Conway, AR Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Minimum site grade
2 percent toward drainage
Stabilization deadline
Within 14 days of work stopping
Stockpile setback
25 feet from roadway/drainage way
Inspection frequency
Weekly and after every rainfall
Cleanup deadline after runoff event
24 hours
Penalty
$100-$500 fine per day, misdemeanor

Summary

In the City of Conway, Arkansas, every permitted construction site, including single-family builds, must keep erosion and sediment controls in place until the site is stabilized and a Certificate of Occupancy issues. Sites must grade to at least a 2 percent slope toward drainage infrastructure, and disturbed soil left idle 14 days must be stabilized.

A.Project Site Responsibility. Site responsibility shall be handled in accordance with section 10.50.03(c). In addition, the construction contractor shall be responsible for ensuring erosion and sediment control measures are implemented and maintained until the site is stabilized and a Certificate of Occupancy (CO) is issued. This responsibility includes preventing adverse impacts from storm water flowing onto adjacent property by ensuring the construction site is sloped at a minimum grade of two (2%) percent to direct storm water to either the curb & gutter or other drainage infrastructure located within either street right of way or a drainage easement as shown on the development's Final Plat. ... 3.Stabilization measures shall be initiated within fourteen (14) days in portions of the site where construction activities have ceased, including uncovered stockpiles of soil. Stockpiles shall be located a minimum of twenty-five (25) feet from a roadway or drainage way.

Full Breakdown

Conway Municipal Code § 10.50.05 makes the construction contractor responsible for implementing and maintaining erosion and sediment control measures from the start of a permitted project until the site is stabilized and a Certificate of Occupancy is issued, then shifts that duty to the property owner afterward. Sites must be graded to a minimum 2 percent slope to direct storm water to curb-and-gutter or other drainage infrastructure in the right-of-way or a recorded drainage easement. Required best management practices, detailed in the City of Conway Standard Details for Roadway & Drainage Construction, cover perimeter erosion and sediment control, curb and inlet protection, construction entrance/exit stabilization, concrete truck wash areas, dirt and topsoil storage, dust control and general good housekeeping.

Stabilization measures must begin within 14 days wherever construction activity has stopped, including on uncovered soil stockpiles, and stockpiles must sit at least 25 feet from any roadway or drainage way. Clearing cannot begin until sediment control devices are installed and stabilized, and a Certificate of Occupancy or Certificate of Compliance cannot issue until disturbed surfaces are permanently stabilized with seeding, paving or another approved measure. Sites must be inspected weekly and after every rainfall event, plus at listed construction milestones.

Violations & Fines

Observation of muddy water leaving a construction site is itself treated as a violation under § 10.50.05(C). Tracking mud onto adjacent streets, allowing sediments into waterways or storm drains, and failing to implement dust control or BMP measures are listed under § 10.50.07 as violations subject to immediate penalty without a warning or Cease-and-Desist Order first. Violators are guilty of a misdemeanor punishable by a fine of $100.00 to $500.00 per offense, with each day of continued violation a separate offense, and the responsible party must remove any sediment carried onto adjacent property within 24 hours.

Frequently Asked Questions

How steep must a Conway construction site be graded?
Section 10.50.05(A) requires at least a 2 percent grade directing storm water to the curb and gutter or other drainage infrastructure within the street right-of-way or a recorded drainage easement shown on the final plat.
How long can disturbed soil sit before it must be stabilized?
Stabilization measures, including on stockpiled soil, must begin within 14 days of construction activity stopping in that part of the site, per § 10.50.05(B)(3).
Is muddy runoff from a job site automatically a violation?
Yes. Observation of muddy water leaving a construction site is treated as a violation of Chapter 10.50, and the responsible party must remove tracked sediment from adjacent property within 24 hours.

Sources & Official References

Other rules in Conway

All Conway rules

Compare Conway to another location·View the Arkansas environmental rules overview

Get notified when Erosion Control in Conway, AR changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.