Key Facts

Rule
Lowest floor elevated 2 feet above BFE minimum
Applies to
New construction, repetitive-loss repairs, substantial improvements
Enforcing office
Floodplain administrator, Building Inspections Dept.
Criminal penalty
Up to $500 fine and/or 6 months jail
Appeal
10 days to Hoover Code Appeals Board
Two counties
SFHA maps differ between Jefferson and Shelby sides

Summary

New and substantially improved buildings in Hoover's mapped flood zones must elevate the lowest floor, including mechanical and electrical equipment, at least 2 feet above the base flood elevation under City Code § 12-72(1). The floodplain administrator in the Building Inspections Department enforces the standard and can require a licensed engineer's certification for non-residential floodproofing.

(1) Residential and non-residential structures. Where BFE data is available, new construction, reconstruction, or repairs made to a repetitive loss structure, and substantial improvement of any structure or manufactured home shall have the lowest floor, including basement, and mechanical and electrical equipment servicing the structure elevated no lower than two (2) feet above the BFE. Should solid foundation perimeter walls be used to elevate a structure, openings sufficient to facilitate the unimpeded movements of flood waters shall be provided in accordance with standards of section 12-72(3).

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 23).

Full Breakdown

Article III of Chapter 12, Flood Damage Prevention, readopted by Ord. No. 24-2636 on March 18, 2024, sets construction standards for every Special Flood Hazard Area in the city. Section 12-72(1) states the core freeboard rule: where base flood elevation (BFE) data is available, new construction, reconstruction, repairs to a repetitive loss structure, and substantial improvement of any structure or manufactured home shall have the lowest floor, including basement, and mechanical and electrical equipment servicing the structure elevated no lower than two feet above the BFE.

Structures built on solid perimeter foundation walls must also include flood-vent openings sized under § 12-72(3) so floodwaters can pass through unimpeded. Non-residential buildings may substitute dry floodproofing to the same two-foot design flood elevation under § 12-72(2), but only with a licensed engineer's or architect's certification kept on permanent file. The floodplain administrator, housed in the Building Inspections Department, reviews every permit application's plot plan for the proposed lowest-floor elevation, requires a post-construction elevation certificate before issuing a certificate of occupancy, and can grant a variance only through the Hoover Code Appeals Board under § 12-60.

Because Hoover straddles Jefferson and Shelby counties, the SFHA maps and BFE data an applicant must use depend on which county's FIRM panel covers the parcel. A violation is a criminal offense under § 12-46(c): a fine of up to $500, up to six months in jail, or both, with each day of noncompliance a separate offense, plus the city can withhold a certificate of occupancy, revoke the permit, or ask FEMA to issue a Section 1316 declaration that cuts off the property's flood insurance eligibility entirely.

Violations & Fines

Building below the required 2-foot freeboard, or skipping the elevation certificate, is a criminal violation under § 12-46(c): up to $500 in fines, up to six months in jail, or both, with each day counted separately. The floodplain administrator can also withhold or revoke a certificate of occupancy, suspend the building permit, or request a FEMA Section 1316 declaration that ends the property's flood insurance eligibility until the violation is cured.

Frequently Asked Questions

How much higher than base flood elevation must I build in Hoover?
At least 2 feet. Section 12-72(1) requires the lowest floor, including the basement and any mechanical or electrical equipment, to sit no lower than two feet above the base flood elevation for new construction, substantial improvements, and repairs to repetitive loss structures anywhere BFE data is available.
What if I want to dry floodproof a commercial building instead of elevating it?
Non-residential structures may be floodproofed instead of elevated under § 12-72(2), but the building and its mechanical and utility systems must be watertight to two feet above the BFE, and a state-licensed engineer or architect must certify the design and keep that certification on file with the floodplain administrator in perpetuity.
Which flood maps apply to my Hoover property since the city is in two counties?
It depends on where your parcel sits. Section 12-40 applies the article to lands in the city's special flood hazard areas as shown on the effective Flood Insurance Rate Maps, and Hoover properties draw from either the Jefferson County or Shelby County FIRM panels depending on which side of the county line the lot is on. The floodplain administrator can confirm which panel governs a specific address.

Sources & Official References

Other rules in Hoover

All Hoover rules

Compare Hoover to another location·View the Alabama environmental rules overview

Get notified when Flood Elevation Requirements in Hoover, AL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Flood Elevation Requirements in Nearby Cities

How other cities in Jefferson County handle flood elevation requirements.

Vestavia Hills, AL
Some Restrictions
Birmingham, AL
Some Restrictions