Garden Grove, CA Sidewalk & Pedestrian Rules: Encroachment Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified August 2026

Key Facts

Permit
Written encroachment permit required
Application
Must state nature, purpose, duration, location
Cost
Fee plus City-approved performance bond
Insurance
Set by City Engineer per project risk
Revocation
City may revoke and require removal anytime
Citation
Municipal Code Sec. 11.12.010

Summary

Placing any temporary structure, appliance, or permanent improvement in a Garden Grove street or right-of-way, from a private structure to an outdoor dining encroachment, requires a written encroachment permit from the City under Municipal Code Section 11.12.010, plus a permit fee, a performance bond, and liability insurance sized to the project's risk.

§ 11.12.010. Permit Required. A. No person shall erect or maintain any temporary structure or appliance in, upon, over, along, or across any street, nor erect or maintain any permanent structure within the planned right-of-way, except as otherwise provided by law, without filing a written application and obtaining a written permit therefor from the City. ... D. Any permit granted under this section shall specify: 1. The nature of the structure or appliance. 2. The purpose for which it will be erected or maintained. 3. The time during which such structure may be maintained. 4. The location thereof. ... F. No permit granted under this section shall be issued until the person applying for it has paid a fee in an amount set by City Council resolution for the issuance of each permit, and has also executed a good and sufficient bond to the City... G. The City may revoke the permit at any time. Prior to the expiration date of the permit or at the revocation of the same, the structure or appliance shall be wholly removed from the location stated in the permit.

Full Breakdown

010 sets the baseline: no person may erect or maintain a temporary structure or appliance in, upon, over, along, or across any street, or a permanent structure within the planned right-of-way, without first filing a written application and obtaining a written permit from the City. The application must describe the structure and its purpose and include a map or diagram of its location, and any permit the City issues must specify the nature of the structure, its purpose, how long it may stay in place, and its exact location.

No permit is issued until the applicant pays a fee set by City Council resolution and executes a bond, with at least two City-approved sureties, holding the City and its officers harmless from costs or damages arising from the encroachment. 121 adds that liability insurance coverage standards for encroachment permits are set by the City Engineer based on the degree of risk the particular project poses to the City. The City can revoke an encroachment permit at any time, and once a permit expires or is revoked, the structure or appliance must be wholly removed from the permitted location.

170, covers unpermitted obstructions placed directly in a dedicated street right-of-way: the City can give the responsible party 10 calendar days' written notice to remove it, and if that deadline passes, remove or relocate the obstruction itself and bill the owner for the cost. 010 framework.

Violations & Fines

Erecting or maintaining an unpermitted structure or appliance in a Garden Grove street or right-of-way violates Section 11.12.010 and is enforceable under the citywide general penalty, Section 1.04.010, as a misdemeanor carrying up to a $1,000 fine and six months in county jail, or as an infraction at the City Attorney's discretion. Unpermitted obstructions can also be removed by the City under Section 11.04.170 after 10 days' notice, with removal costs billed to the responsible party.

Frequently Asked Questions

Do I need a permit to put a structure in the Garden Grove right-of-way?
Yes. Section 11.12.010 requires a written encroachment permit from the City before erecting or maintaining any temporary structure or appliance in, upon, over, along, or across a street, or a permanent structure within the planned right-of-way, whether it's for private use or a business use like outdoor dining.
What does it cost to get an encroachment permit?
The applicant pays a permit fee set by City Council resolution and must post a bond, with at least two City-approved sureties, that protects the City from costs or damages tied to the encroachment. Section 11.12.121 also requires liability insurance sized by the City Engineer to the project's risk level.
Can the City remove a structure I put in the right-of-way without a permit?
Yes. Under Section 11.04.170 the City gives written notice to remove an unpermitted obstruction within 10 calendar days; if you don't comply, the City can remove or relocate it itself and bill you for the cost, separate from any misdemeanor or infraction charge under the general penalty section.

Sources & Official References

Other rules in Garden Grove

All Garden Grove rules

California rules heatmap·Compare Garden Grove to another location·View the California sidewalk & pedestrian rules overview

Get notified when Encroachment Permits in Garden Grove, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Encroachment Permits in Nearby Cities

How other cities in Orange County handle encroachment permits.

Irvine, CA
Some Restrictions
Santa Ana, CA
Some Restrictions
Fullerton, CA
Some Restrictions
Huntington Beach, CA
Some Restrictions
Anaheim, CA
Some Restrictions
Mission Viejo, CA
Some Restrictions
Costa Mesa, CA
Significant Restrictions
Orange, CA
Significant Restrictions