Parsippany-Troy Hills, NJ Environmental Rules: Erosion Control (2026)
Key Facts
- Design standard
- Soil and Sediment Control Act and N.J.A.C. 2:90
- Soil permit trigger
- Five cubic yards of soil or fill on a lot
- Minor permit range
- More than five but less than 100 cubic yards per 12 months
- Application fees
- $20 minor, $400 major
- Work hours
- Not 5:00 p.m. to 8:00 a.m., Sundays, holidays, or Saturday after noon
- Performance guaranty
- $0.10 to $0.50 per cubic yard, minimum $2,000
Summary
In Parsippany-Troy Hills, both major and minor development must be designed for erosion control to the minimum standards of the state Soil and Sediment Control Act and N.J.A.C. 2:90. Moving five cubic yards or more of soil also needs a Township soil moving permit under Chapter 350.
A. Stormwater management measures for major development shall be designed to provide erosion control, groundwater recharge, stormwater runoff quantity control, and stormwater runoff quality treatment as follows: (1) The minimum standards for erosion control are those established under the Soil and Sediment Control Act, N.J.S.A. 4:24-39 et seq., and implementing rules at N.J.A.C. 2:90. ... ... B. Stormwater management measures for minor development shall be designed to provide erosion control and stormwater runoff quantity control, as follows: (1) The minimum standards for erosion control are those established under the Soil and Sediment Control Act, N.J.S.A. 4:24-39 et seq., and implementing rules at N.J.A.C. 2:90.
Full Breakdown
Section 225-96 of the Parsippany-Troy Hills Township Code makes erosion control a design requirement of the stormwater article. Stormwater management measures for major development must provide erosion control, groundwater recharge, runoff quantity control and runoff quality treatment. For minor development they must provide erosion control and runoff quantity control. In both cases the Township adopts as its minimum the standards established under the Soil and Sediment Control Act, N.J.S.A. 4:24-39 et seq., and the implementing rules at N.J.A.C. 2:90. For minor development, § 225-98C(1) adds that soil erosion and sediment control measures are installed in accordance with the Standards for Soil Erosion and Sediment Control in New Jersey. The preliminary subdivision plat checklist also calls for a soil erosion and sedimentation control plan approved by the Morris County Soil Conservation District.
Chapter 350, Soil Removal and Relocation, covers grading itself. Its legislative purpose lists soil erosion by water and wind, inadequate surface water drainage and increased flooding among the harms of uncontrolled soil moving. No one can move five cubic yards of soil or fill on a lot until a soil moving permit is issued. A minor permit covers more than five but less than 100 cubic yards in any 12 consecutive months and is filed with the Township Engineer. The Engineer reclassifies a minor application as major if it presents drainage or erosion problems.
Fees are $20 for a minor application and $400 for a major one, plus $0.15 per cubic yard and engineering and inspection charges of $45 per hour. Permit holders must prevent dust in compliance with the soil erosion and sediment control plan. Work is barred from 5:00 p.m. to 8:00 a.m., on Sundays and legal holidays, and on Saturday after 12:00 noon. Major permits need a performance guaranty of not less than $0.10 nor more than $0.50 per cubic yard, never below $2,000, and it can cover erosion control. Lands under an approved farm plan and foundation or driveway excavation for one single-family house are exempt under § 350-14.
Violations & Fines
Neither § 225-96 nor Chapter 350 prints its own penalty. Section 1-17 of the Township Code sets the maximum where no specific penalty is provided: a fine not exceeding $2,000, imprisonment not exceeding 90 days, or both, or community service not exceeding 90 days. Each day is a separate violation. Under § 350-15 an agent of the Township Engineer's office can enter land to inspect soil moving operations for permit compliance.
Frequently Asked Questions
What erosion control standard applies to construction in Parsippany-Troy Hills?
Do I need a permit to regrade my property in Parsippany-Troy Hills?
What does a soil moving permit cost?
When can soil moving work be done?
Sources & Official References
Other rules in Parsippany-Troy Hills
Compare Parsippany-Troy Hills to another location·View the New Jersey environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.