Key Facts

Responsible party
Abutting property owner
Permit issuer
Township Engineer, written permit
Permit validity
Three months from issuance
Contractor bond
$1,000, one year, approved by Township Attorney
Out-of-grade sidewalk
Relay within 30 days after Engineer's notice
Concrete work blackout
December 1 to April 1, emergency flag repairs excepted

Summary

In Bloomfield Township, New Jersey, installing, repairing and replacing curbs and sidewalks is the responsibility of the abutting property owner. A written permit signed by the Township Engineer is required before any sidewalk, curb, driveway, gutter or drain across the sidewalk space is laid, and each permit is valid for three months.

A. The installation, repair or replacement of curbs and sidewalks is the responsibility of the abutting property owner. ... B. No sidewalk, curb, driveway, gutter or drain across the sidewalk space shall be laid in any street in the Township until a written permit, signed by the Township Engineer, shall have been issued. All such permits shall be valid for three months from the date of issuance.

Full Breakdown

The Bloomfield Township Code leaves sidewalk upkeep with the owner next door, not with the Township. Section 497-16(A) states that the installation, repair or replacement of curbs and sidewalks is the responsibility of the abutting property owner. Subsection B then requires a written permit signed by the Township Engineer before any sidewalk, curb, driveway, gutter or drain across the sidewalk space is laid in any street, and the permit lasts three months from issuance.

The application goes to the Township Engineer on a blank form provided by the Township (§ 497-17). It must specify the location, material and width of the work and the size of any drain across the sidewalk space. A contractor cannot receive a permit until a $1,000 bond with a responsible surety company is on file with the Township Engineer, covering all work under the article for one year, and the Township Attorney approves the bond (§ 497-18). The work is done under the Township Engineer's supervision, with materials and workmanship inspected and approved (§ 497-19), and lines and grades are furnished without a fee (§ 497-20).

The Township can force a repair. A sidewalk that is out of line or grade must be relaid by the property owner within 30 days after notice from the Township Engineer, unless the owner gives the Township Council satisfactory reasons for not doing the work (§ 497-21). Concrete work cannot be done from December 1 to April 1, though emergency repairs to flag sidewalks are allowed (§ 497-24).

Build standards apply to new walks: not less than four feet wide, concrete unless the Council authorizes flag, and concrete not less than three inches thick (§ 497-28). Bluestone is protected by § 497-6.1: removal or reconstruction needs a written permit from the Township Engineer, and in the Historic District the walk must be replaced with similar bluestone. Cutting into a sidewalk also requires an excavation permit under § 497-6. In designated streetscape areas, § 497-56 puts repair on the fronting property owner or business owner.

Violations & Fines

Article V violations are punished under § 497-32, which refers to the general penalty in § 1-15 of the Code: a fine not exceeding $2,000, imprisonment not exceeding 90 days, community service not exceeding 90 days, or a combination. Each day a violation continues is a separate offense unless otherwise provided. Excavating a sidewalk without the Township Engineer's permit falls under § 497-6 and the penalty in § 497-7.

Frequently Asked Questions

Who pays to fix the sidewalk in front of my house in Bloomfield Township?
The abutting property owner. Section 497-16(A) says the installation, repair or replacement of curbs and sidewalks is the responsibility of the abutting property owner. The Township does not take over that cost under this section, and a sidewalk that is out of line or grade must be relaid by the owner after notice from the Township Engineer.
Do I need a permit to replace a sidewalk in Bloomfield Township?
Yes. No sidewalk, curb, driveway, gutter or drain across the sidewalk space can be laid in any street until a written permit signed by the Township Engineer has been issued. The permit is valid for three months from issuance. A contractor must also file a $1,000 bond with the Township Engineer before the permit is granted.
How long do I have to repair a sidewalk after the Township sends notice?
Under § 497-21, a sidewalk in a public street that is out of line or grade must be relaid by the property owner within 30 days after notice from the Township Engineer. The one escape is giving the Township Council satisfactory reasons for the work not being done, so the request goes to the Council, not the Engineer.
Can I remove a bluestone sidewalk in Bloomfield Township?
Only with a written permit from the Township Engineer, and the removed bluestone must be delivered to the Township at a location the Engineer designates. In the Historic District, removal is allowed only if the walk is replaced with a similar bluestone sidewalk, and the Engineer consults the Historic Preservation Commission before issuing the permit.

Sources & Official References

Other rules in Bloomfield

All Bloomfield rules

Compare Bloomfield to another location·View the New Jersey sidewalk & pedestrian rules overview

Get notified when Sidewalk Repair in Bloomfield, NJ changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Sidewalk Repair in Nearby Cities

How other cities in Essex County handle sidewalk repair.

Newark, NJ
Some Restrictions