Conway, AR Environmental Rules: Flood Zones (2026)
FEMA flood zone rules in Conway, AR, also called floodplain regulations or special flood hazard area (SFHA) rules, determine flood insurance requirements and elevation standards for new construction.
Key Facts
- Permit required
- Floodplain Development Permit
- Issued in lieu of
- The standard Grading Permit
- Governing ordinance
- City of Conway Ordinance O-09-15
- May also require
- Development Review or Building Permit
- Penalty for noncompliance
- $100-$500 fine per day
Summary
In the City of Conway, Arkansas, land-altering work on any site inside a designated floodplain needs a Floodplain Development Permit instead of the standard Grading Permit. The permit and review process runs under the city's separate floodplain ordinance, O-09-15, and the property may also need Development Review or a Building Permit.
D.City-Issued Permits. The specific city-issued permit applicable to the type of land altering activity and/or project site location are as follows. ... 4.Floodplain Development Permit—Required for land altering activity on sites located within a designated floodplain. The permit and review processes are governed by City of Conway Ordinance O-09-15. (Issued in lieu of the Grading Permit, sites may additionally be subject to separate permitting requirements such as Development Review or Building Permits).
Full Breakdown
Conway Municipal Code § 10.50.03(D)(4) sets a Floodplain Development Permit as one of four city-issued permit tracks under the stormwater management chapter, required whenever clearing, grading, excavation or other land-altering activity is proposed on a site within a designated floodplain. It is issued in lieu of the general Grading Permit that otherwise applies to sites over one acre, but the code notes the property may still face separate permitting requirements, such as Development Review or a Building Permit, on top of the floodplain permit itself.
The permit and review process for floodplain sites is governed by a dedicated floodplain ordinance, City of Conway Ordinance No. O-09-15, adopted separately from Chapter 10.50. The chapter's underlying findings, adopted by Ord. No. O-20-78 on December 8, 2020, note that increased impervious surface from site development raises peak storm water discharges and can worsen downstream flooding during rainfall events, which is the policy basis for requiring floodplain review before ground-disturbing work begins on flood-prone parcels within city limits.
Violations & Fines
The floodplain permit falls under the same enforcement scheme as the rest of Chapter 10.50: the code enforcement officer, building official and city engineer administer it, and the building official may withhold final inspection approval on a non-compliant property. A person who proceeds with land-altering work in a floodplain without the required permit is guilty of a misdemeanor and faces a fine of $100.00 to $500.00 for each day the violation continues.
Frequently Asked Questions
Do I need a special permit to build in a Conway floodplain?
What ordinance governs the Conway floodplain permit process?
Can I still need other permits besides the floodplain permit?
Sources & Official References
Other rules in Conway
Compare Conway to another location·View the Arkansas environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.