Key Facts
- Elevation standard
- To or above the base flood elevation (§ 15.32.170(C)(1))
- Who certifies
- Registered professional engineer or surveyor
- AR zone elevation
- Lower of AR base flood elevation or three feet above highest adjacent grade
- Enclosure openings
- Two openings, one square inch per square foot enclosed
- Opening height
- Bottom no higher than one foot above grade
- Substantial improvement threshold
- Cost equal to or over 50% of market value
Summary
In the City of Paramount, Section 15.32.170 requires new construction in special flood hazard areas to be elevated to or above the base flood elevation, with the lowest floor certified by an engineer or surveyor. In AR zones, Section 15.32.220 uses the lower of the AR base flood elevation or three feet above the highest adjacent grade.
In all areas of special flood hazards the following standards are required: ... C. Elevation and Floodproofing. (See "basement," "lowest floor," "new construction," "substantial damage" and "substantial improvement" in Section 15.32.050 Definitions.) For AR Zone requirements, see Section 15.32.220. 1. In an A zone, elevated to or above the base flood elevation, as determined by this community. In all other zones, elevated to or above the base flood elevation. Upon the completion of the structure, the elevation of the lowest floor including basement shall be certified by a registered professional engineer or surveyor, and verified by the community building inspector to be properly elevated. Such certification and verification shall be provided to the Floodplain Administrator. 2. Nonresidential construction, new or substantial improvement, shall either be elevated to conform with paragraph 1 above or together with attendant utility and sanitary facilities:
Full Breakdown
Section 15.32.170(C) of the Paramount Municipal Code sets the elevation rule for all areas of special flood hazards. In an A zone, a structure must be elevated to or above the base flood elevation as determined by the community, and the same standard applies in all other zones. When the structure is complete, the elevation of the lowest floor including basement must be certified by a registered professional engineer or surveyor and verified by the community building inspector. That certification and verification go to the Floodplain Administrator, who is the City Manager under Section 15.32.140. The base flood is the flood with a one percent chance of being equaled or exceeded in any given year.
Nonresidential new construction or substantial improvement must either be elevated the same way or be floodproofed to the recommended elevation so the structure is watertight with walls substantially impermeable to water, with structural components able to resist hydrostatic and hydrodynamic loads and buoyancy, and with a certification by a registered professional engineer or architect. Fully enclosed areas below the lowest floor used solely for parking, building access, or storage must equalize flood forces, either with an engineer's or architect's certification or with a minimum of two openings totaling not less than one square inch for every square foot of enclosed area, with the bottom of all openings no higher than one foot above grade.
AR zones work differently. Because Section 15.32.220 treats the entire incorporated City of Paramount as a developed area, all new construction in AR designated areas must meet the Section 15.32.170 through 15.32.220 standards using the lower of either the AR base flood elevation or the elevation that is three feet above the highest adjacent grade. Improvements, including substantial improvements, to existing structures carry no elevation requirement there. A substantial improvement is work whose cost equals or exceeds 50% of the market value of the structure before construction starts.
The sections read print no separate freeboard figure above the base flood elevation. Section 15.32.130 requires the permit application to show the proposed lowest floor elevation, and Section 15.32.200(B) requires manufactured home chassis in Zone A to be supported at no less than 36 inches above grade if the lowest floor is not at or above the base flood.
Violations & Fines
A structure without the elevation certificate, other certifications, or other evidence of compliance that the chapter requires is presumed to be in violation under Section 15.32.050 until the documentation is provided. Under Section 15.32.080, violations are a misdemeanor, and the City of Paramount can take lawful action to prevent or remedy them. Variances from the flood elevation are described in Section 15.32.230 as quite rare.
Frequently Asked Questions
How high must a new building be elevated in a Paramount flood zone?
Does Paramount require freeboard above base flood elevation?
Do additions to existing Paramount buildings have to be elevated?
Can a nonresidential building be floodproofed instead of elevated?
Sources & Official References
Other rules in Paramount
California rules heatmap·Compare Paramount to another location·View the California environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Flood Elevation Requirements in Nearby Cities
How other cities in Los Angeles County handle flood elevation requirements.