Key Facts

Governing section
Bulloch County Code § 4-50(a)(1)
Permit issued by
Bulloch County Building Official
Application review time
5 working days (Sec. 4-51(a)(2))
Permit expires
6 months if work not started
Maximum penalty
$1,000 fine, 60 days jail (Sec. 1-11)

Summary

In unincorporated Bulloch County, anyone who intends to construct, enlarge, alter, repair, move, demolish or change the occupancy of a building or structure, or install a regulated electrical, gas, mechanical or plumbing system, must first apply to the building official and obtain a permit under Sec. 4-50(a)(1) before work starts.

These county ordinances apply to unincorporated areas of Bulloch County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

(a)When required.(1)Any owner or authorized agent who intends to construct, enlarge, alter, repair, move, demolish or change the occupancy of a building or structure, or to erect, install, enlarge, alter, repair, remove, convert, or replace any electrical, gas, mechanical or plumbing system, the installation of which is regulated by the International Residential Code, or to cause any such work to be done, shall first make application to the building official and obtain the required permit. ... (3)Work exempt from a permit includes those items listed in the administration section of the International Residential Code.

Full Breakdown

Bulloch County Code Section 4-50, in the technical codes division of Chapter 4, sets the trigger for when a building permit is required in the unincorporated area. Subsection (a)(1) requires any owner or authorized agent who intends to construct, enlarge, alter, repair, move, demolish or change the occupancy of a building or structure, or to erect, install, enlarge, alter, repair, remove, convert or replace an electrical, gas, mechanical or plumbing system regulated by the International Residential Code, to first apply to the building official and obtain the permit before the work begins.

Subsection (a)(3) exempts only the specific items listed in the administration section of the International Residential Code, so most residential and accessory construction, including additions, remodels and system replacements, needs a permit unless that IRC exemption list applies. Sec. 4-50(a)(6) also blocks any application from an applicant currently in violation of the Bulloch County Code of Ordinances until the violation is cleared and the building official issues a release. Applications must identify the applicant and owner, describe the proposed work, and, when required, include scaled drawings sealed by a Georgia-registered design professional.

Under Sec. 4-51(a)(2), the building official must examine a complete application within five working days and, if the work will comply, approve it and issue the permit; a refusal triggers written notice within ten days stating the reasons. Permits expire under Sec. 4-51(d) if no work starts within six months of issuance or if work is suspended for six months, forfeiting the fees already paid. Building without the required permit violates this division and is punishable under Sec. 4-54(b)(1).

Violations & Fines

Starting work without the Sec. 4-50 permit violates Chapter 4's technical codes division. Sec. 4-54(a) lets the building official issue a stop-work order until the violation is corrected, and Sec. 4-54(b)(1) makes anyone who violates or fails to comply subject to the general penalty in Sec. 1-11: a fine up to $1,000.00, up to 60 days in the county jail, or both, with each day of continued work a separate offense.

Frequently Asked Questions

Do I need a permit to remodel or add onto my house in unincorporated Bulloch County?
Yes. Sec. 4-50(a)(1) requires an owner or authorized agent to apply to the building official and obtain a permit before constructing, enlarging, altering, repairing, moving, demolishing or changing the occupancy of a building or structure, which covers most additions and remodels.
Is any work exempt from a Bulloch County building permit?
Only the specific items listed in the administration section of the International Residential Code are exempt, per Sec. 4-50(a)(3). Everything else, including new construction, alterations and regulated electrical, gas, mechanical or plumbing system work, requires a permit from the building official first.
How long does the county have to review my building permit application?
Sec. 4-51(a)(2) gives the building official five working days after filing to examine the application; if it complies with applicable codes it must be approved and the permit issued, and a refusal requires written notice of the reasons within ten days.
What happens if my Bulloch County building permit expires?
Under Sec. 4-51(d), a permit expires if no work begins within six months of issuance, or if started work is suspended or abandoned for six months, and the fees already paid are forfeited, so plans must be resubmitted for a new permit.

Sources & Official References

Other rules in Bulloch County

All Bulloch County rules

Compare Bulloch County to another location·View the Georgia building safety overview

Get notified when Building Permits in Bulloch County, GA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.