Key Facts

Engineering trigger
Retaining walls over 4 feet tall
Fence/slope setback
2 feet minimum from top/toe of slope
Small-grading exemption
Grading under 50 cubic yards
Permit type
Mass grading permit
Issuing department
Community Development Department
Contour tie-in
50 feet beyond lot lines

Summary

Lyon County requires engineering calculations for any retaining wall over four feet in height as part of a mass grading permit application, under Lyon County Code section 15.240.04. Grading plans must also show a minimum two-foot setback from the property line or fence line at the top and toe of any slope. The rules apply in unincorporated Lyon County; Fernley and Yerington regulate retaining walls under their own codes.

These county ordinances apply to unincorporated areas of Lyon County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

15.240.02: PERMIT REQUIRED: ... A mass grading permit is required for site grading and will only be issued for projects that have received all of the required Community Development Department approvals. ... (11) Show the elevations for top and toe of slopes with slope steepness shown. 2-feet minimum property line/fence setback from top and toe of slopes; ... (15) Any retaining walls (retaining walls over four feet (4') in height require engineering calculations to be included with the grading permit submission.

Full Breakdown

Under Lyon County Code section 15.240.04, an application for a mass grading permit, required whenever site grading precedes a non-residential building permit or otherwise disturbs the land under sections 15.240.01 and 15.240.02, must include a grading plan showing 'the elevations for top and toe of slopes with slope steepness shown' together with a minimum two-foot property line or fence setback from the top and toe of any slope. The same subsection requires that any retaining wall over four feet in height have engineering calculations included with the grading permit submission, so a homeowner building a tall retaining wall as part of a graded pad cannot rely on standard plans alone.

The grading plan must also tie proposed contours into existing ground elevations extending fifty feet beyond the site's lot lines, and show cut-and-fill quantities and on-site and off-site storm drainage improvements as required by the County Engineer. Work grading under fifty cubic yards is exempt from the mass grading permit entirely under section 15.240.03, which would cover many small residential retaining walls built without a broader grading project. Larger walls tied to graded building pads, however, fall under this permit and its four-foot engineering trigger.

This chapter applies only in unincorporated Lyon County communities such as Dayton, Silver Springs, Stagecoach, Mound House and Smith Valley; Fernley and Yerington regulate retaining walls under their own separate building codes.

Violations & Fines

Section 15.240.03B provides that exemption from the mass grading permit, including the fifty-cubic-yard threshold, does not authorize any retaining wall work done in violation of this title or any other county ordinance. A wall built over four feet without the required engineering calculations can be stopped or cited under the county's general code-enforcement authority, and the permit itself will not be issued for a project inconsistent with the site's zoning under section 15.240.02.

Frequently Asked Questions

Does Lyon County require engineering for a retaining wall?
Yes, for taller walls. Lyon County Code section 15.240.04 requires that any retaining wall over four feet in height have engineering calculations included with the mass grading permit submission. The requirement sits inside the same grading-plan checklist that covers slope elevations, cut-and-fill quantities and erosion control for the site.
Is there a setback requirement for a retaining wall near a slope?
Yes. Section 15.240.04 requires the grading plan to show a minimum two-foot property line or fence setback from the top and toe of any slope, alongside the slope's elevations and steepness. This setback applies to the grading plan generally and covers retaining walls built as part of a graded slope.
Do small retaining walls need a permit in Lyon County?
Not always. Section 15.240.03 exempts grading projects under fifty cubic yards from the mass grading permit entirely, which covers many small residential retaining walls built without a larger grading project. A wall tied to a graded building pad or a larger site disturbance, however, falls under the permit and its four-foot engineering-calculation trigger.

Sources & Official References

Other rules in Lyon County

All Lyon County rules

Compare Lyon County to another location·View the Nevada fence regulations overview

Get notified when Retaining Walls in Lyon County, NV changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.