Bothell, WA Environmental Rules: Erosion Control (2026)
Key Facts
- Core requirement
- City-approved erosion and sedimentation control plan for all grading
- Grading permit trigger
- 50 cubic yards or more of earth, or four feet or more of grade change
- Wet season
- October 1 through April 30
- Seasonal plan deadline
- September 15 each year, when the director requires it
- Engineer stamp
- Required for more than 5,000 cubic yards of fill or excavation
- Permit duration
- Expires two years from the date of issuance
Summary
In the City of Bothell, Washington, every grading activity must follow a city-approved erosion and sedimentation control plan and the Storm Water and Drainage Control Code. The public works director can stop work for inadequate controls and can require seasonal plans for the October 1 through April 30 wet season, due by September 15.
All grading activities shall be required to comply with the city of Bothell Design and Construction Standards as adopted within BMC 18.02.010, including the thresholds, definitions, and minimum requirements found within the King County Surface Water Design Manual. A. All grading activities shall be in accordance with a city-approved erosion and sedimentation control plan, as well as the provisions of Chapter 18.04 BMC, Storm Water and Drainage Control Code. ... C. The director may require additional controls or modified minimum requirements for specific projects or areas based on specific site conditions, identified capacity limitations, significant erosion potential, landslide hazards, impacts to critical areas, or seasonal factors as identified within the Bothell Design and Construction Standards.
Full Breakdown
Bothell Municipal Code § 18.05.090 is the surface water rule for grading chapter 18.05. All grading must meet the Bothell Design and Construction Standards, including the thresholds and minimum requirements of the King County Surface Water Design Manual, and must follow a city-approved erosion and sedimentation control plan. The director can add controls for specific sites based on site conditions, capacity limitations, significant erosion potential, landslide hazards, impacts to critical areas, or seasonal factors.
The permit trigger is in BMC 18.05.040: moving 50 cubic yards or more of earth, any grading in a critical area or buffer or in shoreline jurisdiction, any grade change of four feet or more, and grading in public rights-of-way or easements. Under BMC 18.05.050, even grading below those thresholds must install and maintain sediment and erosion control and pollution prevention best management practices. A grading permit application must include a temporary erosion and sedimentation control plan (TESCP), a drainage report, a storm water and drainage control plan, a surface water pollution prevention plan (SWPPP), and a street cleaning schedule covering the entire construction schedule. Plans involving more than 5,000 cubic yards of fill or excavation must be stamped by a Washington State licensed civil engineer (BMC 18.05.080). Pregrading before approvals is prohibited (BMC 18.05.060).
Slopes must be stabilized after cut or excavation operations cease, and cut surfaces cannot be steeper than one unit vertical to three units horizontal, or a 33 percent slope, without director approval (BMC 18.05.100). Under BMC 18.05.150 the director can suspend work during inclement weather or the entire wet season, can order work stopped outside the wet season for inadequate temporary controls, and lifts the order once a revised plan is approved and implemented. Grading permits expire two years from issuance (BMC 18.05.130).
Violations & Fines
BMC 18.05.140 makes any violation unlawful and subjects violators to the civil and criminal penalties of Chapter 11.20 BMC, with each day a separate violation, plus a reinspection fee. Section 11.20.010 sets a maximum civil penalty of $250.00 per day. The director can issue correction orders, stop work orders, suspend or revoke the permit (BMC 18.05.170), and require removal or restoration of noncompliant work to as near preproject condition as possible (BMC 18.05.180).
Frequently Asked Questions
When does grading in the City of Bothell need a permit?
What erosion plans go with the permit application?
Can the city shut down my site for erosion problems?
Do small projects below the permit threshold need erosion control?
Sources & Official References
Other rules in Bothell
Compare Bothell to another location·View the Washington environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Erosion Control in Nearby Cities
How other cities in King County handle erosion control.