Paramount, CA Parking Rules: EV Charging (2026)

Light Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified October 2026

Key Facts

Governing sections
Paramount Municipal Code Chapter 15.06, § 15.06.060 for parking
Deemed complete
Five business days (1 to 25 stations); 10 (more than 25)
Deemed approved
20 business days (1 to 25 stations); 40 (more than 25)
Required parking
Reduced by the amount the station takes
Landscaping
No net loss of landscaped areas
Appeal of use permit requirement
10 days to the Planning Commission

Summary

In the City of Paramount, California, electric vehicle charging stations get an expedited, streamlined permit from the Building Official. An application is deemed complete after five business days for one to 25 stations at a site, or 10 business days for more, and deemed approved after 20 or 40 business days. Under § 15.06.060, required parking is reduced to make room for the equipment.

If an electric vehicle charging station and any associated equipment interfere with, reduce, eliminate, or in any way impact the required parking spaces for existing uses, the City shall reduce the number of required parking spaces for the existing uses by the amount necessary to accommodate the electric vehicle charging station and any associated equipment. There shall be no net loss of landscaped areas.

Full Breakdown

Chapter 15.06 implements Government Code Section 65850.7 in the City of Paramount. The Building Official runs an expedited, streamlined permitting process for electric vehicle charging stations and adopts a checklist of requirements; the checklist and all submission documents must be posted on the City's website (§ 15.06.030). Before applying, the applicant verifies that the installation will not have a specific, adverse impact on public health and safety, covering electrical system capacity and loads, wiring, bonding, overcurrent protection, affected building infrastructure, and the areas of charging equipment and vehicle parking (§ 15.06.040(A)).

Timing runs on business days. An application is deemed complete if, after five business days for one to 25 stations at a single site, or 10 business days for more than 25, the Building Official has neither deemed it complete nor issued a written correction notice. It is deemed approved once 20 business days (one to 25 stations) or 40 business days (more than 25) pass after it was deemed complete without administrative approval, a finding of specific adverse impact, a denial or an appeal. Approval does not authorize an applicant to energize or use the station until the City grants approval. The Building Official must accept electronic submittal and electronic signatures.

Parking and landscaping. Section 15.06.060 requires the City to reduce the number of required parking spaces for existing uses by the amount necessary to accommodate the station and its associated equipment. The same section says there shall be no net loss of landscaped areas.

Review and appeals. If the Building Official finds, on substantial evidence, a specific adverse impact on public health or safety, the City can require a conditional use permit under Chapter 17.48. The applicant can appeal that decision to the Planning Commission by written request within 10 days after receiving it. The Building Official cannot condition approval on approval by an association as defined in Civil Code Section 4080 (§ 15.06.050).

Installation standards in § 15.06.070 require wiring, bonding, disconnecting means and overcurrent devices to meet Article 625 of the California Electrical Code, stations to be counted in load calculations as a continuous load, and anchorage to meet the California Building Code or California Residential Code.

Violations & Fines

Chapter 15.06 prints no stand-alone penalty, so the general enforcement tools apply: § 1.08.010 lets the City issue an administrative citation to any person violating any provision of the Code. Except when a violation creates an immediate danger to health or safety, the cited party gets a reasonable period of time to correct an Electrical Code or Building Code violation before a fine is imposed (§ 1.08.050). Permit approval does not authorize energizing or using the station until the City grants approval.

Frequently Asked Questions

Does installing a charger remove my required parking in Paramount?
If the charging station and associated equipment interfere with, reduce, eliminate, or in any way impact the required parking spaces for existing uses, § 15.06.060 directs the City to reduce the number of required parking spaces by the amount necessary to accommodate the station and equipment. The same section says there shall be no net loss of landscaped areas.
How fast does the City review an EV charger permit?
For one to 25 stations at a single site, an application is deemed complete after five business days without a completeness decision or correction notice, and deemed approved 20 business days after it was deemed complete. For more than 25 stations the periods are 10 and 40 business days. Section 15.06.040 lists the conditions that must all be true.
Can an HOA approval be required for my permit?
Section 15.06.050(B) says the Building Official shall not condition approval of an electric vehicle charging station permit on approval of the system by an association, as defined by California Civil Code Section 4080. That limit binds the Building Official's permit conditions in the City of Paramount.
Can I submit the application online?
Yes. Section 15.06.040(E) requires the Building Official to allow electronic submittal of charging station permit applications and supporting documentation, and to accept electronic signatures on all forms, applications and other documentation instead of a wet signature. The City's adopted checklist and required documents are made publicly available on its website under § 15.06.030.

Sources & Official References

Other rules in Paramount

All Paramount rules

California rules heatmap·Compare Paramount to another location·View the California parking rules overview

Get notified when EV Charging in Paramount, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

EV Charging in Nearby Cities

How other cities in Los Angeles County handle ev charging.

Altadena, CA
Some Restrictions
Burbank, CA
Some Restrictions
Carson, CA
Some Restrictions
Compton, CA
Some Restrictions
Downey, CA
Some Restrictions
El Monte, CA
Some Restrictions
Glendale, CA
Some Restrictions
Inglewood, CA
Some Restrictions