Littleton, CO Building Safety: Building Permits (2026)
Key Facts
- Access distance
- Street and access completed to within 25 feet of the building
- Minimum base course
- At least 2 inches of asphaltic or accepted dustproof material
- Who decides
- The City Manager or a duly appointed representative
- Occupancy hold
- Final approval and certificate of occupancy denied until improvements are inspected
- Guarantee options
- Bond, cash deposit, letter of credit or other approved obligation
- Default window
- 30 days after written notice before the City keeps the guarantee
- Current text effective
- July 24, 2025 (Ord. 11, Series of 2025)
Summary
Littleton issues no building permit until the public street and access to within 25 feet of the building are completed with at least a 2-inch asphaltic base course, or another dustproof, non-erodible material the City Manager's office accepts. Required curb, gutter, sidewalk and drainage work must be finished before final approval and certificate of occupancy, or secured by a bond, cash deposit or letter of credit.
C. Performance Bond or Cash Deposit: 1. The administration shall deny final approval and certificate of occupancy of any building until the required off-site improvements are completed and have been inspected and approved, unless completion of the off-site improvements is guaranteed by a performance bond, cash deposit, letter of credit or other obligation approved by the administration and the city attorney for a sum determined by the administration to be adequate to effect the improvements as required. ... D. Adequate Street Access Required: No building permit shall be issued by the administration until the public street and access to within twenty-five feet (25') of the building for which such permit is requested shall be completed with a minimum base course of at least two inch (2") asphaltic material or other dustproof, non-erodible material as may be accepted by the administration for the purpose of providing access to the site for both construction and emergency service vehicles prior to the initiation of construction.
Full Breakdown
Section 4-1-2 of the Littleton City Code, in Title 4 (Building Regulations), Chapter 1 (Building Codes), ties a building permit to the condition of the public right-of-way next to the project. The section defines "administration" as the City Manager or a duly appointed representative, so every approval, acceptance and guarantee decision below is made by the City Manager or that delegate. It defines "off-site improvements" as any physical improvement above or below ground that the City requires in an alley, street, other public right-of-way or easement, or publicly owned property adjacent to the property for which a building permit is being sought for development, redevelopment or other construction. The definition names curb, gutter, sidewalk, paving, drainage structures and fire hydrants.
The front gate is subsection D, Adequate Street Access Required. No building permit is issued until the public street and access to within twenty-five feet (25') of the building are completed with a minimum base course of at least two inches (2") of asphaltic material, or other dustproof, non-erodible material the administration accepts. The code states the purpose: access to the site for both construction crews and emergency service vehicles, in place before construction starts. An applicant whose lot fronts an unimproved street therefore has to get that access built before the permit exists, not after.
The back gate is subsection C.1. The administration denies final approval and the certificate of occupancy for any building until the required off-site improvements are completed, inspected and approved. The one way around that denial is a guarantee: a performance bond, cash deposit, letter of credit or other obligation approved by both the administration and the city attorney, in a sum the administration determines is adequate to build the improvements.
Subsection C.2 governs the money. A guarantee goes back to the depositor once the administration approves the finished work. If the depositor fails or refuses to install the work within thirty (30) days after receiving written notice from the administration, the City keeps all or part of the guarantee as compensation for performing the work itself.
Subsection E lets the City delay installation for a temporary period when practical difficulties such as a conflict with proposed public improvements or efficiency of coordination call for it. The delay applies only to the off-site installation requirement, and only if the owner or the owner's authorized representative signs a contract to approve creation of an improvement district and to install the improvements within thirty (30) days of written notice. The current text carries Ord. 24 (1974), Ord. 26 (2022) and Ord. 11 (2025), and took effect July 24, 2025.
Violations & Fines
The text of § 4-1-2 prints no fine or jail term. Enforcement works by withholding approvals. The administration refuses to issue the building permit until the street and access standard in subsection D is met. It denies final approval and the certificate of occupancy under C.1 while required off-site work is unfinished and unguaranteed. Under C.2 the City keeps part or all of a guarantee if the depositor does not install the work within thirty days of written notice.
Frequently Asked Questions
Can I get a building permit in Littleton before the street in front of my lot is paved?
Can Littleton refuse a certificate of occupancy if the curb and sidewalk are unfinished?
What counts as an off-site improvement under the Littleton code?
When does Littleton keep a performance guarantee?
Can the City delay the off-site improvement requirement?
Sources & Official References
Other rules in Littleton
Compare Littleton to another location·View the Colorado building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Building Permits in Nearby Cities
How other cities in Arapahoe County handle building permits.