Construction hours in Clovis, CA, sometimes called construction noise rules or contractor work-hour ordinances, set when contractors can run power tools, hammers, and heavy equipment.

Key Facts

Weekday hours
7:00 a.m. to 7:00 p.m.
Weekend hours
9:00 a.m. to 5:00 p.m.
Summer early start
6:00 a.m. weekdays, Jun 1-Sep 15
Extended hours
Require express permit
Governing section
CMC § 5.27.604

Summary

Clovis limits construction activity to 7 a.m. to 7 p.m. weekdays and 9 a.m. to 5 p.m. on weekends, with an earlier 6 a.m. weekday start allowed from June 1 through September 15. Working outside a permit's approved hours is a nuisance violation.

Unless otherwise expressly provided by permit, construction activities are only permitted between the hours of 7:00 a.m. and 7:00 p.m. Monday through Friday and between 9:00 a.m. and 5:00 p.m. on Saturday and Sunday. From June 1st through September 15th, permitted construction activity may commence after 6:00 a.m. Monday through Friday. Extended construction work hours must at all times be in strict compliance with the permit.

Full Breakdown

m. on Saturday and Sunday. m. Monday through Friday, giving crews an earlier start during the hottest stretch of the San Joaquin Valley summer. Any extended construction work hours must at all times be in strict compliance with the permit that authorizes them, meaning a builder cannot simply decide to start earlier or work later without a permit specifically allowing it. 605 separately makes a violation of the City's decibel standards in the General Plan and Development Code a nuisance except where a special permit allows temporarily exceeding them.

Outside the permitted hours, construction tools and equipment used for alteration, construction, demolition, drilling, or repair work may not create a noise disturbance across a residential property line, and stationary equipment such as generators must be enclosed in a noise-attenuating structure near existing residences unless the Director approves otherwise.

Violations & Fines

Working outside the 7 a.m. to 7 p.m. weekday or 9 a.m. to 5 p.m. weekend window without a permit authorizing extended hours is a nuisance violation subject to citation by Clovis code enforcement or police, and the City can order the work to stop; a contractor operating stationary equipment like generators next to homes without required sound attenuation faces the same enforcement.

Frequently Asked Questions

What are the legal construction hours in Clovis, CA?
7:00 a.m. to 7:00 p.m. Monday through Friday and 9:00 a.m. to 5:00 p.m. on Saturday and Sunday under CMC § 5.27.604, unless a permit expressly allows different hours.
Can construction start earlier in Clovis during summer?
Yes. From June 1 through September 15, permitted construction activity may begin at 6:00 a.m. on weekdays instead of 7:00 a.m., per § 5.27.604.
Do I need a permit to work outside normal construction hours in Clovis?
Yes. Section 5.27.604 requires that any extended construction work hours be expressly provided by permit and stay in strict compliance with that permit's terms.

Sources & Official References

Other rules in Clovis

All Clovis rules

How Clovis compares: Cities with the Strictest Construction Hours·California rules heatmap·Compare Clovis to another location·View the California noise ordinances overview

Get notified when Construction Hours in Clovis, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Construction Hours in Nearby Cities

How other cities in Fresno County handle construction hours.

Fresno, CA
Few Restrictions