Key Facts

Adopted code
National Electrical Code
Citation
Barrow County Code § 22-31(a)(5)
Inspections required
5: pole, underground, rough-in, permanent, final
Concealment ban
Before required inspection clears (§ 22-98(h))
Contractor licensing
State license number required before permit (§ 22-95)

Summary

Unincorporated Barrow County enforces the National Electrical Code as one of its technical codes (§ 22-31(a)(5)), applying it to "the installation of electrical systems, including alterations, repairs, replacement" and related equipment (§ 22-34(a)(4)). Electrical work needs the same building-official permit as other technical-code work, checked through five staged inspections.

These county ordinances apply to unincorporated areas of Barrow County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

(a)The latest edition of the following codes, as adopted and amended by the state department of community affairs, shall be enforced by the county:(1)Standard Building Code;(2)Standard Mechanical Code;(3)Standard Gas Code;(4)Standard Plumbing Code;(5)National Electrical Code; ... (4)Applicability of National Electrical Code. The provisions of the National Electrical Code, as amended, shall apply to the installation of electrical systems, including alterations, repairs, replacement, equipment, appliances, fixtures, fittings and appurtenances thereto. ... (2)Electrical inspections.a.Temporary power pole inspection. To be made after the pole is in place.b.Underground inspection. To be made after trenches or ditches are excavated and conduit or cable is installed and before any backfill is put in place. ... d.Permanent power inspection. To be made after all required electrical fixtures are in place and properly connected or protected and the meter base is set and properly secured to the structure.e.Final inspection. To be made after the building is complete, all required electrical fixtures are in place and properly connected or protected and the structure is ready for occupancy.

Full Breakdown

The county adopts "the latest edition" of the National Electrical Code, "as adopted and amended by the state department of community affairs" (§ 22-31(a)(5)), and applies it to "the installation of electrical systems, including alterations, repairs, replacement, equipment, appliances, fixtures, fittings and appurtenances thereto" (§ 22-34(a)(4)). Because the NEC is one of the article's technical codes, any covered electrical job needs a permit from the building official before work starts (§ 22-91(a)), and a contractor doing that work must supply the county with a state license number before the permit issues (§ 22-95).

The building official then walks the job through five staged inspections under § 22-98(f)(2): a temporary power pole inspection once the pole is set; an underground inspection after conduit or cable is installed and before backfill covers it; a rough-in inspection once framing, fire blocking and bracing are up and before wall or ceiling membranes are installed; a permanent power inspection once required fixtures are connected and the meter base is secured to the structure; and a final inspection once the building is complete and ready for occupancy.

Work cannot proceed past any of these points without the building official's written release, and reinforcing steel, insulation or electrical system work cannot be covered or concealed without that release either (§ 22-98(g)-(h)). A certificate of occupancy will not issue under § 22-99 until the electrical system, along with the other required systems, has been inspected and released for compliance with the technical codes.

Violations & Fines

Covering wiring or conduit before the building official releases the underground or rough-in inspection violates § 22-98(h). Connecting permanent power before the permanent-power inspection clears is a technical-code violation punishable as a misdemeanor under § 22-38, and starting electrical work without a permit adds the 100-percent late-permit penalty under § 22-97(b).

Frequently Asked Questions

What electrical code does Barrow County enforce?
The county has adopted the National Electrical Code as amended by the state, applying it to "the installation of electrical systems, including alterations, repairs, replacement, equipment, appliances, fixtures, fittings and appurtenances" (§ 22-31(a)(5), § 22-34(a)(4)) for any covered electrical work in the unincorporated area.
What electrical inspections does a project have to pass?
Five, in order: the temporary power pole once set, an underground inspection before backfill covers conduit or cable, a rough-in inspection before wall or ceiling membranes go up, a permanent power inspection once fixtures are connected and the meter base secured, and a final inspection before occupancy (§ 22-98(f)(2)).
Do electricians need a state license to pull a Barrow County permit?
Yes. Any contractor who installs or repairs electrical systems under a permit must supply the county with a state license number before the building official will issue the permit (§ 22-95), on top of complying with the technical codes themselves.

Sources & Official References

Other rules in Barrow County

All Barrow County rules

Compare Barrow County to another location·View the Georgia building safety overview

Get notified when Electrical Permits in Barrow County, GA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.