Georgetown, TX Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

1+ acre disturbed
Full SWPPP required (EPA/TCEQ/TPDES)
Under 1 acre
Site erosion & sedimentation control plan
Single-family homes
Site-specific plan required, no acreage floor
Approval gate
City Engineer must approve before permit/construction
Redevelopment exemption
Unless >1/4 acre pervious-to-impervious conversion
Standard fine
Up to $500 per violation per day

Summary

Georgetown requires a Storm Water Pollution Prevention Plan (SWPPP) for any construction disturbing an acre or more, and a site-specific erosion and sedimentation control plan for smaller sites, including single-lot, single-family homes. No building permit or subdivision construction plan can be approved until the City Engineer signs off on the plan.

An SWPPP is currently required by EPA and TCEQ for all construction activities where one or more acres will be disturbed during development. Developments of sites that disturb one acre or more within City jurisdiction shall prepare a SWPPP that satisfies EPA, TCEQ regulations, the NPDES or TPDES construction general permit, and this chapter. No construction activities may begin until the SWPPP is approved by the City Engineer or designee. ... (2)If the site is one acre or more, but less than one acre will be disturbed, an erosion and sedimentation control plan is required. ... An erosion and sedimentation control plan is not required when a portion of a previously developed tract of land is redeveloped, unless the redevelopment will result in the conversion of more than ¼ acre from a porous surface to an impervious surface.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 32 | Unified Development Code: Supplement 15).

Full Breakdown

Sec. 080 of the Georgetown Code of Ordinances sets the construction-phase erosion and sediment control rules under the City's MS4 chapter. For sites disturbing one acre or more, state and federal rules already require an SWPPP, and Georgetown requires the developer to submit that SWPPP, satisfying EPA and TCEQ regulations and the NPDES or TPDES construction general permit, at the time subdivision construction plans, a site development application, or a building permit application is filed; no work can start until the City Engineer or a designee approves it, and copies of any Notice of Intent and Notice of Termination filed with EPA or TCEQ must also go to the City Engineer.

Where the site is at least an acre but less than an acre will actually be disturbed, the code calls instead for an erosion and sedimentation control plan. For commercial, industrial, multifamily and subdivision development under one acre, and for single-lot single-family construction, a site-specific erosion and sedimentation control plan is likewise required before a building permit or development approval issues. The plan's pollution-control measures, such as treating wash water in a sediment basin and shielding building materials and chemicals from rain, must be built and inspected during normal construction inspections.

A Certificate of Completion, Certificate of Occupancy, or City acceptance of public improvements can be withheld until the Chief Building Official confirms every temporary and permanent measure in the plan is in place. Redevelopment of a previously developed tract is exempt from needing a new plan unless it converts more than one-quarter acre from pervious to impervious surface. Special land uses such as fueling stations, vehicle washing facilities and outdoor storage of erodible materials must additionally identify best management practices from the City's Construction Specifications and Standards.

Violations & Fines

Failing to obtain or follow an approved erosion and sedimentation control plan or SWPPP is enforced as a Chapter 13.30 violation: a strict-liability offense punishable by up to $500 per violation per day (Sec. 13.30.230(a)), rising to $2,000 per violation per day if committed intentionally, knowingly, recklessly or negligently. The City can also withhold the building permit, Certificate of Occupancy, or Certificate of Completion, issue a stop work order, or pursue civil nuisance abatement until the plan's measures are in place.

Frequently Asked Questions

Do I need an erosion control plan to build a single house in Georgetown?
Yes. Sec. 13.30.080(b)(3) requires a site-specific erosion and sedimentation control plan for single-lot, single-family residential construction regardless of how small the lot is, and it must be approved before a building permit issues.
What triggers a full SWPPP instead of a simple erosion control plan in Georgetown?
Disturbing one acre or more of land. Sec. 13.30.080(a)(1) requires an SWPPP meeting EPA, TCEQ and TPDES construction general permit standards for sites at that threshold, submitted with subdivision plans, site development applications, or the building permit.
Can I skip the erosion control plan if I'm just redeveloping an existing lot in Georgetown?
Only if the redevelopment converts one-quarter acre or less from a porous to an impervious surface. Convert more than that and a new plan is required under Sec. 13.30.080(b)(5).
What happens if I start grading in Georgetown without an approved plan?
The City can issue a stop work order, withhold your Certificate of Occupancy or Completion, and prosecute the omission as a Chapter 13.30 violation carrying fines up to $500 per day, or $2,000 per day if done knowingly, under Sec. 13.30.230.

Sources & Official References

Other rules in Georgetown

All Georgetown rules

Texas rules heatmap·Compare Georgetown to another location·View the Texas environmental rules overview

Get notified when Erosion Control in Georgetown, TX changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.