- Governing chapter
- Aliso Viejo Municipal Code Chapter 13.10 (Ord. 2017-191)
- Who runs the process
- The building official
- Checklist
- Adopted by the city and published on its website
- Association approval
- Cannot be a condition of the permit
- Use permit trigger
- Substantial-evidence finding of specific adverse health or safety impact
- Energizing
- Not allowed until the city grants approval
Summary
In the City of Aliso Viejo, California, Chapter 13.10 requires the building official to run an expedited permit process for electric vehicle charging stations, with a published checklist. Approval cannot be conditioned on association approval, and a complete application must be promptly processed. A use permit is required only on a substantial-evidence finding of a specific adverse health or safety impact.
Consistent with California Government Code Section 65850.7, the building official shall implement an expedited administrative permit review process for electric vehicle charging stations, and adopt a checklist of all requirements with which electric vehicle charging stations shall comply with in order to be eligible for expedited review. ... The city’s adopted checklist shall be published on the city’s website. ... 13.10.030 Association approval. Consistent with California Government Code Section 65850.7, the building official shall not condition the approval for any electric vehicle charging station permit on the approval of such a system by an association, as that term is defined by California Civil Code Section 4080. ... 13.10.040 Permit application processing. A permit application that satisfies the information requirements in the city’s adopted checklist shall be deemed complete and be promptly processed.
Full Breakdown
Chapter 13.10 of the Aliso Viejo Municipal Code, adopted by the Aliso Viejo City Council as Ordinance 2017-191, is the city's electric vehicle charging station permit expediting ordinance. It does not set parking space counts. It governs how the city permits charging equipment, and it ties every step to California Government Code Section 65850.7.
Under § 13.10.020, the building official must implement an expedited administrative permit review process and adopt a checklist of all requirements a station must meet to qualify. The process and checklist can refer to the "Plug-In Electric Vehicle Infrastructure Permitting Checklist" in the "Zero-Emission Vehicles in California: Community Readiness Guidebook" published by the Governor's Office of Planning and Research. The city's adopted checklist must be published on the city's website. The same expedited process is repeated in the city's amendment to Section 107.3 of Chapter 1 of the California Building Code in § 13.02.060, which also promises simplified submittal forms on the city's website.
Section 13.10.030 bars the building official from conditioning approval of any charging station permit on approval by an association, as that term is defined by California Civil Code Section 4080. Section 13.10.040 sets the processing rule: an application that satisfies the information requirements in the adopted checklist is deemed complete and promptly processed. Once the building official confirms the application and supporting documents meet the checklist and are consistent with all applicable laws, the official approves it and issues all necessary permits. Approval does not authorize the applicant to energize or use the station until the city grants approval. An incomplete application gets a written correction notice detailing every deficiency and the added information needed.
Section 13.10.050 states the intent to encourage installation by removing permitting obstacles, without superseding the building official's authority over higher priority life-safety situations. If the building official finds, based on substantial evidence, that a station could have a specific adverse impact upon public health or safety, as defined in Government Code Section 65850.7, the city can require the applicant to apply for a use permit.
Violations & Fines
Chapter 13.10 prints no penalty of its own. Section 109.4 of the California Building Code Chapter 1, as amended by § 13.02.060, treats failure to pay fees and obtain a permit before commencing work as a violation, and an assessment can include double the required permit fees for work on a building, structure, mechanical, gas, electrical or plumbing system started before permits are issued. Paying the assessment does not excuse full compliance.
Frequently Asked Questions
Does the City of Aliso Viejo require a permit for an EV charger?
Can an association block an EV charger permit in Aliso Viejo?
Can I switch on the charger as soon as the permit is approved?
When does Aliso Viejo require a use permit for a charging station?
Sources & Official References
Other rules in Aliso Viejo
California rules heatmap·Compare Aliso Viejo to another location·View the California parking rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
EV Charging in Nearby Cities
How other cities in Orange County handle ev charging.