Lake Havasu City, AZ Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

SWPPP threshold
Required for construction sites of 1 acre or more
State filing
Notice of Intent filed with ADEQ
Enforcing official
City Engineer under Chapter 8.28
Civil penalty
$200 to $2,500 per day under § 1.12.040
Court remedy
Injunction available in Mohave County Superior Court
Adopted
Ordinance 14-1105, passed January 14, 2014

Summary

Lake Havasu City requires stormwater pollution prevention plans for construction projects of one acre or more under Chapter 8.28, Stormwater. Builders must file a Notice of Intent with the Arizona Department of Environmental Quality, use Best Management Practices to stop illicit discharges into the municipal storm sewer system, and maintain those BMPs until the site is fully stabilized.

B. The city shall require that any person submitting a grading, building, or other improvement plan disclose if illicit discharge, stormwater, or permitted non-stormwater discharge of any type to the MS4 may occur as a result of, or in conjunction with the implementation of the plan. To the extent that the discharge would be an illicit discharge, if connected to the MS4, the plan shall include BMP measures to remove or prevent the illicit discharge during and after construction of the improvement or project. The BMP shall be subject to approval of the city. ... ... F. Site-specific stormwater pollution prevention plans shall be developed for all construction projects 1 acre or greater in size and a Notice of Intent (NOI) shall be filed with ADEQ. The site-specific plan shall identify the minimum BMPs to be utilized upon further development of the project area, when the person submitting the plan will not develop the entire project though building occupancy or other full development intent. Smaller areas may develop a site-specific plan.

Full Breakdown

Chapter 8.28, Stormwater, adopted by Ordinance 14-1105 in 2014, regulates erosion and sediment control on construction sites to protect the city's municipal separate storm sewer system (MS4) and comply with the federal Clean Water Act and Arizona Pollutant Discharge Elimination System rules. Under § 8.28.100, anyone submitting a grading, building or other improvement plan must disclose whether an illicit discharge, stormwater or permitted non-stormwater discharge to the MS4 could occur, and the plan must include city-approved Best Management Practices (BMPs) to remove or prevent that discharge during and after construction.

Those BMPs must be maintained by the person initiating the project, and by their heirs and assigns, until the site reaches final stabilization; any change to an approved BMP must be reported to the city in writing. For construction projects covering one acre or more, § 8.28.100.F requires a site-specific Stormwater Pollution Prevention Plan identifying the minimum BMPs to be used, and a Notice of Intent must be filed with the Arizona Department of Environmental Quality; smaller sites may develop a site-specific plan voluntarily. Developers who continue work on parcels that were part of a larger prior development must keep using BMPs at least as protective as those in the original project's plan.

The city may suspend a site's MS4 access without prior notice if a discharge presents an imminent danger under § 8.28.110, and industrial or construction activity subject to an AZPDES or NPDES permit must prove compliance with that permit under § 8.28.120.

Violations & Fines

A stormwater or erosion-control violation is enforced under Chapter 1.12 of the code by the City Engineer or a designee, per § 8.28.160, and carries a civil citation of not less than $200 nor more than $2,500 per day under § 1.12.040. The city may also petition the Mohave County Superior Court for an injunction under § 8.28.170, and a violation that threatens public health or safety can be declared a public nuisance and abated at the violator's expense under § 8.28.180.

Frequently Asked Questions

Do construction sites in Lake Havasu City need an erosion control plan?
Yes. Any grading, building or improvement plan must disclose potential illicit discharges to the storm sewer system and include city-approved Best Management Practices under § 8.28.100.B. Projects of one acre or more must also prepare a site-specific Stormwater Pollution Prevention Plan and file a Notice of Intent with the Arizona Department of Environmental Quality under § 8.28.100.F.
Who enforces erosion and stormwater rules on a job site?
The City Engineer or a designee enforces Chapter 8.28 under § 8.28.160, applying the civil citation process in Chapter 1.12. The city can also suspend a site's access to the municipal storm sewer system without notice under § 8.28.110 if a discharge poses an imminent danger to the environment or public health.
What is the penalty for violating erosion control requirements?
Violations are punished as civil infractions under § 1.12.040, with fines of not less than $200 nor more than $2,500 for each separate violation per day. The city may also seek an injunction from the Mohave County Superior Court under § 8.28.170 or abate a nuisance-level violation at the violator's expense under § 8.28.180.

Sources & Official References

Other rules in Lake Havasu City

All Lake Havasu City rules

Compare Lake Havasu City to another location·View the Arizona environmental rules overview

Get notified when Erosion Control in Lake Havasu City, AZ changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.