Bulloch County, GA Building Safety: Building Inspections (2026)
Key Facts
- Governing section
- Bulloch County Code § 4-52(a)
- First inspection
- Foundation, after footings excavated
- Mid-stage inspection
- Dry-in, roof and framing complete
- Final inspection
- Certificate of occupancy required
- Inspection scheduling
- Within 48 hours (Sec. 4-52(c))
Summary
Bulloch County's building official inspects construction in stages under Sec. 4-52(a): foundation, dry-in, insulation, permanent power and a final certificate-of-occupancy inspection. Work cannot proceed past each stage until the building official signs off, and a certificate of occupancy must be issued before the structure is used.
(a)The building official upon notification from the permit holder or his agent shall make the following inspections of buildings and such other inspections as may be necessary, and shall either approve the portion of construction as completed or shall notify the permit holder or his agent of any violation of compliance with this division:(1)Foundation inspection/temporary power: To be made after trenches for footings are excavated and all forms and required reinforcement materials erected. Temporary electric service should also be erected. ... (8)Dry-in inspection: To be made after the roof, all framing, fireblocking and bracing is in place. Plumbing, electrical and mechanical systems are to be roughed-in, including all pipes and concealed wiring. Chimney ducts and vents are complete. ... (11)Certificate of occupancy inspection:a.Certificate of occupancy is required before a structure for which a building permit has been issued may be occupied or used.
Full Breakdown
Bulloch County Code Section 4-52(a) lists the inspections the building official makes 'upon notification from the permit holder or his agent,' approving each completed stage or notifying the holder of any violation of Chapter 4's technical codes division. The sequence begins with the foundation inspection, made after footing trenches are excavated and forms and reinforcement are erected, with temporary electric service also in place at that point. It continues through slab, sub-floor, framing and exterior sheathing checks before reaching the dry-in inspection, made once the roof, framing, fireblocking and bracing are in place and plumbing, electrical and mechanical systems are roughed-in, including concealed wiring and chimney vents.
An insulation inspection follows to confirm energy-code compliance, then a permanent power inspection tied to National Electric Code compliance. The final step is the certificate of occupancy inspection: Sec. 4-52(a)(11) requires a certificate of occupancy, signed by the zoning administrator and building official, before any structure built under a building permit may be occupied or used. Sec. 4-52(b) bars work beyond the point marked by each successive inspection without the building official's approval, and Sec. 4-52(c) commits the building official to scheduling required inspections within 48 hours, excluding Saturdays, Sundays and county-observed holidays.
Violations & Fines
Proceeding with construction past an inspection stage without the building official's approval violates Sec. 4-52(b) and Chapter 4's technical codes division generally. Sec. 4-54(a) allows a stop-work order, and Sec. 4-54(b)(1) subjects the violator to the general penalty of Sec. 1-11, a fine up to $1,000.00, up to 60 days in jail, or both, and occupying a structure without the required certificate of occupancy under Sec. 4-52(a)(11) is treated the same way.
Frequently Asked Questions
What is the first inspection in a Bulloch County building project?
What does the dry-in inspection check?
Can I move into a new home before the county issues a certificate of occupancy?
How fast will Bulloch County schedule a required inspection?
Sources & Official References
Other rules in Bulloch County
Compare Bulloch County to another location·View the Georgia building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.