Key Facts

Governing manual
Austin Drainage Criteria Manual, as amended
Survey interval
1-foot vertical contour intervals
Alternative control
mulch tubes may replace silt fencing
Applies to
non single/two-family site development plans
Plan reviewer
City Engineer
One-time extension
automatic 12-month extension available

Summary

In the City of Kyle, a site development plan for any land not undergoing single- or two-family residential use must include an erosion and sedimentation control plan under City Code § 32-45(3). All temporary and permanent erosion and sediment controls in the city must follow the Austin Drainage Criteria Manual, as amended.

(3) Erosion and sedimentation control plan.An erosion and sedimentation control plan, showing the following: a. Proposed fill or other structure elevating techniques, levees, channel modifications and detention facilities. ... ... c. The location, size, and character of all temporary and permanent erosion and sediment controls with specifications detailing all on-site erosion control measures which will be established and maintained during all periods of development and construction. Specifications should include a provision for the use of mulch tubes in place of wire silt fencing in areas deemed by city engineer to be high runoff or environmentally sensitive. This provision will not require the exclusive use of mulch tubes as an erosion control measure within the site area. ... ... f. All temporary and permanent erosion and sedimentation controls within the city shall be designed in accordance with the Austin Drainage Criteria Manual, as amended.

Full Breakdown

The erosion and sedimentation control plan must show proposed fill or other elevating techniques, levees, channel modifications and detention facilities, plus existing and proposed topography surveyed at vertical intervals no greater than one foot and tied to a USGS or Coastal and Geodetic Survey benchmark (§ 32-45(3)a, b). It must detail the location, size and character of every temporary and permanent erosion and sediment control that will be built and maintained throughout construction, and the city engineer may require mulch tubes instead of wire silt fencing in areas found to be high-runoff or environmentally sensitive, though mulch tubes are not mandated citywide (§ 32-45(3)c).

The plan must also identify contractor staging areas, vehicle access areas, and temporary and permanent spoils storage, along with a restoration plan to mitigate erosion in any area disturbed during construction (§ 32-45(3)d, e). Every temporary and permanent control must ultimately be designed to the Austin Drainage Criteria Manual, adopted by reference with the City of Kyle substituted for the City of Austin's departments and specific paragraphs excluded (§ 32-45(3)f, (5)f). This erosion control plan is only one part of the larger site development plan required for any lot zoned other than single- or two-family residential, or intended for a use other than single- or two-family residential occupancy (§ 32-42), and if conditions change after approval, the plan must be resubmitted and approved again by city staff before work continues (§ 32-50).

Violations & Fines

A site development plan, including its erosion and sedimentation control plan, must be reviewed and approved before grading or construction begins on a qualifying lot (§ 32-42, § 32-45). If site conditions change, the developer must resubmit the revised plan for city staff approval before proceeding (§ 32-50), and an approved plan nearing expiration may be extended only once, automatically, for 12 months if the developer requests it before the lapse (§ 32-51).

Frequently Asked Questions

Who has to file an erosion control plan in Kyle?
Anyone developing or improving a lot that is zoned other than single- or two-family residential, or intended for a use other than single- or two-family residential occupancy, must submit a full site development plan that includes an erosion and sedimentation control plan under § 32-45(3).
What standard does Kyle use for erosion control design?
All temporary and permanent erosion and sediment controls must be designed according to the Austin Drainage Criteria Manual, as amended, which the city has adopted by reference with the City of Kyle substituted wherever the manual refers to City of Austin departments or divisions.
Can silt fencing be replaced with something else on a Kyle construction site?
Yes, in some cases. The city engineer can require mulch tubes instead of wire silt fencing in areas identified as high-runoff or environmentally sensitive, though the code does not require mulch tubes across every site.

Sources & Official References

Other rules in Kyle

All Kyle rules

Texas rules heatmap·Compare Kyle to another location·View the Texas environmental rules overview

Get notified when Erosion Control in Kyle, TX changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.