Key Facts
- Applies to
- Every construction contractor performing work in the city
- Core requirement
- Filter materials at the catch basin to retain debris
- Additional authority
- City engineer may set runoff volume and rate controls
- Criminal penalty
- Misdemeanor, chargeable as an infraction
- Enforcement access
- Inspections under Sec. 13.45.130, warrant if entry refused
Summary
Livermore requires every construction contractor working in the city to install filter materials at catch basins so job-site debris and dirt cannot reach the storm sewer system. LMC Sec. 13.45.090 also lets the city engineer or water resources manager impose additional controls on runoff volume and rate from new development and redevelopment projects to curb pollutant discharge during and after construction.
Any construction contractor performing work in the City shall provide filter materials at the catch basin to retain any debris and dirt flowing into the City's storm sewer system. The city engineer and/or water resources manager may establish controls on the volume and rate of stormwater runoff from new developments and redevelopments as may be appropriate to minimize the discharge and transport of pollutants.
Full Breakdown
45), targets sediment and debris generated by active construction. Every contractor performing work in the City must place filter materials at the catch basin serving the site to keep debris and dirt out of the municipal storm sewer system defined in Sec. 020 as the network of roads, curbs, gutters, ditches, channels and storm drains that is not part of a treatment works. Beyond the catch-basin filter requirement, the city engineer and the water resources manager have standing authority to set additional controls on the volume and rate of stormwater runoff from new developments and redevelopments, sized to minimize the discharge and transport of pollutants leaving the site.
This construction-phase duty sits inside the chapter's broader scheme: Sec. 060 separately requires anyone whose activity may send pollutants into the storm sewer to take all practicable measures to reduce them, and Sec. 120 requires anyone with a watercourse on their property to keep it free of the trash, debris and excess vegetation that erosion can dislodge, and bars grading or other development within a watercourse setback without a written permit from the water resources manager. Authorized enforcement officials, defined in Sec. 020 as the Public Works Director, the water resources division manager, the source control coordinator and source control inspectors, may inspect a job site under Sec. 130 to confirm filter materials and runoff controls are in place, entering with consent or, if refused, a search warrant.
Violations & Fines
Failing to install catch-basin filter materials or comply with the city engineer's runoff controls violates Chapter 13.45 and is a misdemeanor under Sec. 13.45.170, though it can be charged as an infraction instead. Each day the condition continues is a separate offense. Section 13.45.180 also treats uncontrolled construction runoff as a public nuisance the City may abate at the contractor's or owner's expense, with unpaid costs becoming a lien on the property.
Frequently Asked Questions
Do construction sites in Livermore need erosion control?
Who can add extra runoff conditions to my construction project?
What happens if a construction site sends sediment into the storm drain?
Sources & Official References
Other rules in Livermore
California rules heatmap·Compare Livermore to another location·View the California environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Erosion Control in Nearby Cities
How other cities in Alameda County handle erosion control.