Key Facts

Residential freeboard
12 inches above base flood elevation
Nonresidential option
elevate 12 inches or floodproof and certify
Enclosure vent ratio
1 sq in per sq ft of enclosed area
Certifying party
registered engineer, architect, or surveyor
Enforcing official
Floodplain Administrator (Inspection Services)
Governing chapter
City Code Chapter 15.44, Article V

Summary

Georgetown requires new and substantially improved residential structures in special flood hazard areas to elevate the lowest floor at least 12 inches above base flood elevation. Nonresidential buildings must either meet that same elevation or be fully floodproofed and certified by a licensed engineer or architect.

Residential Construction. New construction and substantial improvement of any residential structure shall have the lowest floor (including basement), elevated at least 12 inches above the base flood elevation. A registered professional engineer, architect, or land surveyor shall submit a certification to the Floodplain Administrator that the standard of this subsection as proposed in Section 15.44.130 A.1., is satisfied.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 32 | Unified Development Code: Supplement 15).

Full Breakdown

City Code Sec. 160 sets the specific construction standards that apply once base flood elevation data exists for a site. Under Subsection A, new construction and substantial improvement of any residential structure must have the lowest floor, including any basement, elevated at least 12 inches above the base flood elevation, and a registered professional engineer, architect, or land surveyor must certify that standard to the Floodplain Administrator. Subsection B gives commercial, industrial, and other nonresidential buildings a choice: elevate the lowest floor the same 12 inches, or floodproof the structure below that level so walls are substantially impermeable and can resist hydrostatic and hydrodynamic loads, with a licensed engineer or architect certifying the design and the specific elevation to which the building is floodproofed.

Enclosures below the lowest floor used only for parking, access, or storage must equalize hydrostatic pressure through at least two openings on separate walls totaling one square inch of net area per square foot of enclosed space, with opening bottoms no higher than one foot above grade (Subsection C). Manufactured homes placed on sites in flood zones A1-30, AH, and AE must likewise be elevated on a permanent foundation so the lowest floor sits at least 12 inches above base flood elevation and is anchored against flotation, collapse, and lateral movement (Subsection D).

The Floodplain Administrator, a role held by the Director/Building Official of Inspection Services under Sec. 110, reviews and maintains the elevation certifications required under this section as part of the development permit process established in Sec. 050.

Violations & Fines

Building without the required elevation certification, or below the 12-inch freeboard standard, exposes an owner to enforcement under Sec. 15.44.070: the Floodplain Administrator can order an illegally located structure or fill removed from the floodplain at the owner's expense within a stated deadline. Failure to comply is a misdemeanor subject to the general penalty in Section 1.08, and the City may remove the obstruction itself and bill the owner, placing a lien on the property if payment is not made.

Frequently Asked Questions

How high above base flood elevation must a Georgetown home be built?
New construction and substantial improvements of residential structures must have the lowest floor, including any basement, elevated at least 12 inches above the base flood elevation under Sec. 15.44.160 A. A registered engineer, architect, or land surveyor must certify the elevation to the Floodplain Administrator before the permit is finalized.
Can a commercial building in Georgetown skip elevating and floodproof instead?
Yes. Sec. 15.44.160 B lets nonresidential structures either elevate the lowest floor 12 inches above base flood elevation or be designed watertight below that level, with walls able to resist hydrostatic and hydrodynamic loads. A licensed engineer or architect must certify the floodproofing design and record the certified elevation.
What happens if a structure is built below the required elevation?
Sec. 15.44.070 authorizes the Floodplain Administrator to require removal of an illegally located structure or fill at the owner's expense within a set deadline. Noncompliance is a misdemeanor under the Section 1.08 general penalty, and the City can remove the violation itself and lien the property for the cost.

Sources & Official References

Other rules in Georgetown

All Georgetown rules

Texas rules heatmap·Compare Georgetown to another location·View the Texas environmental rules overview

Get notified when Flood Elevation Requirements in Georgetown, TX changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.