Rothschild, WI Environmental Rules: Erosion Control (2026)
Key Facts
- Trigger threshold
- 1+ acre of land disturbance
- Permit required from
- Administrator of Public Works
- Start notice
- Within 48 hours of beginning work
- BMP inspection
- Within 24 hrs of 0.5" rain, weekly
- Permit duration
- 180 days, extendable 180 more
- Review time
- 20 business days
- Penalty
- $10-$500 first offense, per day
Summary
Rothschild requires an approved erosion and sediment control plan and a permit from the Administrator of Public Works before any land disturbing activity of an acre or more begins, with weekly BMP inspections during construction, under Village Code Sections 590-47 and 590-48.
The responsible party shall implement an erosion and sediment control plan developed in accordance with § 590-49 that incorporates the requirements of this section. ... A written plan shall be developed in accordance with § 590-49A and implemented for each construction site. ... The plan required under Subsection B shall include requirements in accordance with § NR 151.11(6), Wis. Adm. Code. ... The Administrator of Public Works, or the designee, may establish erosion control requirements more stringent than those set forth in this section if the Administrator of Public Works, or the designee, determines that an added level of protection is needed for sensitive resources. ... No responsible party may commence a land disturbing construction activity subject to this article without receiving prior approval of an erosion and sediment control plan for the site and a permit from the Administrator of Public Works.
Full Breakdown
Chapter 590, Article IV governs erosion during active construction separately from the long-term post-construction stormwater rules that follow it. Section 590-45 applies the erosion control article to construction sites with one or more acres of land disturbing activity, while exempting redevelopment with no increase in exposed parking or roads, sites under 10% connected imperviousness with under an acre of parking and rooftop, agricultural and silviculture work, routine maintenance under five acres, and underground utility work. 11(6), with best management practices located ahead of the point where runoff reaches state waters; the Administrator of Public Works can demand stricter controls where sensitive resources need added protection.
Section 590-48 makes the permit itself mandatory before any covered activity starts: the application, plan and fee go to the Administrator of Public Works, who has 20 business days to approve or deny, may require a surety bond or letter of credit, and can issue a permit valid 180 days with extensions of up to another 180 days. Permit holders must notify the Administrator within 48 hours of starting work, notify completion of each BMP within 10 days, inspect BMPs within 24 hours of any rainfall of half an inch or more and at least weekly otherwise, log every inspection with date, inspector name and construction phase, repair any siltation or erosion damage to neighboring land, and allow site access for compliance inspections. Section 590-49 further requires the plan to map the site, sequence construction phases, and specify stabilization, sediment-trapping and dust-control measures.
Violations & Fines
Section 590-57 applies to this article: the Administrator of Public Works issues a certified-mail notice describing the violation and the correction schedule, and can post a stop-work order, revoke the permit, or seek a cease and desist order or injunction through the Village Attorney. Noncompliance is subject to a forfeiture of $10 to $500 for a first offense and $50 to $500 for a second, with each day a separate offense plus prosecution costs.
Frequently Asked Questions
What size project needs an erosion control permit in Rothschild?
How often must a contractor inspect erosion controls on a Rothschild site?
How long is a Rothschild erosion control permit valid?
Can Rothschild require a bond for erosion control compliance?
Sources & Official References
Other rules in Rothschild
Compare Rothschild to another location·View the Wisconsin environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Erosion Control in Nearby Cities
How other cities in Marathon County handle erosion control.