Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Permit trigger
Any walk/drive/curb/gutter work on public property
Issuing office
Building inspection department
Tied to a building permit
Contractor's voucher, no extra fee
No building permit
Standalone concrete permit + Master Fee Schedule fee
Contractor requirement
Must be registered, bonded
Reinspection fee
Due before 3rd and later reinspections

Summary

Before anyone builds, alters or resurfaces a walk, drive, curb, gutter or paved area on public property in Richardson, the building inspection department has to authorize it first. That happens either through a contractor's voucher tied to an existing building permit, at no extra charge, or through a standalone concrete permit with a fee from the Master Fee Schedule.

No person shall construct, reconstruct, alter, repair, remove, replace, pave, repave, surface, or resurface any walk, drive, curb, gutter, paved area, or appurtenances on public property in the city without first obtaining from the building inspection department authorization to do such work... (2) When work is to be done and no building permit is required, a concrete permit must be obtained from the building inspection department prior to commencing of work. The application for a permit must be in writing on forms provided by the building inspection department and a fee set forth in the Master Fee Schedule shall be paid.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 35 Update 2).

Full Breakdown

Section 20-36 requires city authorization before any walk, drive, curb, gutter, paved area or appurtenance on public property is constructed, reconstructed, altered, repaired, removed, replaced, paved, repaved, surfaced or resurfaced, essentially the city's mechanism for letting a private property owner build or maintain improvements that sit in the public right-of-way in front of their lot, such as a driveway approach or a section of public sidewalk. There are two paths to authorization. If the concrete work is part of a project already covered by a building permit, the bonded concrete contractor files a contractor's voucher with the building inspection department before the required inspection, and no additional fee applies.

If no building permit is involved, the applicant must obtain a standalone concrete permit before starting work, applying in writing on city forms and paying the fee set in the Master Fee Schedule. Every concrete contractor doing this work must be registered with the building inspection department and must furnish a list of authorized representatives who can sign vouchers or applications on the contractor's behalf. Section 20-37 can require an applicant to submit a scaled lot or plot plan showing the proposed work, existing structures, and utilities to the street centerline. Section 20-13 separately bars mixing concrete or leaving concrete residue on public pavement, requiring immediate cleanup of any spill.

Violations & Fines

It is unlawful under section 20-36(e) to pour concrete on public property without inspection and approval from the building inspection department. When a reinspection turns up uncorrected work, a reinspection fee is due before the third reinspection and every one after that. Because chapter 20 carries no chapter-specific fine, the general penalty in section 1-8 applies: a misdemeanor punishable by a fine of up to $500, with each day of an ongoing violation counted separately.

Frequently Asked Questions

Do I need a permit to pour a new driveway apron in Richardson?
Yes. Section 20-36 requires authorization from the building inspection department before any walk, drive, curb, gutter or paved area on public property is built or altered, whether that's a fresh driveway approach or repaired curb.
Is there always a fee?
Not always. If the concrete work is covered under an existing building permit, the contractor files a voucher at no additional charge; standalone concrete work requires its own permit with a fee set in the Master Fee Schedule.
Who can pull the permit, me or my contractor?
The bonded concrete contractor typically files the voucher or application, and must be registered with the building inspection department along with a list of authorized signers.
What happens if the inspector rejects the work twice?
A reinspection fee applies before the third reinspection and every subsequent one, payable by the responsible contractor under section 20-36(d).

Sources & Official References

Other rules in Richardson

All Richardson rules

Texas rules heatmap·Compare Richardson to another location·View the Texas sidewalk & pedestrian rules overview

Get notified when Encroachment Permits in Richardson, TX changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Encroachment Permits in Nearby Cities

How other cities in Dallas County handle encroachment permits.

Grand Prairie, TX
Some Restrictions
Garland, TX
Some Restrictions
Irving, TX
Some Restrictions
Dallas, TX
Significant Restrictions