Lakewood, WA Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Trigger
Any clearing, grading or site disturbance
SWPPP required for
Projects meeting Table 12.11-1 thresholds
State permit trigger
Over 1 acre with discharge potential
State permit issuer
Washington Dept. of Ecology
Governing sections
LMC 12.10.040, 12.11.040(B), 12.11.050

Summary

Every Lakewood project that clears, grades or otherwise disturbs a site must use erosion and sediment control best management practices to keep sediment from reaching downstream drainage, water resources and neighboring properties, under LMC 12.10.040. Larger projects must also prepare a construction stormwater pollution prevention plan and, above one acre with discharge potential, a state DOE permit.

12.10.040 Erosion control. ... All proposed projects that will clear, grade, or otherwise disturb a site shall provide erosion and sediment control best management practices (BMPs) to prevent, to the maximum extent possible, the transport of sediment from the project site to downstream drainage facilities, water resources, and adjacent properties. ... 12.11.040 Minimum surface water and storm water requirements. ... ... B. Minimum Requirement No. ... 2 – Construction Storm Water Pollution Prevention. All new development and redevelopment projects are responsible for preventing erosion and discharge of sediment and other pollutants leaving the site. Projects meeting the thresholds described in LMC 12.11.030, Table 12.11-1, shall prepare a construction storm water pollution prevention plan (SWPPP) as part of the storm water site plan. ... In addition, projects greater than one acre that have the potential to discharge to waters of the state, as determined by the City Engineer, shall apply for a construction storm water general permit through the DOE.

View official code

Official source re-checked September 8, 2026: no newer edition of the code had been published (publisher’s edition: current through Ordinance 852, passed June 15, 2026).

Full Breakdown

LMC 12.10.040 requires temporary and permanent erosion and sediment control BMPs on any project that clears, grades or otherwise disturbs a site, designed to prevent, to the maximum extent possible, sediment transport from the project site to downstream drainage facilities, water resources and adjacent properties. LMC 12.11.040(B), Minimum Requirement No. 2 of the City's stormwater code, builds on that duty: every new development and redevelopment project is responsible for preventing erosion and the discharge of sediment or other pollutants leaving the site, and any project meeting the drainage-review thresholds in Table 12.11-1 at LMC 12.11.030 must prepare a construction stormwater pollution prevention plan (SWPPP) as part of its stormwater site plan.

Projects larger than one acre that could discharge to waters of the state, as the City Engineer determines, must also obtain a construction stormwater general permit from the Washington Department of Ecology, with SWPPP guidance available through DOE. LMC 12.11.050 ties the timing to construction sequencing: erosion and sediment control measures for both interim and permanent drainage systems must be built according to the approved plan before any grading or clearing beyond what the erosion control plan itself allows, and they must be maintained until all improvements, restoration and landscaping are complete and the risk of on-site erosion has passed. Recording of short plats and subdivisions cannot occur before drainage facilities, roadways and sidewalks are built and accepted.

Violations & Fines

LMC 12.11.020(D) bars any land-clearing, grading or other construction activity covered by Title 12 from starting or continuing without a valid permit from the Department, and a project's SWPPP must be implemented from initial soil disturbance until final stabilization under LMC 12.11.040(B). A site left without the required BMPs, or an unauthorized DOE stormwater general permit for a project over one acre, risks stop-work action and denial of final plat, occupancy or site-development sign-off until compliance is demonstrated.

Frequently Asked Questions

When does a Lakewood construction project need a stormwater pollution prevention plan?
Once your project meets the drainage-review thresholds in Table 12.11-1 at LMC 12.11.030, you must prepare a construction SWPPP as part of your stormwater site plan under LMC 12.11.040(B). The plan must stay in effect from the first soil disturbance until the site is fully stabilized.
Do I need a state permit for erosion control on a Lakewood project?
If your project is larger than one acre and the City Engineer determines it could discharge to waters of the state, LMC 12.11.040(B) requires you to obtain a construction stormwater general permit from the Washington Department of Ecology, in addition to the City's own erosion-control BMP requirements.
When must erosion control be in place on a Lakewood site?
LMC 12.11.050 requires erosion and sediment control measures to be built according to the approved plan before any grading or clearing beyond what that plan allows, and maintained until all improvements and landscaping are finished and the risk of on-site erosion has passed.

Sources & Official References

Other rules in Lakewood

All Lakewood rules

Compare Lakewood to another location·View the Washington environmental rules overview

Get notified when Erosion Control in Lakewood, WA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Nearby Cities

How other cities in this county handle erosion control.

Tacoma, WA
Some Restrictions