Key Facts

Permit issuer
Conservation Commission, § 154-5
Permit trigger
Land disturbance of one acre or more
Minor project tier
1/2 acre up to but not including one acre
Minor project notice
Written notice at least seven calendar days before work
Construction entrance apron
Gravel, 15 feet wide, at least 24 feet long
Commission decision deadline
90 days from filing, § 154-10(A)

Summary

In Southborough, construction that disturbs one acre or more of land needs a stormwater and erosion control permit from the Conservation Commission. Section 154-9 requires temporary erosion and sedimentation controls during construction, a gravel apron 15 feet wide and at least 24 feet long at paved-way access points, and siltation barriers until the disturbed area is permanently stabilized.

A. The Commission shall not approve any application for a stormwater and erosion control permit unless it finds that BMPs will be employed to meet the following requirements: ... (10) During construction, temporary erosion and sedimentation control measures will be employed in accordance with the approved plan; (11) During construction, any site access from a paved public way shall be improved with a gravel apron of 15 feet wide and at least 24 feet long to prevent unstable material from being transported onto the street by vehicle tires or by runoff; (12) Until a disturbed area is permanently stabilized, sediment in runoff water shall be trapped by using a siltation barrier, siltation fences, and/or sedimentation traps; ... (14) Permanent erosion control and vegetative measures shall be in accordance with the approved plan; and

Full Breakdown

Chapter 154 of the Town's bylaws, adopted by Town Meeting on 3-25-2023 under Article 30, regulates erosion and sediment control on construction sites in Southborough. Section 154-1 states the aim: preventing soil erosion and sedimentation resulting from site construction and development. Under § 154-5 the Conservation Commission is the permit granting authority and administers and enforces the bylaw.

A stormwater and erosion control permit is required under § 154-3 for activity subject to major site plan review (§ 174-10) unless no land disturbance is commencing, for land disturbance of one acre or more, for an increase in impervious surfaces of more than 50% of a parcel or lot larger than one acre, and for disturbance of land with 15% or greater slope where the disturbance is greater than or equal to 15,000 square feet within the sloped area. Maintenance, reconstruction or resurfacing of a public way is covered when the road is expanded three feet or greater for 100 feet or more.

Smaller jobs get a lighter track. Soil disturbance of 1/2 acre, 21,780 square feet, up to but not including one acre, 43,560 square feet, follows the Stormwater Policy for Minor Projects enforced by the Conservation Agent. The owner notifies the Commission in writing, with a sketch, at least seven calendar days before land disturbing activities begin, and installs measures such as erosion control barriers at the direction of the Commission or its agent.

Section 154-9(A) lists the construction-phase findings. Besides the items quoted above, the Commission requires a written time table, approved by the Commission, for how long disturbed areas stay exposed (3), a planting plan for permanent revegetation where the site is not covered (7), loam of not less than six inches compacted depth with seeding on planted areas (8), and dust control during grading within 500 feet of an occupied residence or place of business, school, playground, park, cemetery, or place of worship (9). The applicant must name a contact reachable 24 hours a day and seven days a week who is responsible for erosion and sediment control (§ 154-5(E)(1)), and must record the permit with the Registry of Deeds before land disturbing activity begins (§ 154-9(C)).

Violations & Fines

Section 154-11 gives the Conservation Commission or its authorized agent and the Town the power and duty to pursue all civil and criminal remedies. Section 154-11(A) subjects violators of the bylaw, a regulation or a permit to fines, civil action, criminal prosecution and tax liens; no dollar amount is printed. Unpaid repayment of Town services after 30 days can become a tax lien, and § 154-11(C) allows noncriminal disposition under MGL c. 40, § 21D.

Frequently Asked Questions

At what size does a Southborough project need an erosion control permit?
Section 154-3 requires a stormwater and erosion control permit for land disturbance of one acre or more, among other triggers. Disturbance from 1/2 acre, 21,780 square feet, up to but not including one acre follows the minor projects policy, with written notice to the Conservation Commission at least seven calendar days in advance.
What does the bylaw require at the construction entrance?
Section 154-9(A)(11) requires any site access from a paved public way to be improved during construction with a gravel apron of 15 feet wide and at least 24 feet long, to prevent unstable material from being transported onto the street by vehicle tires or by runoff.
How long does the Commission take to decide and can the decision be appealed?
Under § 154-10(A) the Commission acts within 90 days of the date of filing with the Commission and the Town Clerk. Its decision is final, and relief is reviewable in Superior Court in an action filed within 60 days, in accordance with MGL c. 249, § 4.
Who pays for plan review?
The applicant. Section 154-6 has the Commission set fees, allows it to charge for a registered professional engineer or other consultant, and allows an escrow account to cover those costs. Review fees must be paid before the review process begins. Section 154-7 allows a cash performance guaranty.

Sources & Official References

Other rules in Southborough

All Southborough rules

Compare Southborough to another location·View the Massachusetts environmental rules overview

Get notified when Erosion Control in Southborough, MA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Nearby Cities

How other cities in this county handle erosion control.

Leominster, MA
Some Restrictions
Worcester, MA
Some Restrictions