Key Facts

Governing section
Lakeville City Code § 10-4-5
BMP standard
Minnesota Stormwater Manual (MPCA 2005)
State permit referenced
NPDES general construction permit MN R100001
Topsoil restoration depth
Minimum 6 inches
Channel design standard
Withstand 10-year storm without erosion
Disturbance trigger for seeding
Over 1 acre on disturbed soils

Summary

In the City of Lakeville, Minnesota, development must follow erosion and sediment control best management practices under the Minnesota Stormwater Manual and the state NPDES general construction permit, install temporary controls before land disturbance begins, and restore removed topsoil to a minimum depth of six inches.

A. The development shall conform to the natural limitations presented by topography and soil so as to create the least potential for soil erosion. B. Erosion and sediment control measures shall be consistent with best management practices (BMPs) for erosion and sedimentation control as specified in the Minnesota Stormwater Manual (MPCA 2005), as amended, and shall be sufficient to retain sediment on site. ... ... H. All temporary erosion and sediment controls shall be installed on all down gradient perimeters before commencing the land disturbing activity and left in place and maintained until the site has been stabilized.

Full Breakdown

Lakeville City Code section 10-4-5 requires that development conform to natural topography and soil limitations to minimize erosion potential, and that erosion and sediment control measures be consistent with best management practices in the Minnesota Stormwater Manual (MPCA 2005), as amended, sufficient to retain sediment on site. Controls must meet the standards for the state's general NPDES construction stormwater permit (permit MN R100001) issued by the Minnesota Pollution Control Agency, with final site stabilization completed per that permit's requirements. Land must be developed in workable increments so adequate erosion and siltation controls can be maintained as construction progresses, exposing the smallest practical area for the shortest feasible period as specified in the development agreement.

Where topsoil is removed, it must be set aside and restored to a minimum depth of six inches, matching the pre-development soil quality. Natural vegetation must be protected wherever practical, and runoff must be diverted to a sedimentation basin before entering the natural drainage system, with on-site conveyance channels designed to withstand a 10-year storm without erosion. Section 10-4-5.H requires all temporary erosion and sediment controls to be installed on all down-gradient perimeters before land-disturbing activity begins and maintained until the site is stabilized, with permanent controls installed and operational per the approved design.

Section 10-4-5.I adds that disturbances over one acre on previously disturbed sites, such as tilled agricultural land, must seed unstabilized areas with temporary or permanent cover before commencing land disturbance, per NPDES general construction permit part IV.B.5 timeframes.

Violations & Fines

Failure to install required temporary erosion and sediment controls before commencing land-disturbing activity, or to maintain them until stabilization, is a violation of section 10-4-5 enforceable through the city's subdivision development agreement and site plan approval process administered by Planning and Community Development and the City Engineer, in addition to any separate state MPCA enforcement under the NPDES general construction permit.

Frequently Asked Questions

What erosion control standard applies to construction sites in Lakeville?
Section 10-4-5 requires erosion and sediment control measures consistent with best management practices in the Minnesota Stormwater Manual (MPCA 2005) and the state's NPDES general construction stormwater permit (MN R100001) issued by the Minnesota Pollution Control Agency.
When must erosion controls be installed on a Lakeville construction site?
Section 10-4-5.H requires all temporary erosion and sediment controls to be installed on down-gradient perimeters before land-disturbing activity begins, and maintained in place until the site has been stabilized.
How deep must topsoil be restored after grading in Lakeville?
Section 10-4-5.E requires topsoil removed during development to be set aside and restored to a minimum depth of six inches, at a quality at least equal to the pre-development soil.

Sources & Official References

Other rules in Lakeville

All Lakeville rules

Compare Lakeville to another location·View the Minnesota environmental rules overview

Get notified when Erosion Control in Lakeville, MN changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.