Key Facts
- Permit trigger
- 1 acre disturbed or 20,000 sq ft new impervious surface
- TSS reduction
- 80% new development, 40% redevelopment of paved areas
- Peak discharge
- Held at pre-development rate for 1-, 2-, 10-, 100-year storms
- Permit term
- 24 months, one 12-month extension available
- Enforcing agency
- Land Resources and Environment Department Zoning Administrator
- Penalty
- $200 to $1,000 per offense, per day
Summary
Chapter 51 of the Sauk County Code requires a Land Resources and Environment Department permit before any land-disturbing activity of one acre or more, or any project adding 20,000 square feet of impervious surface, moves dirt in unincorporated Sauk County. Stormwater facilities must hold post-development peak runoff at or below pre-development rates for the one-, two-, ten- and 100-year, 24-hour storms.
(1)This ordinance is enacted pursuant to the authority granted by Wisconsin Statutes, including, but not limited to, Wis. Stats. §§ 59.693, and 281.33(3m). This ordinance supersedes all provisions of any ordinance previously enacted by Sauk County that relate to construction site erosion control and stormwater management. ... ... Sec. 51.03. - Jurisdiction.(1)The provisions of this ordinance will apply to all unincorporated lands within the jurisdictional boundaries of Sauk County.(2)County-owned lands. Unless exempted by this ordinance, this ordinance applies to all County-owned lands regardless of the municipality in which the land is located or what entity is assigned land management duties, including highway right-of-way. ... Except for redevelopment projects, all stormwater facilities shall be designed, installed and maintained to effectively accomplish the following:1.Maintain or reduce the predevelopment peak runoff discharge rates respectively, or to the maximum extent possible for the one-year, 24-hour storm event (using the NRCS MSE4 storm distribution).
Full Breakdown
Sauk County enacted its stormwater ordinance under Wis. Stats. §§ 59.693 and 281.33(3m), and Sec. 51.03 limits it to unincorporated lands within the county plus all county-owned land regardless of which municipality it sits in, including highway right-of-way. Section 51.14 triggers a land use permit for any land disturbance of one acre or more, any smaller disturbance that is part of a larger development, any new or reconstructed public or private road, and any project that cumulatively adds 20,000 square feet of impervious surface. The Zoning Administrator, housed in the Department of Land Resources and Environment, reviews applications under Sec.
51.16, which requires peak-flow calculations, site plans stamped by a professional engineer for ponds, swales and basins, and a financial guarantee escrowed to cover third-party plan review. Performance standards in Sec. 51.17 require best management practices to cut total suspended solids by 80 percent for new development and 40 percent for redevelopment of parking areas and roads, and to hold post-development peak discharge at or below pre-development rates for the one-, two-, ten- and 100-year, 24-hour storm events. Infiltration BMPs must replace 60 to 90 percent of pre-development infiltration volume depending on how much of the site is paved.
Permits run 24 months, with a one-time 12-month extension, and a long-term maintenance agreement must be recorded with the Register of Deeds. Violators face a fine of $200.00 to $1,000.00 per offense under Sec. 51.23, with each day of violation counted separately.
Violations & Fines
Building or grading without the required land use permit, or ignoring an approved plan's peak-discharge and infiltration standards, violates Chapter 51 and can draw a stop work order posted on the site under Sec. 51.19(2)(f). Sec. 51.23 sets a fine of not less than $200.00 nor more than $1,000.00 per offense, exclusive of court costs, and treats each section violated and each day it continues as a separate offense; the Zoning Administrator can also revoke the permit outright.
Frequently Asked Questions
Does Sauk County require a permit for stormwater work?
What stormwater standards must a new development in Sauk County meet?
Who enforces Sauk County's stormwater ordinance?
What is the fine for violating Sauk County's stormwater rules?
Sources & Official References
Other rules in Sauk County
Compare Sauk County to another location·View the Wisconsin environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.