Key Facts

Permit issuer
City of Alhambra Building Official
Governing chapter
Municipal Code Chapter 20.05, Building Code Section 107
Permit expiration
1 year after last required inspection
Work start deadline
Must commence within 1 year of issuance
Late-restart fee cap
25% of original permit fee
Base code adopted
L.A. County Code Title 26

Summary

Alhambra's Building Code bars anyone from erecting, altering, enlarging, repairing, moving, demolishing or grading any building or structure without first obtaining a separate permit from the Building Official for each structure or grading operation. Permits automatically expire one year after the last required inspection or if work never starts within a year of issuance.

107.1 Permit Required. No person, shall erect, construct, enlarge, alter, repair, move, improve, remove, connect, convert, demolish, or equip any building, structure, or portion thereof, perform any grading, or cause the same to be done, without first obtaining a separate permit for each such building, structure or grading from the Building Official... 107.6 Expiration of Permit. Every permit issued by the building official under the provisions of this Code shall expire automatically by limitation and become null and void one year after the date of the last required building inspection approval by the building official or if work authorized by such permit is not commenced within one year from the issuance date of such permit. Before such work can be commenced or recommenced, a new permit shall be first obtained.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: 2026 S-25: Supplement contains: Local legislation current through Ord. 4851, passed 10-27-25).

Full Breakdown

Section 107.1 of the Building Code, adopted as Alhambra Municipal Code Chapter 20.05 (the Los Angeles County Code, Title 26, as locally amended), requires a separate permit before any person erects, constructs, enlarges, alters, repairs, moves, improves, removes, connects, converts, demolishes, or equips a building, structure or portion of one, or performs grading. A permit for an automatic fire-protection system likewise needs its own separate application. Before issuance, the Building Official must confirm the work conforms to the Code, that fees set by resolution are paid, and, where applicable, that a Coastal Act permit under Public Resources Code Section 30600 has been obtained (Section 107.4).

Roughly two dozen minor categories are exempt from a building permit outright under Section 107.2, including one-story accessory sheds under 120 square feet, fences and retaining walls below set height thresholds, and portable playground equipment, though separate plumbing, electrical or mechanical permits can still apply. Once issued, a permit expires automatically one year after the date of the last required inspection approval, or one year after issuance if work never commences (Section 107.6); resuming expired work needs a new permit, with a plan-review or permit fee capped at 25% of the original if requested within a year and unchanged plans.

The Building Official may also suspend or revoke a permit issued in error, based on false information, or where work violates approved plans (Section 107.7), and an unused permit can be cancelled by the applicant for a refund of fees other than issuance fees (Section 107.8).

Violations & Fines

Working without the required permit, continuing after a permit is suspended or revoked, or occupying unpermitted work exposes the owner or contractor to prosecution as a misdemeanor or infraction and to stop-work orders from the Building Official. Alhambra Municipal Code Section 20.05.050 sets penalties for Building Code violations, and any unpermitted structure remains subject to enforcement, correction orders, and re-inspection fees until it is brought into compliance and finaled.

Frequently Asked Questions

Does Alhambra require a permit for every building project?
Yes, with limited exceptions. Building Code Section 107.1 requires a separate permit from the Building Official for erecting, altering, enlarging, repairing, moving, or demolishing any building, structure or portion of one, or for grading. Section 107.2 lists roughly two dozen minor exemptions, such as small accessory sheds and low fences.
How long is an Alhambra building permit valid?
A permit expires automatically one year after the date of the last required building inspection approval, or one year after issuance if the authorized work never commences, per Building Code Section 107.6. Restarting expired work requires a new permit and possible additional fees.
Can Alhambra revoke a building permit already issued?
Yes. Under Section 107.7, the Building Official may suspend or revoke a permit in writing if it was issued in error, based on incorrect information, or if the work violates the approved plans, other laws, or the Building Code itself.

Sources & Official References

Other rules in Alhambra

All Alhambra rules

California rules heatmap·Compare Alhambra to another location·View the California building safety overview

Get notified when Building Permits in Alhambra, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Permits in Nearby Cities

How other cities in Los Angeles County handle building permits.

Carson, CA
Some Restrictions
Compton, CA
Some Restrictions
Downey, CA
Some Restrictions
El Monte, CA
Some Restrictions
Inglewood, CA
Some Restrictions
Lakewood, CA
Some Restrictions
Lancaster, CA
Some Restrictions
Long Beach, CA
Some Restrictions