Elgin, IL Environmental Rules: Flood Elevation Requirements (2026)
Key Facts
- Detention facility freeboard
- 2 feet above BFE
- Overland flow path freeboard
- 1 foot minimum
- Open channel freeboard
- 2 feet minimum
- Civil fine per violation
- $100 to $1,000 per day
- BFE source, Cook County
- FIS/FIRM dated January 23, 2026
- BFE source, Kane County
- Kane Co. Stormwater Ordinance § 9-136.A
- Administering official
- City engineer (administrator)
Summary
Elgin's stormwater code sets the base flood elevation from FEMA's Cook and Kane County flood maps and requires two feet of freeboard above it around detention facilities. Overland flow paths need at least one foot of freeboard, and open channels in major drainage systems need two feet, enforced by the city engineer under Title 21.
A minimum of two (2) feet of freeboard above the base flood elevation shall be provided around the perimeter of the detention facility with the exception of the overflow structure. Water surface elevations two (2) feet above the base flood elevation shall not damage the detention facility.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 7).
Full Breakdown
01. A of the Kane County Stormwater Management Ordinance and FEMA's current Kane County FIS and FIRMs. If a party disputes the mapped data, that party must finance the detailed engineering study needed to produce better data and submit it to FEMA and the Illinois Department of Natural Resources, Office of Water Resources, before developing the site. 020 amends the underlying county ordinance's site runoff storage requirements: detention facilities must carry a minimum of two feet of freeboard above the base flood elevation around their perimeter, except at the overflow structure, and a two-foot rise above the base flood elevation cannot damage the facility.
The same section sets a one-foot minimum freeboard on any overland flow path regardless of the service area's size, and requires open channels in a major drainage system to carry a minimum two-foot freeboard while limiting the product of maximum velocity and depth during the base flood to four or less. Establishing a BFE is mandatory in an A Zone for any new subdivision or development of fifty lots or five acres, whichever is smaller. The city engineer administers the program as the 'administrator' under section 104(2).
Violations & Fines
Section 703 of the amended stormwater ordinance makes any offense punishable by a civil fine of not less than $100 and not more than $1,000, with each calendar day a violation continues counted as a separate offense. The administrator or director can also revoke a stormwater management permit, issue a written stop-work order posted on site, and pursue legal or equitable action, including an injunction, to enforce compliance.
Frequently Asked Questions
How much freeboard does Elgin require above the base flood elevation?
Where does Elgin get its base flood elevation data?
What if I disagree with Elgin's mapped flood elevation?
What are the penalties for violating Elgin's stormwater freeboard rules?
Sources & Official References
Other rules in Elgin