Medford, OR Environmental Rules: Erosion Control (2026)
Key Facts
- Local permit trigger
- 7,000 sq ft of land disturbance
- State DEQ trigger
- 1 acre disturbed (NPDES 1200-C)
- Reviewing agency
- Public Works Engineering Division
- Plan required before
- Any earthwork begins
- Max penalty
- $5,000, or $1,000/day continuing
Summary
Medford requires its own Erosion Control Permit for any construction project disturbing 7,000 square feet or more of land, on top of the state DEQ's NPDES 1200-C permit once disturbance reaches one acre. The Public Works Engineering Division reviews erosion control plans alongside building or grading permit applications under Medford Municipal Code § 9.800.
(1) Purpose. As required by the City's National Pollutant Elimination System (NPDES) Municipal Separate Storm Sewer System (MS4), the City does hereby proclaim an ordinance to address Stormwater Erosion Control. (2) Applicability. A City of Medford Erosion Control Permit is required for all construction projects that result in land disturbance of 7000 square feet or more. For construction projects that disturb one or more acres (or that disturb less than one acre, if part of a "common plan of development or sale" disturbing one or more acres) a NPDES 1200C permit from the Oregon Department of Environmental Quality (DEQ) will also be required.
Official source re-checked September 8, 2026: no newer edition of the code had been published (publisher’s edition: current through Ordinance 2026-32, passed May 6, 2026).
Full Breakdown
800 was adopted to satisfy the City's National Pollutant Discharge Elimination System Municipal Separate Storm Sewer System (NPDES MS4) permit obligations. It sets a local trigger well below the state threshold: any project that disturbs 7,000 square feet or more of land needs a City of Medford Erosion Control Permit, regardless of whether state permitting applies. Projects that disturb one acre or more, or that disturb less than an acre but are part of a larger 'common plan of development or sale' totaling an acre or more, additionally need a NPDES 1200-C permit issued by the Oregon Department of Environmental Quality.
Erosion control plans must be submitted together with the building or grading permit application, using the City's current Erosion Control Plan Template, and the Public Works Engineering Division reviews them and issues the Erosion Control Permit alongside the building or grading permit. The approved plan has to be in place before any earthwork starts and kept current as site conditions change over the life of the project; a copy must stay on site and be available for review by both the City and DEQ. Erosion control measures shown on the approved plan must be installed prior to any earth-disturbing work and maintained continuously through construction, not just at the outset.
Violations & Fines
Starting land-disturbing work without an approved Erosion Control Permit, or failing to install and maintain the erosion control measures shown on the approved plan, is a Chapter 9 building code violation. It is enforced the same way as other Chapter 9 violations under § 9.660: an administrative civil penalty of up to $5,000, or up to $1,000 for each day a continuing violation persists, following a Notice of Civil Violation from the Building Official.
Frequently Asked Questions
Does a small home addition in Medford need an erosion control permit?
Who reviews Medford erosion control plans?
What's the difference between Medford's permit and the state DEQ permit?
Sources & Official References
Other rules in Medford
Compare Medford to another location·View the Oregon environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.