Rothschild, WI Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Trigger threshold
1+ acre of land disturbance
Permit required from
Administrator of Public Works
Start notice
Within 48 hours of beginning work
BMP inspection
Within 24 hrs of 0.5" rain, weekly
Permit duration
180 days, extendable 180 more
Review time
20 business days
Penalty
$10-$500 first offense, per day

Summary

Rothschild requires an approved erosion and sediment control plan and a permit from the Administrator of Public Works before any land disturbing activity of an acre or more begins, with weekly BMP inspections during construction, under Village Code Sections 590-47 and 590-48.

The responsible party shall implement an erosion and sediment control plan developed in accordance with § 590-49 that incorporates the requirements of this section. ... A written plan shall be developed in accordance with § 590-49A and implemented for each construction site. ... The plan required under Subsection B shall include requirements in accordance with § NR 151.11(6), Wis. Adm. Code. ... The Administrator of Public Works, or the designee, may establish erosion control requirements more stringent than those set forth in this section if the Administrator of Public Works, or the designee, determines that an added level of protection is needed for sensitive resources. ... No responsible party may commence a land disturbing construction activity subject to this article without receiving prior approval of an erosion and sediment control plan for the site and a permit from the Administrator of Public Works.

Full Breakdown

Chapter 590, Article IV governs erosion during active construction separately from the long-term post-construction stormwater rules that follow it. Section 590-45 applies the erosion control article to construction sites with one or more acres of land disturbing activity, while exempting redevelopment with no increase in exposed parking or roads, sites under 10% connected imperviousness with under an acre of parking and rooftop, agricultural and silviculture work, routine maintenance under five acres, and underground utility work. 11(6), with best management practices located ahead of the point where runoff reaches state waters; the Administrator of Public Works can demand stricter controls where sensitive resources need added protection.

Section 590-48 makes the permit itself mandatory before any covered activity starts: the application, plan and fee go to the Administrator of Public Works, who has 20 business days to approve or deny, may require a surety bond or letter of credit, and can issue a permit valid 180 days with extensions of up to another 180 days. Permit holders must notify the Administrator within 48 hours of starting work, notify completion of each BMP within 10 days, inspect BMPs within 24 hours of any rainfall of half an inch or more and at least weekly otherwise, log every inspection with date, inspector name and construction phase, repair any siltation or erosion damage to neighboring land, and allow site access for compliance inspections. Section 590-49 further requires the plan to map the site, sequence construction phases, and specify stabilization, sediment-trapping and dust-control measures.

Violations & Fines

Section 590-57 applies to this article: the Administrator of Public Works issues a certified-mail notice describing the violation and the correction schedule, and can post a stop-work order, revoke the permit, or seek a cease and desist order or injunction through the Village Attorney. Noncompliance is subject to a forfeiture of $10 to $500 for a first offense and $50 to $500 for a second, with each day a separate offense plus prosecution costs.

Frequently Asked Questions

What size project needs an erosion control permit in Rothschild?
Section 590-45 applies the permit requirement to sites with one acre or more of land disturbing construction activity after the ordinance's effective date, unless an exemption applies, such as small redevelopment, under-10%-imperviousness sites, farming, or utility trenching.
How often must a contractor inspect erosion controls on a Rothschild site?
Section 590-48E requires inspection within 24 hours after any rainfall of half an inch or more that causes runoff during active construction, and at least once a week regardless, with findings logged by date, inspector name and construction phase in a site erosion control log.
How long is a Rothschild erosion control permit valid?
Section 590-48G sets the permit at 180 days from issuance or the length of the associated building permit, whichever is longer, and the Administrator of Public Works may grant one or more 180-day extensions, sometimes adding new BMP conditions.
Can Rothschild require a bond for erosion control compliance?
Yes. Section 590-48D lets the Administrator of Public Works require a surety bond or irrevocable letter of credit as a condition of permit approval, to guarantee good-faith execution of the approved erosion and sediment control plan and any permit conditions.

Sources & Official References

Other rules in Rothschild

All Rothschild rules

Compare Rothschild to another location·View the Wisconsin environmental rules overview

Get notified when Erosion Control in Rothschild, WI changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.