Skip to main content
CityRuleLookup

Huntington, NY Hurricane Preparedness: Flood Elevation (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Standard elevation
2 ft above base flood elevation
Zone A, no data
3 ft above highest adjacent grade
Applies to
new construction & substantial improvements only
Enforcing official
Local Administrator (Dir. of Engineering Services)
Permit
floodplain development permit, riders on Ch. 87 permit
Fine range
$1,000-$5,000, up to 15 days jail

Summary

In Huntington's special flood hazard areas, new homes and substantially improved houses must have their lowest floor, including any basement, raised to or above two feet above the base flood elevation. Zone A parcels without published elevation data use a three-foot-above-grade standard instead.

A. Within Zones A1-A30, AE and AH and Zone A if base flood elevation data are available, new construction and substantial improvements shall have the lowest floor (including basement) elevated to or above two (2) feet above the base flood elevation. B. Within Zone A, when no base flood elevation data are available, new and substantially improved structures shall have the lowest floor (including basement) elevated at least three feet above the highest adjacent grade.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 4940543; v75 updated 2026-06-09; through 06-09-2026).

Full Breakdown

Town Code Chapter 168 sets Huntington's floodplain construction standards outside the incorporated villages of Huntington Bay, Lloyd Harbor, Northport and Asharoken, which run their own codes. Under § 168-20(A), any new construction or substantial improvement in Zones A1-A30, AE or AH, or in Zone A where base flood elevation data exist, must have the lowest floor, including a basement or cellar, elevated to or above two feet above the base flood elevation shown on the Town's Flood Insurance Rate Map. Where Zone A carries no published base flood elevation, § 168-20(B) instead requires the lowest floor elevated at least three feet above the highest adjacent grade.

Zone AO parcels use a depth-number-plus-two-feet formula under § 168-20(C), and § 168-20(D) requires drainage paths around structures on sloped AH and AO sites. Coastal high hazard Zones V1-V30, VE and V follow a separate pile-and-column elevation standard in § 168-21 rather than fill. These standards apply on top of the general anchoring, flood-resistant materials and utility-elevation rules in § 168-18 and § 168-19, and the elevation work is folded into the floodplain development building permit issued under § 168-13, which rides along with the Chapter 87 building permit at no extra fee (though the Local Administrator, the Director of Engineering Services, may require up to a $1,500 deposit for extraordinary review costs). Non-compliant construction is reported to FEMA if no variance was granted.

Violations & Fines

Under § 168-40(A), as amended by L.L. No. 56-2019, building below the required elevation is a violation punishable by a fine of not less than $1,000 nor more than $5,000, up to 15 days imprisonment, or both, with each day the violation continues counted as a separate offense. The Local Administrator may also issue a stop-work order under § 168-39, and disregarding it is a separate misdemeanor with escalating fines up to $15,000 for repeat offenses.

Frequently Asked Questions

Does Huntington's 2-foot elevation rule apply to my existing house?
No. Section 168-20 only reaches new construction and substantial improvements to structures in an area of special flood hazard; a house not undergoing a substantial improvement has no duty to raise its lowest floor.
Which Huntington flood zones require elevation to 2 feet above BFE?
Zones A1-A30, AE and AH, plus Zone A where base flood elevation data exist, require the lowest floor, including any basement, elevated to or above two feet above the base flood elevation under Town Code § 168-20(A).
What if my Huntington lot is in Zone A with no published flood elevation?
Section 168-20(B) substitutes a different measure: the lowest floor, including basement, must be elevated at least three feet above the highest adjacent grade instead of a base-flood-elevation figure.
What is the penalty for building below the required flood elevation in Huntington?
Section 168-40(A) sets a fine of $1,000 to $5,000, up to 15 days in jail, or both, and treats each day the violation continues as a separate offense, on top of possible stop-work orders.

Sources & Official References

Other rules in Huntington

All Huntington rules

New York rules heatmap·Compare Huntington to another location·View the New York hurricane preparedness overview

Get notified when Flood Elevation in Huntington, NY changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.