Conway, AR Environmental Rules: Stormwater Management (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Grading Permit threshold
Required for sites over 1 acre
SWPPP required
All sites 1 acre or larger (ADEQ)
NOI required
Sites larger than 5 acres
Application review time
30 days for Grading/Floodplain permits
Penalty
$100-$500 fine per day, misdemeanor
Enacted by
Ord. No. O-20-78, 12-8-2020

Summary

In the City of Conway, Arkansas, any clearing, grading, excavation or land-altering activity that disturbs bare soil, changes slope contours or reroutes drainage must have a city-issued permit before work starts. A Grading Permit covers any site over one acre; subdivisions and residential builds use separate permit tracks instead.

A.Applicability. Any clearing, grading, excavation, development, or other land altering activity that may result in any of the following impacts shall have been issued one (1) of the city-issued permits described in subsection (d) of this section prior to the start of the activity.1.Disturbance of the ground surface layer exposing bare soil to the effects of erosion and allowing transport of sediments off-site to enter the storm drain system;2.Changing the contouring and/or any other slope characteristics of the land;3.Stopping, constricting, or rerouting the natural flow of water to, through or from any parcel of property. ... D.City-Issued Permits. The specific city-issued permit applicable to the type of land altering activity and/or project site location are as follows.1.Grading Permit—Required for any site over one (1) acre in size where land altering activities occur unless one of the other city-issued permits below applies.

Full Breakdown

Conway Municipal Code Chapter 10.50 requires a city-issued permit before any clearing, grading, excavation, development or other land-altering activity that disturbs bare soil, changes land contours, or stops or reroutes natural drainage. Section 10.50.03 lists four permit tracks: a Grading Permit for any site over one acre, a Site Development Permit for subdivisions needing preliminary plat approval or projects subject to Development Review, a Residential Building Permit for single- or two-family construction, and a Floodplain Development Permit for sites in designated flood areas. Sites of one acre or larger must also carry an Arkansas Department of Environmental Quality Storm Water Pollution Prevention Plan (SWPPP), with a Notice of Coverage required between one and five acres and a Notice of Intent required above five acres.

The property owner and any contractor share responsibility for obtaining the correct permit and maintaining erosion and sediment controls throughout construction. The city engineer or designee must act on a complete Grading Permit or Floodplain Development Permit application within thirty days, approving, conditionally approving or denying it in writing. The chapter was enacted by Ord. No. O-20-78 on December 8, 2020.

Violations & Fines

Enforcement runs through the code enforcement officer, the building official and the city engineer under the mayor's administrative policies. The building official may refuse final inspection approval on any property still in violation of Chapter 10.50. Violators are guilty of a misdemeanor and face a fine of not less than $100.00 nor more than $500.00 per offense, with each day of continued violation counted as a separate offense; violators also bear the cost of any required site restoration.

Frequently Asked Questions

Do I need a permit to grade my land in Conway?
Yes, if the site is over one acre, you need a Grading Permit under Conway Municipal Code § 10.50.03 before starting. Smaller residential lots may instead be covered by the Residential Building Permit process, which requires an Erosion Control Compliance Certification.
What triggers an ADEQ stormwater permit in Conway?
Any construction site of one acre or larger needs a Storm Water Pollution Prevention Plan. Sites between one and five acres get an automatic Notice of Coverage; sites over five acres must submit a Notice of Intent to ADEQ along with a fee.
What happens if I skip the required city permit?
You are guilty of a misdemeanor under § 10.50.07, punishable by a fine between $100.00 and $500.00 for each day the violation continues, and you must still pay to restore the site to compliance.

Sources & Official References

Other rules in Conway

All Conway rules

Compare Conway to another location·View the Arkansas environmental rules overview

Get notified when Stormwater Management in Conway, AR changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.