Key Facts

Permit required for
Construct/enlarge/alter/repair/move/demolish/change occupancy
Citation
Barrow County Code § 22-91(a)
Building official
Director, County Licenses & Permits Dept.
Permit expires
6 months unused or suspended
Extension
90 days each, written justified request
Unpermitted-work penalty
100% of usual fee (§ 22-97(b))
Minor repairs
Exempt with official's approval (§ 22-91(c))

Summary

In unincorporated Barrow County, anyone who wants to construct, enlarge, alter, repair, move, demolish or change the occupancy of a building or structure, or install a covered electrical, gas, mechanical or plumbing system, must first apply to the county building official and obtain a permit (§ 22-91(a)). Ordinary minor repairs are exempt, but only with the building official's approval.

These county ordinances apply to unincorporated areas of Barrow County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

(a)Permit required; application. Any owner, authorized agent or contractor who desires to construct, enlarge, alter, repair, move, demolish or change the occupancy of a building or structure or to erect, install, enlarge, alter, repair, remove, convert or replace any electrical, gas, mechanical or plumbing system, the installation of which is regulated by the technical codes or to cause any such work to be done, shall first make application to the building official and obtain the required permit for the work. ... (b)Penalty for commencing work before obtaining permit. Any person who commences any work on a building, structure or electrical, gas, mechanical, plumbing, etc., system before obtaining the necessary permits shall be subject to a penalty of 100 percent of the usual permit fee in addition to the required permit fees.

Full Breakdown

" The application must be filed on the county's form with the required fee, contain a general description and location of the work, and be signed by the owner or an authorized agent (§ 22-91(d)). The building official who reviews it is the director of the county licenses and permits department (§ 22-34(a)(3)). A permit is void if work is not started within six months of issuance, or is suspended for six months once started, though the official may grant one or more 90-day extensions for written, justified requests (§ 22-91(e), § 22-96(a)).

Ordinary minor repairs can skip the permit only with the building official's sign-off, and only if they don't violate the technical codes (§ 22-91(c)). If the submitted plans don't conform to the technical codes, the official must deny the permit and, on request, give the reason for refusal in writing (§ 22-94(b)); conversely, an applicant waiting on full plan approval can get a special foundation-only permit at the official's discretion, at the applicant's own risk (§ 22-94(c)). Encroachments on public right-of-way additionally require the applicant to get the public works director's street lines before a permit issues (§ 22-94(d)). Fees are set by the board of commissioners and must be paid before the permit is issued (§ 22-97(a)).

Violations & Fines

Starting work before obtaining the permit triggers a penalty equal to 100 percent of the usual permit fee in addition to the fee itself (§ 22-97(b)), and the building official can issue an immediate stop-work order, with no written notice required first if an emergency exists (§ 22-63). Violating the technical codes generally is also a misdemeanor under § 22-38, with each day of continued violation a separate offense.

Frequently Asked Questions

When do I need a building permit in unincorporated Barrow County?
Any time you construct, enlarge, alter, repair, move, demolish or change the occupancy of a building or structure, or install a covered electrical, gas, mechanical or plumbing system, you must apply to the building official first and get the permit before doing the work (§ 22-91(a)).
Are small repairs exempt from the permit requirement?
Ordinary minor repairs can be done without a permit, but only with the building official's approval and only if they don't violate the technical codes (§ 22-91(c)); anything beyond a minor fix still needs a filed application and fee.
What if I do the work before the permit is issued?
The building official can deny the permit or issue a stop-work order, and once you do apply, you owe a penalty equal to 100 percent of the normal permit fee on top of the fee itself (§ 22-97(b)), separate from misdemeanor exposure under § 22-38.
How long does a Barrow County building permit stay valid?
It expires if the authorized work hasn't started within six months of issuance, or if the work is suspended or abandoned for six months once started (§ 22-91(e)). The building official may grant one or more 90-day extensions on a written, justified request.

Sources & Official References

Other rules in Barrow County

All Barrow County rules

Compare Barrow County to another location·View the Georgia building safety overview

Get notified when Building Permits in Barrow County, GA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.