Broomfield, CO Fence Regulations: Retaining Walls (2026)
Key Facts
- No permit needed
- Wall 3 ft or less, footing to top
- Permit still required if
- Wall supports a surcharge
- Height measured from
- Bottom of footing
- Grading permit
- Separate, City/County Engineering
- Issuing office
- Division of Building Safety
Summary
Broomfield exempts retaining walls of three feet or less, measured from the bottom of the footing to the top, from needing a building permit, unless the wall supports a surcharge or impounds flammable liquids. Taller walls, or any wall carrying extra load, require a permit and city review.
(B)Work exempt from permit. Exemptions from permit requirements of this code shall not be deemed to grant authorization for any work to be done in any manner in violation of the provisions of this code or any other laws or ordinances of this jurisdiction. Permits shall not be required for the following: Building: 1.Retaining walls that are three feet (1,219 mm) or less in height measured from the bottom of the footing to the top of the wall, unless supporting a surcharge or impounding flammable liquids.
Full Breakdown
Section 15-03-070(B), B.M.C. lists work exempt from the building permit requirement, and item 1 under the 'Building' category exempts 'retaining walls that are three feet (1,219 mm) or less in height measured from the bottom of the footing to the top of the wall, unless supporting a surcharge or impounding flammable liquids.' That measurement runs from the footing, not from finished grade, so a wall with a deeper footing counts taller than it looks above ground. The surcharge carve-out means even a short wall needs a permit if it bears extra load, such as a driveway, patio, or structure built above it.
Any retaining wall over three feet, or a shorter wall with a surcharge or flammable-liquid load, requires an application to the building official under section 15-03-070(A), review of construction documents and, where the building official requires it, an engineered design (15-03-080). The permit is reviewed and issued by the Division of Building Safety and Inspection Services (15-03-050), and lapses if work is not started within 180 days or is suspended that long (15-03-070(E)). Site grading around a retaining wall is regulated separately: Broomfield's local Appendix J112 amendment requires 'all grading' to secure a permit from the City and County Engineering Department (J112.3.1), on top of any building permit for the wall itself.
Violations & Fines
Building a retaining wall over three feet, or a shorter surcharge-bearing wall, without a permit is a violation subject to the general penalty schedule in chapter 1-12, B.M.C., and the building official may issue a stop work order to halt construction immediately. Failing to secure the required grading permit for associated site work is a separate violation enforceable by the City and County Engineering Department.
Frequently Asked Questions
Does a short retaining wall in Broomfield need a permit?
How is retaining wall height measured in Broomfield?
Do I need a separate grading permit for a retaining wall project?
What if my retaining wall is under three feet but holds up a driveway?
Sources & Official References
Other rules in Broomfield
Compare Broomfield to another location·View the Colorado fence regulations overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.