West Bloomfield, MI Environmental Rules: Flood Elevation Requirements (2026)
Key Facts
- Freeboard required
- One foot above 100-year high water elevation
- Design storm
- 100-year peak runoff, Oakland County method
- Max side slope
- 1 vertical to 6 horizontal
- Spillway surface
- Concrete, asphalt or grouted rip-rap
- Reviewing official
- Township engineer
Summary
West Bloomfield Township requires every stormwater detention basin built for new development to hold a one-foot freeboard above the design 100-year high water elevation. The township engineer must approve the overflow route, spillway surface and side-slope design before the basin is accepted.
(a)All new developments shall be required to provide stormwater holding facilities to retain runoff and limit peak discharge to that of the existing hydrology. ... (e)All detention basins must have a one-foot freeboard above the design one hundred-year high water elevation. All basins must have an overflow provision draining to a location which can reasonably accept such overflow without damage to any property and without the creation of a health or safety problem. All spillway overflow must discharge into a recognized natural drainage course or drain. All spillways must have a hard surface consisting of concrete, asphalt or grouted rip-rap, or as otherwise approved by the township engineer, under the circumstances.(f)Detention basin side slopes shall be no steeper than one vertical to six horizontal (1:6).
Full Breakdown
Township Code § 24-185 governs stormwater holding facilities required of all new developments to retain runoff and cap peak discharge at existing hydrology rates, with the two-year, twenty-four-hour peak discharge held to the existing rate and volume. Subsection (e) sets the elevation standard directly: every detention basin must carry a one-foot freeboard above the design one-hundred-year high water elevation, and must include an overflow provision that drains to a location able to accept the overflow without property damage or a health or safety hazard. Overflow must discharge to a recognized natural drainage course or drain, and every spillway must have a hard surface of concrete, asphalt or grouted rip-rap unless the township engineer approves another material for the circumstances.
Side slopes on detention basins may be no steeper than one vertical to six horizontal, per subsection (f), and basins must be able to fully dewater by gravity under subsection (c), with pump discharge allowed only where the engineer finds gravity drainage infeasible. Design volumes are computed using the Oakland County Water Resources Office's Variable Release Rate method for a one-hundred-year peak runoff on developed sites under subsection (j), and an operation and maintenance agreement approved by township legal counsel must be executed before a building permit or final plat approval issues under subsection (i).
This freeboard standard applies to the detention and retention infrastructure required of new subdivisions and site plans rather than to individual building foundations, which are instead addressed through the flood hazard area permit requirements of chapter 12.
Violations & Fines
A detention basin built without the required one-foot freeboard, an approved overflow route, or a hard-surfaced spillway fails § 24-185 review and cannot be accepted by the township engineer; the operation-and-maintenance agreement condition also blocks issuance of the building permit or final plat approval until corrected.
Frequently Asked Questions
How much freeboard does a detention basin need in West Bloomfield?
Who approves the overflow route for a basin?
Does this freeboard rule apply to my house's foundation?
Sources & Official References
Other rules in West Bloomfield
Compare West Bloomfield to another location·View the Michigan environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Flood Elevation Requirements in Nearby Cities
How other cities in Oakland County handle flood elevation requirements.