Shoreline, WA Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Scope
ESC required for any site-disturbing activity, permit or not
Slope limit
Max cut/fill slope 2 horizontal to 1 vertical
Benches
10 ft wide, 25 ft vertical spacing maximum
Work hours
7am-7pm weekdays, 9am-9pm weekends
Civil penalty
Starts at $500, doubles every 14 days
Governing manual
Surface Water Management Code, SMC § 13.10.200

Summary

In the City of Shoreline, any activity that clears, grades or otherwise disturbs a site, whether a permit is required or not, must control erosion and sediment under SMC § 20.50.340(A), tying construction sites to the City's Surface Water Management Code standards in SMC § 13.10.200 and limiting grading and tree-cutting hours.

A. Any activity that will clear, grade or otherwise disturb the site, whether requiring a clearing or grading permit or not, shall provide erosion and sediment control (ESC) that prevents, to the maximum extent possible, the transport of sediment from the site to drainage facilities, water resources and adjacent properties. Erosion and sediment controls shall be applied as specified by the temporary ESC measures and performance criteria and implementation requirements in SMC § 13.10.200, Surface Water Management Code and adopted standards. ... ... G. Hours of Operation. Hours of operation for tree cutting, clearing and grading, unless otherwise authorized by the Director, shall be between 7:00 a.m. and 7:00 p.m. weekdays and 9:00 a.m. to 9:00 p.m. on Saturdays and Sundays. Additionally, tree cutting (felling) shall further be limited to daylight hours.

Full Breakdown

SMC § 20.50.340(A) applies erosion and sediment control (ESC) to any activity that clears, grades or otherwise disturbs a Shoreline site, whether it needs a clearing or grading permit or not, and ties the temporary ESC measures to the performance criteria in SMC § 13.10.200, the City's Surface Water Management Code. Cuts and fills approved by the Director may not exceed a slope steeper than two horizontal to one vertical under SMC § 20.50.340(B)(1), and disturbed cut and fill faces must be prepared and maintained to control erosion consistent with the Surface Water Design Manual under subsection (B)(2).

Fill material cannot include detrimental organic material or rock larger than 12 inches in maximum dimension, and drainage provisions must prevent surface water or seepage from damaging cut or fill faces and must carry concentrated runoff to a natural watercourse or another method approved by Public Works. Required benches must be at least 10 feet wide, back-sloped, spaced no more than 25 feet vertically, with swale gradients capped at five percent. The Director can require access-road gates, warning signs and temporary fencing on active grading sites.

Work hours for tree cutting, clearing and grading are limited to 7:00 a.m. to 7:00 p.m. on weekdays and 9:00 a.m. to 9:00 p.m. on Saturdays and Sundays under subsection (G), with felling restricted to daylight hours, and haul-route traffic control plans are required under subsection (H).

Violations & Fines

Failing to control erosion and sediment during land-disturbing work exposes a responsible party to the general SMC § 20.30.770 enforcement scheme: a Class 1 civil infraction, a misdemeanor carrying up to a $1,000 fine and 90 days in jail per week the violation continues, and civil penalties starting at $500 for a notice-and-order violation that double every 14 days it remains uncorrected.

Frequently Asked Questions

Do I need a permit to control erosion on my Shoreline construction site?
Not necessarily for a permit specific to erosion control, but SMC § 20.50.340(A) requires erosion and sediment control on any activity that clears, grades or disturbs a site, whether a clearing or grading permit is required or not, applying the standards in the City's Surface Water Management Code, SMC § 13.10.200.
How steep can a cut or fill slope be?
SMC § 20.50.340(B)(1) caps cut and fill slopes at two horizontal feet for every one vertical foot unless the Director approves a steeper slope as safe for the intended use, and the disturbed cut and fill faces must then be prepared and maintained to control erosion under the Surface Water Design Manual.
What hours can contractors clear or grade a Shoreline site?
SMC § 20.50.340(G) limits clearing, grading and tree-cutting work to 7:00 a.m. to 7:00 p.m. on weekdays and 9:00 a.m. to 9:00 p.m. on Saturdays and Sundays, and tree felling is further confined to daylight hours, unless the Director authorizes different hours.
What happens if erosion controls fail on my site?
The City can issue a stop-work order and a notice and order under SMC § 20.30.770, carrying a $500 civil penalty for the first 14 days that escalates to 150 percent and then doubles every 14-day period the violation continues uncorrected.

Sources & Official References

Other rules in Shoreline

All Shoreline rules

Compare Shoreline to another location·View the Washington environmental rules overview

Get notified when Erosion Control in Shoreline, WA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Nearby Cities

How other cities in King County handle erosion control.

Renton, WA
Some Restrictions
Kirkland, WA
Some Restrictions
Kent, WA
Some Restrictions
Auburn, WA
Some Restrictions
Bellevue, WA
Some Restrictions
Federal Way, WA
Some Restrictions
Seattle, WA
Some Restrictions