West Bloomfield, MI Environmental Rules: Flood Elevation Requirements (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Freeboard required
One foot above 100-year high water elevation
Design storm
100-year peak runoff, Oakland County method
Max side slope
1 vertical to 6 horizontal
Spillway surface
Concrete, asphalt or grouted rip-rap
Reviewing official
Township engineer

Summary

West Bloomfield Township requires every stormwater detention basin built for new development to hold a one-foot freeboard above the design 100-year high water elevation. The township engineer must approve the overflow route, spillway surface and side-slope design before the basin is accepted.

(a)All new developments shall be required to provide stormwater holding facilities to retain runoff and limit peak discharge to that of the existing hydrology. ... (e)All detention basins must have a one-foot freeboard above the design one hundred-year high water elevation. All basins must have an overflow provision draining to a location which can reasonably accept such overflow without damage to any property and without the creation of a health or safety problem. All spillway overflow must discharge into a recognized natural drainage course or drain. All spillways must have a hard surface consisting of concrete, asphalt or grouted rip-rap, or as otherwise approved by the township engineer, under the circumstances.(f)Detention basin side slopes shall be no steeper than one vertical to six horizontal (1:6).

Full Breakdown

Township Code § 24-185 governs stormwater holding facilities required of all new developments to retain runoff and cap peak discharge at existing hydrology rates, with the two-year, twenty-four-hour peak discharge held to the existing rate and volume. Subsection (e) sets the elevation standard directly: every detention basin must carry a one-foot freeboard above the design one-hundred-year high water elevation, and must include an overflow provision that drains to a location able to accept the overflow without property damage or a health or safety hazard. Overflow must discharge to a recognized natural drainage course or drain, and every spillway must have a hard surface of concrete, asphalt or grouted rip-rap unless the township engineer approves another material for the circumstances.

Side slopes on detention basins may be no steeper than one vertical to six horizontal, per subsection (f), and basins must be able to fully dewater by gravity under subsection (c), with pump discharge allowed only where the engineer finds gravity drainage infeasible. Design volumes are computed using the Oakland County Water Resources Office's Variable Release Rate method for a one-hundred-year peak runoff on developed sites under subsection (j), and an operation and maintenance agreement approved by township legal counsel must be executed before a building permit or final plat approval issues under subsection (i).

This freeboard standard applies to the detention and retention infrastructure required of new subdivisions and site plans rather than to individual building foundations, which are instead addressed through the flood hazard area permit requirements of chapter 12.

Violations & Fines

A detention basin built without the required one-foot freeboard, an approved overflow route, or a hard-surfaced spillway fails § 24-185 review and cannot be accepted by the township engineer; the operation-and-maintenance agreement condition also blocks issuance of the building permit or final plat approval until corrected.

Frequently Asked Questions

How much freeboard does a detention basin need in West Bloomfield?
Township Code § 24-185(e) requires a one-foot freeboard above the design one-hundred-year high water elevation for every detention basin built for new development.
Who approves the overflow route for a basin?
The township engineer must approve the overflow provision, spillway surface material and any departure from gravity dewatering under § 24-185.
Does this freeboard rule apply to my house's foundation?
No. Section 24-185 sets freeboard for stormwater detention and retention basins in new developments; individual building elevation in flood hazard areas is instead governed by the state construction code permit process in chapter 12.

Sources & Official References

Other rules in West Bloomfield

All West Bloomfield rules

Compare West Bloomfield to another location·View the Michigan environmental rules overview

Get notified when Flood Elevation Requirements in West Bloomfield, MI changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Flood Elevation Requirements in Nearby Cities

How other cities in Oakland County handle flood elevation requirements.

Farmington Hills, MI
Some Restrictions