Bloomfield, NJ Environmental Rules: Erosion Control (2026)
Key Facts
- No disturbance
- Slopes of 35% or greater
- Transitional grading only
- Slopes of 25.0% to 34.9%
- Steep slope definition
- Slopes in excess of 15% in gradient
- Revegetation plan
- Required when a steep slope is disturbed
- Tree identification
- Caliper of eight inches or more, measured three inches above ground
- Municipal exemption
- Municipally owned properties are exempt
Summary
In Bloomfield Township, New Jersey, § 315-30(Q) bars all soil disturbance on slopes of 35% or greater, limits slopes of 25.0% to 34.9% to transitional grading, and requires a revegetation plan for disturbed steep slopes. The code states the aim as preventing erosion and siltation of streams.
Q. Steep slope. ... (2) Objective. The purpose of this subsection is to minimize cutting and grading of steep slope areas as well as to minimize the disturbance of soil and removal of vegetative cover. Adherence to these regulations will assist in preventing erosion, siltation of streams; and other maintenance and safety problems. ... GRADING LIMITATIONS The extent of the disturbance allowed see chart below. Slopes (percent) Disturbance Allowed 35% or greater No disturbance allowed 25.0% to 34.9% Only transitional grading 15.0% to 24.9% Only transitional grading or road construction 0.0% to 14.9% All construction allowed ... (5) If any disturbance is planned to a steep slope area or if a steep slope has been disturbed by prior land use such as agriculture, a revegetation plan shall be provided.
Full Breakdown
Bloomfield Township addresses erosion most directly in the steep slope subsection of its design standards, § 315-30(Q), added 3-19-2012 by Ord. No. 12-15. It applies to the disturbance of soil and the construction of structures, roads, retaining walls and parking lots in areas of steep slopes, and municipally owned properties are exempt. The stated objective is to minimize cutting and grading of steep slope areas and the disturbance of soil and removal of vegetative cover, which the code says assists in preventing erosion and siltation of streams.
The grading limitations chart sets the allowed disturbance by slope: 35% or greater, no disturbance allowed; 25.0% to 34.9%, only transitional grading; 15.0% to 24.9%, only transitional grading or road construction; 0.0% to 14.9%, all construction allowed. Steep slope includes slopes in excess of 15% in gradient, measured by two-foot contours in a thirty-foot horizontal length.
An applicant must submit a steep slope analysis on a plot plan showing the slope classes with square footage in each, a lot grading plan, retaining wall details, and the limits of clearing and disturbance, which are held to be the maximum permitted on the site. A landscaping plan must identify trees with a caliper of eight inches or more measured three inches above ground level and show which are to be removed. If any disturbance is planned to a steep slope, or a steep slope was disturbed by prior land use such as agriculture, a revegetation plan must be provided. Relief goes to the Zoning Board of Adjustments, and existing structures are exempt while maintained in good order.
Two other chapters add erosion standards. Section 494-3(A)(1) sets the minimum standards for erosion control for major development stormwater measures by the Soil and Sediment Control Act, N.J.S.A. 4:24-39 et seq., and N.J.A.C. 2:90. Section 484-13(B) bars soil moving that increases the velocity or changes the direction of surface water runoff without on-site management.
Violations & Fines
Disturbing soil on a slope of 35% or greater, grading beyond the limits allowed for the slope class, or skipping the required revegetation plan violates § 315-30(Q). The Zoning Officer or Construction Official can issue stop-work orders and withhold permits under § 315-53, the Municipal Judge decides penalties, and § 1-15 sets a fine not exceeding $2,000, imprisonment up to 90 days or community service up to 90 days, with each day a separate offense.
Frequently Asked Questions
Can I regrade a steep slope on my Bloomfield Township lot?
How does Bloomfield measure a steep slope?
What plans does the Township require before disturbing a steep slope?
Where do stormwater erosion standards come from in Bloomfield?
Sources & Official References
Other rules in Bloomfield
Compare Bloomfield to another location·View the New Jersey environmental rules overview