Significant Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Permit trigger
1+ acre disturbed, or within 500 ft of water
Enforcing agency
Development services department, Sec. 8-363
Permit term
Expires one year from issuance, Sec. 8-378(c)
Building-permit hold
No building permit until SESC issued, Sec. 8-380
Enforcement cap
$10,000 township self-help work before extra notice

Summary

West Bloomfield Township's Sec. 8-376 makes it unlawful to conduct an earth change without a Soil Erosion and Sedimentation Control (SESC) permit from the development services department, required whenever the disturbance covers an acre or more or lies within 500 feet of state waters or wetlands.

(a)It shall be unlawful to permit, authorize or conduct an earth change without first obtaining a SESC permit with approved SESC plans from the development services department unless a permit and/or plans are not required under the provisions of this article, Part 91, or the Rules.(b)SESC permit requirements. Unless otherwise exempt by this article, Part 91, or the Rules, a landowner or designated agent who contracts for, allows, or engages in, an earth change in this township shall obtain a SESC permit from the development services department which shall be kept current throughout all active earth change operations, before commencing an earth change which:(1)Disturbs one (1) or more acres of land; or(2)Is within five hundred (500) feet of any waters of the state and wetlands. ... (c)A person who knowingly violates Part 91, the Rules or this article shall be issued a municipal civil infraction citation authorized by the Revised Judicature Act, MCL 600.8701, et seq.; and section 1-10 of the Code of Ordinances.

Full Breakdown

Adopted under Sec. 8-360 pursuant to Part 91 of Michigan's Natural Resources and Environmental Protection Act, MCL 324.9101 et seq., Article XV names the development services department as the Municipal Enforcing Agency (Sec. 8-363). Sec. 8-376(a)-(b) requires any landowner or designated agent to obtain an SESC permit before commencing an earth change that disturbs one or more acres of land, or that falls within 500 feet of any waters of the state or wetlands, and to keep that permit current throughout active operations. Sec. 8-377 exempts limited activities, agricultural plowing, minor earth changes stabilized within 24 hours, and small residential jobs like post holes or lawn seeding away from the water, but Sec.

8-377(b) makes clear even exempt work loses its exemption if it causes an erosion or sedimentation problem. Sec. 8-378 bars issuance where the work would cause uncontrolled erosion or safety hazards, and sets a one-year permit expiration. Sec. 8-380 blocks a building permit from issuing on the same project until the SESC permit and approved plans are secured. Sec. 8-383(a)-(b) lets the township recover its enforcement costs from noncompliant landowners and place a lien on the property, and Sec. 8-383(e) allows a court to order restoration of the affected land.

Violations & Fines

Sec. 8-383(c) makes a knowing violation of Part 91, the state rules, or this article a municipal civil infraction under Sec. 1-10, with civil fines deposited to the township's general fund. Sec. 8-383(e) adds that a violator is also liable to the state for damages to natural resources and can be ordered by a court to restore the site to its pre-violation condition or otherwise abate the violation.

Frequently Asked Questions

Do I need a permit to grade or clear land in West Bloomfield Township?
Yes, if the earth change disturbs one acre or more, or is within 500 feet of any waters of the state or wetlands. Sec. 8-376 requires a Soil Erosion and Sedimentation Control (SESC) permit from the development services department before that work begins.
Are any activities exempt from the erosion permit?
Sec. 8-377 exempts things like normal road maintenance, minor earth changes stabilized within 24 hours, and small residential jobs such as post holes, tree planting, or limited lawn reseeding away from the water, but exempt work still must not cause erosion or sedimentation.
Can I get my building permit before the erosion permit?
No. Sec. 8-380 specifically bars the development services department from issuing a building permit for a project that requires an SESC permit until the landowner has first obtained that soil erosion and sedimentation control permit with approved plans.

Sources & Official References

Other rules in West Bloomfield

All West Bloomfield rules

Compare West Bloomfield to another location·View the Michigan environmental rules overview

Get notified when Erosion Control in West Bloomfield, MI changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Nearby Cities

How other cities in Oakland County handle erosion control.

Farmington Hills, MI
Some Restrictions