Broomfield, CO Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Trigger threshold
1 acre or more disturbed
Required permit
CDPS/NPDES stormwater permit
BMP duration
Maintained indefinitely
Stated purpose
Reduce siltation, streambank erosion
Noncompliance consequence
Permit denial
Max fine
$2,650.00/violation/day

Summary

Broomfield has no standalone erosion ordinance; it controls construction-site erosion and siltation through its stormwater chapter. Sites disturbing an acre or more must hold a CDPS/NPDES construction stormwater permit and, once built, install and maintain permanent water-quality control measures.

(C)To minimize increases in stormwater runoff from any development in order to reduce flooding, siltation, and streambank erosion, and maintain the integrity of stream channels; ... Any person subject to an industrial or construction activity CDPS/NPDES stormwater discharge permit shall comply with all provisions of such permit, the city's Standards and Specifications, and this chapter. ... It is hereby required that the property owners of all construction or redevelopment projects that disturb an area greater than or equal to one acre, including projects less than one acre that are part of a larger common plan of development or sale, must design, construct, install, perform inspections on and maintain indefinitely permanent Control Measures/BMP units or systems that prevent or minimize water quality impacts.

Full Breakdown

Broomfield does not maintain a separate erosion-and-sediment-control chapter; it addresses construction-site erosion inside chapter 13-40, the Stormwater Regulations. The chapter's stated purpose includes minimizing increases in runoff from development 'in order to reduce flooding, siltation, and streambank erosion, and maintain the integrity of stream channels' (13-40-010(C)). 'Construction activity' is defined as any project disturbing one acre or more, or a smaller phase of a larger common plan of development, and covers clearing, grubbing, grading, excavating and demolition (13-40-020(G)). Any person doing construction work under a CDPS/NPDES stormwater discharge permit must comply with every term of that permit, the city's Standards and Specifications for Public Improvements, and this chapter, and the city can demand proof of compliance before allowing discharges (13-40-080).

Building or grading permits can be refused to anyone out of compliance with the chapter (13-40-160). After construction, qualifying projects disturbing an acre or more must design, construct, install, inspect and permanently maintain Control Measure/BMP units that prevent or minimize water-quality impacts, with narrow carve-outs for routine pavement resurfacing, small roadway widenings, and utility work that does not alter drainage patterns (13-40-120). Owners must document BMP inspections and keep the public works department updated on the responsible contact.

Violations & Fines

Failing to hold or comply with a required CDPS/NPDES construction stormwater permit, or to install and maintain the required permanent Control Measure/BMP units, can result in denial of a grading or building permit, an administrative fine of up to $2,650.00 per violation per day, and, if the site is left as a public nuisance, city abatement with the cost charged back to the property owner.

Frequently Asked Questions

Does Broomfield have a separate erosion control ordinance?
No. Erosion and siltation from construction are regulated through the stormwater regulations chapter, 13-40, B.M.C., whose stated purpose includes reducing flooding, siltation, and streambank erosion from development.
What size construction project triggers Broomfield's stormwater erosion rules?
One acre or more of land disturbance, or a smaller phase of a larger common plan of development or sale, as defined in section 13-40-020(G) of the Broomfield Municipal Code.
What must a builder do about erosion once construction is finished?
Qualifying projects must design, construct, install, inspect and permanently maintain Control Measure or best-management-practice units that prevent or minimize water-quality impacts, under section 13-40-120, with limited exclusions for minor pavement or utility work.
What happens if a Broomfield builder skips required erosion controls?
The city can deny or revoke a grading or building permit, assess an administrative fine of up to $2,650.00 per violation per day, and treat the noncompliant site as a public nuisance subject to abatement at the owner's expense.

Sources & Official References

Other rules in Broomfield

All Broomfield rules

Compare Broomfield to another location·View the Colorado environmental rules overview

Get notified when Erosion Control in Broomfield, CO changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.