Parsippany-Troy Hills, NJ Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Design standard
Soil and Sediment Control Act and N.J.A.C. 2:90
Soil permit trigger
Five cubic yards of soil or fill on a lot
Minor permit range
More than five but less than 100 cubic yards per 12 months
Application fees
$20 minor, $400 major
Work hours
Not 5:00 p.m. to 8:00 a.m., Sundays, holidays, or Saturday after noon
Performance guaranty
$0.10 to $0.50 per cubic yard, minimum $2,000

Summary

In Parsippany-Troy Hills, both major and minor development must be designed for erosion control to the minimum standards of the state Soil and Sediment Control Act and N.J.A.C. 2:90. Moving five cubic yards or more of soil also needs a Township soil moving permit under Chapter 350.

A. Stormwater management measures for major development shall be designed to provide erosion control, groundwater recharge, stormwater runoff quantity control, and stormwater runoff quality treatment as follows: (1) The minimum standards for erosion control are those established under the Soil and Sediment Control Act, N.J.S.A. 4:24-39 et seq., and implementing rules at N.J.A.C. 2:90. ... ... B. Stormwater management measures for minor development shall be designed to provide erosion control and stormwater runoff quantity control, as follows: (1) The minimum standards for erosion control are those established under the Soil and Sediment Control Act, N.J.S.A. 4:24-39 et seq., and implementing rules at N.J.A.C. 2:90.

Full Breakdown

Section 225-96 of the Parsippany-Troy Hills Township Code makes erosion control a design requirement of the stormwater article. Stormwater management measures for major development must provide erosion control, groundwater recharge, runoff quantity control and runoff quality treatment. For minor development they must provide erosion control and runoff quantity control. In both cases the Township adopts as its minimum the standards established under the Soil and Sediment Control Act, N.J.S.A. 4:24-39 et seq., and the implementing rules at N.J.A.C. 2:90. For minor development, § 225-98C(1) adds that soil erosion and sediment control measures are installed in accordance with the Standards for Soil Erosion and Sediment Control in New Jersey. The preliminary subdivision plat checklist also calls for a soil erosion and sedimentation control plan approved by the Morris County Soil Conservation District.

Chapter 350, Soil Removal and Relocation, covers grading itself. Its legislative purpose lists soil erosion by water and wind, inadequate surface water drainage and increased flooding among the harms of uncontrolled soil moving. No one can move five cubic yards of soil or fill on a lot until a soil moving permit is issued. A minor permit covers more than five but less than 100 cubic yards in any 12 consecutive months and is filed with the Township Engineer. The Engineer reclassifies a minor application as major if it presents drainage or erosion problems.

Fees are $20 for a minor application and $400 for a major one, plus $0.15 per cubic yard and engineering and inspection charges of $45 per hour. Permit holders must prevent dust in compliance with the soil erosion and sediment control plan. Work is barred from 5:00 p.m. to 8:00 a.m., on Sundays and legal holidays, and on Saturday after 12:00 noon. Major permits need a performance guaranty of not less than $0.10 nor more than $0.50 per cubic yard, never below $2,000, and it can cover erosion control. Lands under an approved farm plan and foundation or driveway excavation for one single-family house are exempt under § 350-14.

Violations & Fines

Neither § 225-96 nor Chapter 350 prints its own penalty. Section 1-17 of the Township Code sets the maximum where no specific penalty is provided: a fine not exceeding $2,000, imprisonment not exceeding 90 days, or both, or community service not exceeding 90 days. Each day is a separate violation. Under § 350-15 an agent of the Township Engineer's office can enter land to inspect soil moving operations for permit compliance.

Frequently Asked Questions

What erosion control standard applies to construction in Parsippany-Troy Hills?
Section 225-96 sets the minimum standards for erosion control as those established under the Soil and Sediment Control Act, N.J.S.A. 4:24-39 et seq., and the implementing rules at N.J.A.C. 2:90. This applies to both major and minor development, and § 225-98C(1) repeats it for minor development.
Do I need a permit to regrade my property in Parsippany-Troy Hills?
Yes, once five cubic yards of soil or fill is moved on a lot, § 350-4 requires a soil moving permit first. Minor permits go to the Township Engineer. Foundation or driveway excavation for one single-family house outside a two-lot-or-more subdivision is exempt under § 350-14B.
What does a soil moving permit cost?
Section 350-7 charges a nonrefundable application fee of $20 for a minor permit or $400 for a major one, a soil moving fee of $0.15 per cubic yard less the application fee, and engineering and inspection fees of $45 per hour. Utilities and public bodies can seek an exemption from the Township Council.
When can soil moving work be done?
Section 350-9D bars soil or fill moving, including loading and unloading, between 5:00 p.m. and 8:00 a.m., on Sundays and legal holidays, and on Saturday after 12:00 noon. A permit lasts no more than one year unless renewal is applied for and approved in writing.

Sources & Official References

Other rules in Parsippany-Troy Hills

All Parsippany-Troy Hills rules

Compare Parsippany-Troy Hills to another location·View the New Jersey environmental rules overview

Get notified when Erosion Control in Parsippany-Troy Hills, NJ changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.