Key Facts

No disturbance
Slopes of 35% or greater
Transitional grading only
Slopes of 25.0% to 34.9%
Steep slope definition
Slopes in excess of 15% in gradient
Revegetation plan
Required when a steep slope is disturbed
Tree identification
Caliper of eight inches or more, measured three inches above ground
Municipal exemption
Municipally owned properties are exempt

Summary

In Bloomfield Township, New Jersey, § 315-30(Q) bars all soil disturbance on slopes of 35% or greater, limits slopes of 25.0% to 34.9% to transitional grading, and requires a revegetation plan for disturbed steep slopes. The code states the aim as preventing erosion and siltation of streams.

Q. Steep slope. ... (2) Objective. The purpose of this subsection is to minimize cutting and grading of steep slope areas as well as to minimize the disturbance of soil and removal of vegetative cover. Adherence to these regulations will assist in preventing erosion, siltation of streams; and other maintenance and safety problems. ... GRADING LIMITATIONS The extent of the disturbance allowed see chart below. Slopes (percent) Disturbance Allowed 35% or greater No disturbance allowed 25.0% to 34.9% Only transitional grading 15.0% to 24.9% Only transitional grading or road construction 0.0% to 14.9% All construction allowed ... (5) If any disturbance is planned to a steep slope area or if a steep slope has been disturbed by prior land use such as agriculture, a revegetation plan shall be provided.

Full Breakdown

Bloomfield Township addresses erosion most directly in the steep slope subsection of its design standards, § 315-30(Q), added 3-19-2012 by Ord. No. 12-15. It applies to the disturbance of soil and the construction of structures, roads, retaining walls and parking lots in areas of steep slopes, and municipally owned properties are exempt. The stated objective is to minimize cutting and grading of steep slope areas and the disturbance of soil and removal of vegetative cover, which the code says assists in preventing erosion and siltation of streams.

The grading limitations chart sets the allowed disturbance by slope: 35% or greater, no disturbance allowed; 25.0% to 34.9%, only transitional grading; 15.0% to 24.9%, only transitional grading or road construction; 0.0% to 14.9%, all construction allowed. Steep slope includes slopes in excess of 15% in gradient, measured by two-foot contours in a thirty-foot horizontal length.

An applicant must submit a steep slope analysis on a plot plan showing the slope classes with square footage in each, a lot grading plan, retaining wall details, and the limits of clearing and disturbance, which are held to be the maximum permitted on the site. A landscaping plan must identify trees with a caliper of eight inches or more measured three inches above ground level and show which are to be removed. If any disturbance is planned to a steep slope, or a steep slope was disturbed by prior land use such as agriculture, a revegetation plan must be provided. Relief goes to the Zoning Board of Adjustments, and existing structures are exempt while maintained in good order.

Two other chapters add erosion standards. Section 494-3(A)(1) sets the minimum standards for erosion control for major development stormwater measures by the Soil and Sediment Control Act, N.J.S.A. 4:24-39 et seq., and N.J.A.C. 2:90. Section 484-13(B) bars soil moving that increases the velocity or changes the direction of surface water runoff without on-site management.

Violations & Fines

Disturbing soil on a slope of 35% or greater, grading beyond the limits allowed for the slope class, or skipping the required revegetation plan violates § 315-30(Q). The Zoning Officer or Construction Official can issue stop-work orders and withhold permits under § 315-53, the Municipal Judge decides penalties, and § 1-15 sets a fine not exceeding $2,000, imprisonment up to 90 days or community service up to 90 days, with each day a separate offense.

Frequently Asked Questions

Can I regrade a steep slope on my Bloomfield Township lot?
It depends on the slope class printed in § 315-30(Q). On slopes of 35% or greater no disturbance is allowed. On 25.0% to 34.9% only transitional grading is allowed, and on 15.0% to 24.9% only transitional grading or road construction. Construction is fully allowed only on slopes of 0.0% to 14.9%.
How does Bloomfield measure a steep slope?
The code measures vertical rise on the basis of two-foot contours in a thirty-foot horizontal length, with contours documented by on-site survey or photogrammetric aerial topography. Steep slope includes slopes in excess of 15% in gradient, and the applicant's plot plan must show slope classes with the area in square feet within each class.
What plans does the Township require before disturbing a steep slope?
Section 315-30(Q)(4) requires a steep slope analysis, a lot grading plan showing driveways, structures and retaining walls, retaining wall profiles and calculations, the limits of clearing and disturbance, and landscaping plans identifying trees with a caliper of eight inches or more. Section 315-30(Q)(5) adds a revegetation plan when a steep slope is disturbed.
Where do stormwater erosion standards come from in Bloomfield?
For major development, § 494-3(A)(1) of the Stormwater Control chapter says the minimum standards for erosion control are those established under the Soil and Sediment Control Act, N.J.S.A. 4:24-39 et seq., and implementing rules at N.J.A.C. 2:90. Chapter 484 soil permits carry a $500 application fee for a minor permit and $1,500 for a major permit.

Sources & Official References

Other rules in Bloomfield

All Bloomfield rules

Compare Bloomfield to another location·View the New Jersey environmental rules overview

Get notified when Erosion Control in Bloomfield, NJ changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Nearby Cities

How other cities in Essex County handle erosion control.

Newark, NJ
Some Restrictions