Puyallup, WA Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Permit trigger
Any land-disturbing activity within city limits
Maximum slope
2 feet horizontal to 1 foot vertical, absent engineered exception
Exposure limit
30 working days before ground cover/erosion control required
Floodway fills
Prohibited outright in the regulatory floodway
Archaeological find
Work stops immediately; city, state DAHP and tribes notified

Summary

No one may clear, grade, or fill land in Puyallup without first obtaining a clearing, filling and grading permit and installing erosion controls that keep sediment on site. Slopes are capped at two-to-one and violators face civil infractions plus gross misdemeanor penalties for repeat offenses.

Plan Required. ... No person shall initiate or engage in any land-disturbing activity without having obtained a permit as required by this chapter. All work must be performed in accordance with a sequence shown on the approved plan or a revised sequence approved by the city engineer. ... The maximum surface gradient on any artificially created slope shall be two feet of horizontal run to one foot of vertical fall. ... Fills in the regulatory floodway shall not be permitted.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 4985225; v6 updated 2026-07-21; through 07-21-2026).

Full Breakdown

020, requires a permit before any land-disturbing activity begins. 070 makes the plan requirement mandatory: no person may initiate land-disturbing activity without a permit, work must follow the approved sequence, and a vegetated buffer must confine visible siltation within the 25 percent of the buffer nearest any environmentally sensitive area. Graded slopes and fills may be exposed no longer than 30 working days before ground cover or erosion control devices restrain erosion, and permits are not transferable. 5 factor of safety, and fills are flatly prohibited within the regulatory floodway.

300 bars clearing in any protected area, native growth protection easement, or greenbelt without a permit, and requires the limits of sensitive area setbacks to be fenced before any adjacent clearing begins. The city engineer inspects at defined stages, including installation of sediment control measures, rough grading, and final grading, and can issue a stop-work order without prior warning where land disturbance proceeds without a permit or where required sediment controls are missing. 375 adds a distinct Puyallup River valley obligation: if excavation uncovers suspected historic or cultural artifacts, all work must stop immediately and the developer must notify the city, the State Department of Archaeology and Historic Preservation, the Puyallup Tribe of Indians, and the Muckleshoot Indian Tribe.

Violations & Fines

PMC § 21.14.430 declares any violation of Chapter 21.14 unlawful and directs that a notice of violation be served setting a compliance deadline, with enforcement action following if the deadline is missed; the council has directed that penalties be strictly enforced without suspended sentences except in exceptional circumstances. The city engineer may also revoke or suspend a permit under PMC § 21.14.420 for violating plan conditions or endangering life or property, and can issue an immediate stop-work order where unpermitted land disturbance or missing sediment controls create a hazard.

Frequently Asked Questions

Do I need a permit before clearing or grading land in Puyallup?
Yes. PMC § 21.14.070(1) prohibits any land-disturbing activity without a clearing, filling and grading permit issued under Chapter 21.14, and the work must follow the sequence shown on the approved plan.
How steep can a graded slope be in Puyallup?
PMC § 21.14.310(3) caps artificially created slopes at two feet of horizontal run to one foot of vertical fall, unless the applicant's engineer demonstrates a 1.5 factor of safety for a steeper slope, and fills are never allowed in the regulatory floodway.
What happens if artifacts are found while grading a site?
PMC § 21.14.375 requires all work to stop immediately and the property owner or developer to notify the city, the State Department of Archaeology and Historic Preservation, the Puyallup Tribe of Indians, and the Muckleshoot Indian Tribe before any further excavation.

Sources & Official References

Other rules in Puyallup

All Puyallup rules

Compare Puyallup to another location·View the Washington environmental rules overview

Get notified when Erosion Control in Puyallup, WA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Nearby Cities

How other cities in this county handle erosion control.

Lakewood, WA
Some Restrictions
Tacoma, WA
Some Restrictions