FEMA flood zone rules in Bristol, CT, also called floodplain regulations or special flood hazard area (SFHA) rules, determine flood insurance requirements and elevation standards for new construction.

Key Facts

Permit required
Before any development in a flood hazard area
Permit administrator
City engineer, reviewed by Flood and Erosion Commission
Fees
$5 permitted use to $100 special exception
Max penalty
$250/day willful, $100/day otherwise, or 10 days jail
Appeal body
Bristol Flood and Erosion Commission

Summary

Before any development activity begins in a Bristol special flood hazard area, Appendix D § 3.3 requires a floodplain development permit from the city engineer, acting as ordinance administrator. Applicants pay $5 to $100 depending on use type, and violating the ordinance is a misdemeanor punishable under § 7.6 by daily fines of up to $250, imprisonment, and payment of the city's legal costs.

A floodplain development permit shall be required in conformance with the provisions of this ordinance prior to the commencement of any development activities. ... 7.6. ... Penalties for violation. Violation of the provisions of this ordinance or failure to comply with any of its requirements, including violation of conditions and safeguards established in connection with grants of variance or special exceptions, shall constitute a misdemeanor. Any person who violates this ordinance or fails to comply with any of its requirements shall, upon conviction thereof, be fined not more than two hundred fifty dollars ($250.00) per day if proven done willfully and one hundred dollars ($100.00) per day if not, or imprisoned for not more than ten (10) days for each day of violation, or both, and in addition, shall pay all costs and reasonable legal fees involved in the case.

Full Breakdown

Appendix D, the Flood Damage Prevention ordinance adopted August 12, 2008, applies to every Special Flood Hazard Area (SFHA) shown on the FEMA Flood Insurance Rate Maps for Bristol, including the May 16, 2017 panel and the September 26, 2008 panels covering the rest of the city (§ 3.2). Section 3.3 requires a floodplain development permit before any development activity in those zones. The city engineer, designated as the ordinance administrator under § 4.1 and subject to review by the Flood and Erosion Commission, processes applications, which must show the proposed lowest-floor elevation, describe encroachment into the flood-fringe, and state whether the project meets the substantial-improvement definition (§ 4.2).

Application fees run $5.00 for a permitted use, $50.00 for a regulated use, and $100.00 for a special exception (§ 4.7.1). Permit decisions are published in a newspaper of general circulation, and a permit takes effect seven days after that publication if no appeal is filed (§ 4.2.1(l)). New development or substantial improvement inside the regulated floodway can be allowed only as a special exception granted by the Bristol Flood and Erosion Commission, and only when the applicant's registered engineer certifies no increase in flood levels will result, with expansions capped at 25 percent of the existing building's footprint (§ 4.6). Appeals from the administrator's interpretation or a permit denial go to the Flood and Erosion Commission under the ordinance's variance procedures (§ 7).

Violations & Fines

Section 7.6 makes any violation of the flood damage prevention ordinance, including violation of a variance or special-exception condition, a misdemeanor. A willful violation carries a fine of up to $250.00 per day; an unintentional one, up to $100.00 per day, or imprisonment for up to ten days, or both, plus all of the city's costs and reasonable legal fees for the case.

Frequently Asked Questions

Do I need a permit to build in a Bristol flood zone?
Yes. Appendix D § 3.3 requires a floodplain development permit from the city engineer before any development activity begins in an area of special flood hazard, and the application must show the proposed structure's elevation and how it will affect the flood-fringe area.
How much does a Bristol floodplain permit cost?
Section 4.7.1 sets a $5.00 fee for a permitted use, $50.00 for a regulated use such as new construction in the flood fringe, and $100.00 for a special exception allowing development in the regulated floodway itself.
What happens if I develop without a floodplain permit?
Section 7.6 treats the violation as a misdemeanor: up to $250.00 per day if the violation was willful, up to $100.00 per day if not, up to ten days in jail, or both, plus the city's costs and legal fees in pursuing the case.
Can Bristol allow building inside the floodway itself?
Only as a special exception granted by the Flood and Erosion Commission under § 4.6, and only when a registered engineer certifies the project will not increase flood levels and any expansion stays within 25 percent of the existing building's footprint.

Sources & Official References

Other rules in Bristol

All Bristol rules

Compare Bristol to another location·View the Connecticut environmental rules overview

Get notified when Flood Zones in Bristol, CT changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.