Southborough, MA Environmental Rules: Flood Elevation Requirements (2026)
Key Facts
- Elevation basis
- 100-year base flood elevations on the July 16, 2014 FIRM
- Unnumbered A Zones
- Building Department uses best available federal, state or other data
- Large developments
- Technical data required above 50 lots or five acres, whichever is less
- FEMA notice
- Within six months of data changing a base flood elevation
- Elevation records
- Select Board keeps lowest-floor elevations under § 19-3
- Variance letter
- Owner told of higher flood insurance premiums
Summary
In Southborough, base flood elevation is the reference point for building in the Wetland and Floodplain District. Where FEMA has published no elevation or floodway data for an A Zone, the Building Department uses the best available federal, state or other data to require elevating residential structures, and developments greater than 50 lots or five acres, whichever is less, must supply their own technical data.
F. Unnumbered A Zones. (1) In A Zones, in the absence of FEMA BFE data and floodway data, the Building Department will obtain, review, and reasonably utilize base flood elevation and floodway data available from a federal, state, or other source as criteria for requiring new construction, substantial improvements, or other development in Zone A as the basis for elevating residential structures to or above base flood level, for floodproofing or elevating nonresidential structures to or above base flood level, and for prohibiting encroachments in floodways. ... (2) Base Flood Elevation Data for Subdivision Proposals. (a) When proposing subdivisions or other developments greater than 50 lots or five acres (whichever is less), the proponent must provide technical data to determine base flood elevations for each developable parcel shown on the design plans.
Full Breakdown
Section 174-8.9(B) ties the district boundaries to the 100-year base flood elevations shown on the Worcester County Flood Insurance Rate Map dated July 16, 2014. Where the map shows a Zone A with no FEMA base flood elevation or floodway data, subsection F directs the Building Department to obtain, review and reasonably utilize base flood elevation and floodway data from a federal, state or other source. That data becomes the criteria for requiring new construction, substantial improvements and other development to elevate residential structures to or above base flood level, to floodproof or elevate nonresidential structures to or above base flood level, and to prohibit encroachments in floodways.
Larger projects carry their own burden. Under subsection G(2)(a), a proponent of subdivisions or other developments greater than 50 lots or five acres, whichever is less, must provide technical data to determine base flood elevations for each developable parcel shown on the design plans. If the Town itself acquires data that changes the base flood elevation in a FEMA mapped Special Flood Hazard Area, subsection J requires it to notify FEMA within six months by submitting the supporting technical or scientific data to the NFIP State Coordinator at the Massachusetts Department of Conservation and Recreation and to the NFIP Program Specialist at FEMA Region 1.
Elevation also drives record keeping. Chapter 19, § 19-3, appoints the Select Board to maintain for public inspection, and to furnish on request, a record of elevations, in relation to mean sea level, of the lowest floor, including basement, of all new or substantially improved structures in the special flood hazard areas. If the lowest floor is below grade on one or more sides, the elevation of the floor immediately above must also be recorded.
When the State Building Code Appeals Board hears a variance, subsection K requires the Town to request a copy of that part of the hearing and to send the owner a letter, signed by a community official, stating that a variance to build below the base flood level will result in increased flood insurance premium rates, up to amounts as high as $25 to $100 of insurance coverage, and increases risks to life and property.
Violations & Fines
Elevation requirements sit inside the Zoning Bylaw, so § 174-24 governs enforcement. The Building Inspector, acting as Zoning Enforcement Officer, enforces it, and a violation of the bylaw or a permit condition is punished by a fine not exceeding $300 for each offense, with each day a separate offense. Noncriminal disposition under MGL c. 40, § 21D is also available through a written notice to appear within 21 days.
Frequently Asked Questions
What happens in a Southborough A Zone with no published base flood elevation?
Does a developer have to supply base flood elevations?
Where are lowest-floor elevations recorded in Southborough?
What does the Town tell an owner who gets a variance to build below base flood level?
Sources & Official References
Other rules in Southborough
Compare Southborough to another location·View the Massachusetts environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.