffer may shrink to 25% of that setback, with a 10-foot floor. Applicants must also design a BMP to detain the two-year, 24-hour storm to the pre-development one-year flow rate, using a minimum three-inch outlet orifice with a trash rack against clogging. The chapter does not include lakes or wetlands within this streambank buffer duty.
Violations & Fines
Section 142-905 makes any violation of Chapter 142 a summary offense: on conviction, a fine of not more than $200 for each violation, plus costs, and each day the violation continues is a separate, cumulative offense. The township may also pursue injunctive or mandamus relief in court, and § 142-906 allows an aggrieved person to appeal a township decision to the Montgomery County Court of Common Pleas within 30 days.
Frequently Asked Questions
Do I need an erosion control plan to build in Abington Township?
How wide a stream buffer does Abington require?
What's the penalty for violating the stormwater/erosion ordinance?
Sources & Official References
Other rules in Abington
Compare Abington to another location·View the Pennsylvania environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Erosion Control in Nearby Cities
How other cities in Montgomery County handle erosion control.