Building stages
Foundation, slab, frame, final
Enforcing official
Building official
No-permit penalty
100% of permit fee (§ 22-97)
Concealment rule
Written release required before covering work
Permit card
Must be posted on-site until CO issues

Summary

In unincorporated Barrow County, the building official inspects construction at set stages under Barrow County Code § 22-98: foundation, slab, frame and final for building work, plus matching stage inspections for electrical, plumbing, mechanical and gas systems before any covering or occupancy.

These county ordinances apply to unincorporated areas of Barrow County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

(f)Required inspections. The building official, upon notification from the permit holder or his agent, shall make the following inspections and such other inspections as necessary, and shall either release that portion of the construction or shall notify the permit holder or his agent of any violations which must be corrected in order to comply with the technical code:(1)Building inspections.a.Foundation inspection. To be made after trenches are excavated and forms erected, after the foundation walls are erected and before the backfill is placed.b.Slab inspection. To be made after trenches are excavated, forms are erected, plumbing lines are backfilled, gravel is in place and the vapor barrier is in place.c.Frame inspection. To be made after the roof and all framing, fire blocking and bracing are in place, all concealed wiring and all pipes, chimneys, ducts, vents and three-quarter siding are complete.d.Final inspection. To be made after the building is completed and ready for occupancy.

Full Breakdown

Barrow County Code § 22-98 lays out the inspection sequence the building official runs on every permitted project in unincorporated Barrow County. For building work the required stops are the foundation inspection, made after trenches are excavated and forms erected but before backfill; the slab inspection, made after trenches, forms, backfilled plumbing lines, gravel and the vapor barrier are in place; the frame inspection, made once the roof, framing, fire blocking, bracing, concealed wiring, pipes, chimneys, ducts, vents and siding are complete; and the final inspection, made once the building is ready for occupancy.

Electrical, plumbing, mechanical and gas systems each carry their own underground, rough-in and final stages under the same section, and energy work gets a frame and final check on wall insulation, sealing and equipment SEER ratings. Under subsection (g), work cannot proceed past the point covered by an inspection without a written release from the building official, and subsection (h) bars covering or concealing reinforcing steel, structural frame, insulation, or plumbing, mechanical or electrical work before that release issues. The permit holder or agent must post the permit card on the premises before work starts and keep it there until a certificate of occupancy or completion is issued (subsection (e)).

The building official inspects under subsection (d) at various intervals during the work and again at final completion, before a certificate of occupancy or completion can be issued under § 22-99. He may also accept reports from recognized private inspection services if satisfied as to their qualifications and reliability, but a certificate cannot rest on such a report unless it is written and signed by a responsible officer of that service (subsection (c)).

Violations & Fines

Proceeding past an inspection point, or covering reinforcing steel, framing, insulation or plumbing/mechanical/electrical work, without a written release from the building official violates § 22-98(g)-(h). Section 22-97(b) separately penalizes commencing any work before obtaining the required permit at 100 percent of the usual permit fee, on top of the fee itself; the building official can also withhold the certificate of occupancy under § 22-99 until every required inspection is released.

Frequently Asked Questions

What inspection stages apply to a new house in unincorporated Barrow County?
Barrow County Code § 22-98(f)(1) requires a foundation inspection before backfill, a slab inspection once plumbing lines, gravel and the vapor barrier are in, a frame inspection once framing and rough systems are complete, and a final inspection before occupancy.
Can a contractor cover framing or wiring before the county inspects it?
No. Section 22-98(h) prohibits covering or concealing reinforcing steel, structural frame, insulation, or plumbing, mechanical or electrical work until the building official issues a written release under subsection (g).
What happens if work starts before a permit is issued?
Section 22-97(b) imposes a penalty equal to 100 percent of the usual permit fee, charged in addition to the required permit fees, for commencing work before obtaining the necessary permit.
Who can perform inspections besides the county building official?
Under § 22-98(c), the building official may accept reports from recognized private inspection services if satisfied of their qualifications, but any certificate based on such a report must be in writing and signed by a responsible officer of that service.

Sources & Official References

Other rules in Barrow County

All Barrow County rules

Compare Barrow County to another location·View the Georgia building safety overview

Get notified when Building Inspections in Barrow County, GA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.