New Jersey Statewide Rule
New Jersey Stormwater Management Rules Statewide Standards
Key Facts
- Code
- N.J.A.C. 7:8
- Regulator
- NJ DEP
- Permit framework
- NJPDES MS4
- Triggers at
- Major development
Summary
New Jersey Stormwater Management Rules at N.J.A.C. 7:8 set uniform statewide design and water-quality standards that municipalities must adopt by ordinance, preventing cities from weakening these baseline requirements.
40:55D-93. Preparation; storm water control ordinances to implement; date of completion; reexamination Every municipality in the State shall prepare a storm water management plan and a storm water control ordinance or ordinances to implement said plan. Such a storm water management plan shall be completed within 1 year from the date of promulgation of comprehensive storm water management regulations by the Commissioner of the Department of Environmental Protection, or by the next reexamination of the master plan required pursuant to section 76 of P.L.1975, c. 291 (C. 40:55D-89), whichever shall be later, provided that a grant for the preparation of the plan has been made available pursuant to section 6 hereof. The plan shall be reexamined at each subsequent scheduled reexamination of the master plan pursuant thereto. Such a storm water control ordinance or ordinances shall be adopted within 1 year of the completion of the storm water management plan and shall be revised thereafter as needed.
Full Breakdown
Under the Stormwater Management Act and N.J.A.C. 7:8, the Department of Environmental Protection sets uniform standards for major development, including groundwater recharge, runoff quantity, and water-quality treatment. Every NJ municipality must adopt a model stormwater control ordinance and a Municipal Stormwater Pollution Prevention Plan as conditions of its NJPDES Tier A or Tier B MS4 permit. Local rules can be more protective but cannot fall below state minimums for green infrastructure and pollutant removal.
Violations & Penalties
Failure to comply can result in DEP penalties, NJPDES permit enforcement, project stop-work orders, and required retrofits.
Frequently Asked Questions
What counts as major development for NJ stormwater rules?
Can my town opt out of state stormwater standards?
Sources
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.