Key Facts

Adopted code
Standard Plumbing Code, with 8 appendices
Citation
Barrow County Code § 22-31(a)(4)
Inspections required
Underground, rough-in, final (§ 22-98(f)(3))
Required tests
Sec. 417 of the Standard Plumbing Code
Self-inspection
County opted out of O.C.G.A. § 8-2-26(d) (§ 22-4)

Summary

Barrow County enforces the Standard Plumbing Code as one of its technical codes (§ 22-31(a)(4)), applying it to "every plumbing installation, including alterations, repairs, replacement" connected to water or sewer service (§ 22-34(a)(7)). Plumbing work needs a building-official permit checked through underground, rough-in and final inspections plus the code's own required tests.

These county ordinances apply to unincorporated areas of Barrow County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

(4)Standard Plumbing Code. ... (7)Applicability of Standard Plumbing Code. The provisions of the Standard Plumbing Code, as amended, shall apply to every plumbing installation, including alterations, repairs, replacement, equipment, appliances, fixtures, fittings and appurtenances, and when connected to a water or sewerage system. ... The county is exempted from the provisions of O.C.G.A. § 8-2-26(d) relating to the self-inspection of certain water and sewer lines, and such provisions shall not be applicable in the county. ... (3)Plumbing inspections.a.Underground inspection. To be made after trenches or ditches are excavated and piping installed and before any backfill is put in place.b.Rough-in inspection. To be made after the roof, framing, fire blocking, three-quarter siding and bracing is in place and all soil, waste and vent piping is complete and prior to the installation of wall or ceiling membranes.c.Final inspection. To be made after the building is complete, all plumbing fixtures are in place and properly connected and the structure is ready for occupancy.d.Required tests. See section 417 of the Standard Plumbing Code for required tests.

Full Breakdown

The county adopts "the latest edition" of the Standard Plumbing Code, along with its appendices A through G and J (§ 22-31(a)(4), (b)(3)), and applies it to "every plumbing installation, including alterations, repairs, replacement, equipment, appliances, fixtures, fittings and appurtenances, and when connected to a water or sewerage system" (§ 22-34(a)(7)). Plumbing falls under the same permit rule as other technical-code work: an owner, agent or contractor must apply to the building official and obtain a permit before starting (§ 22-91(a)). The building official then runs three staged plumbing inspections under § 22-98(f)(3): an underground inspection after trenches are excavated and piping installed but before backfill; a rough-in inspection once framing and bracing are up and all soil, waste and vent piping is complete, before wall or ceiling membranes go in; and a final inspection once fixtures are connected and the building is ready for occupancy.

The code cross-references its own testing standard, directing inspectors to "section 417 of the Standard Plumbing Code for required tests" on top of the visual inspections. " That means those lines still go through the building official's own inspection rather than a contractor's self-certified sign-off, regardless of what state law allows elsewhere in Georgia.

Violations & Fines

Covering underground piping or closing walls before the rough-in inspection clears is a technical-code violation under § 22-98(h). Connecting fixtures before the final plumbing inspection, or starting work without a permit at all, adds the 100-percent late-permit penalty under § 22-97(b) on top of misdemeanor exposure under § 22-38.

Frequently Asked Questions

What plumbing code applies in unincorporated Barrow County?
The county enforces the Standard Plumbing Code as amended by the state, applying it to "every plumbing installation, including alterations, repairs, replacement, equipment, appliances, fixtures, fittings and appurtenances" connected to water or sewer service (§ 22-31(a)(4), § 22-34(a)(7)).
What plumbing inspections does the county require?
Three staged inspections: underground, before backfill covers the piping; rough-in, once framing is up and all soil, waste and vent piping is complete but before walls are closed; and final, once fixtures are connected and the building is ready for occupancy (§ 22-98(f)(3)).
Can a licensed plumber self-inspect their own water and sewer line work here?
No. Barrow County opted out of the state law that allows self-inspection of certain water and sewer lines: § 22-4 exempts the county from O.C.G.A. § 8-2-26(d), so those lines still go through the building official's inspection rather than a contractor's self-certification.

Sources & Official References

Other rules in Barrow County

All Barrow County rules

Compare Barrow County to another location·View the Georgia building safety overview

Get notified when Plumbing Permits in Barrow County, GA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.