Key Facts

Adopted code
2024 International Building Code
Permit withheld until
off-site improvements approved
Street access required
paved to within 25 ft of building
Appeal deadline
10 days to Appeals and Adjustment Commission
Fee exemption
government entities, but permit still required

Summary

Littleton requires a building permit for construction reviewed under the locally amended 2024 International Building Code, and the Building Division will not issue one until plans for off-site improvements such as curb, gutter and sidewalk are approved and the site has adequate paved street access. Government entities must still apply for permits even though their fees are waived.

A. Approval of Plans Required: No building permit shall be issued by the administration until plans for installation of off-site improvements, in conformity with the standards of the City, have been submitted and approved. ... ... D. Adequate Street Access Required: No building permit shall be issued by the administration until the public street and access to within twenty-five feet (25') of the building for which such permit is requested shall be completed with a minimum base course of at least two inch (2") asphaltic material or other dustproof, non-erodible material as may be accepted by the administration for the purpose of providing access to the site for both construction and emergency service vehicles prior to the initiation of construction.

Full Breakdown

1 accessibility standard, the 2026 NEC and the 1997 Uniform Code for the Abatement of Dangerous Buildings, all administered by the city's Building Inspection Division. Section 4-1-2 adds a local condition on top of the model code: no building permit issues until plans for off-site improvements, meaning curb, gutter, sidewalk, paving, drainage structures, fire hydrants and similar work in an adjacent right-of-way, are submitted and approved, and the administration can require a performance bond, cash deposit or letter of credit to guarantee that work gets finished.

Subsection (D) adds an adequate street access rule: no permit issues until the public street and access to within 25 feet of the building are built out with at least a 2-inch asphaltic base course or other dustproof material, so construction and emergency vehicles can reach the site. The administration can temporarily waive the off-site improvement requirement under subsection (E) if the owner signs a contract to create an improvement district and still completes the work within 30 days of written notice. Appeals of a building official's decision go to the Appeals and Adjustment Commission within 10 days under § 4-1-3.

Federal, state, school and county governmental units are exempt from building permit fees under § 4-1-4, but that exemption does not excuse them from applying for a permit or from inspection.

Violations & Fines

Violating any provision of the building codes adopted in § 4-1-1, including building without a required permit or without approved off-site improvements, is unlawful under Littleton City Code § 4-1-8. It is punishable under the general penalty in § 1-4-1: a fine of up to $2,650, imprisonment of up to 364 days, or both, with each day the violation continues treated as a separate offense.

Frequently Asked Questions

What building code does Littleton use?
The 2024 International Building Code, adopted by Littleton City Code § 4-1-1 along with a full set of companion International codes, the 2026 National Electric Code and the 2017 ICC A117.1 accessibility standard. The Building Inspection Division administers and enforces them, and the most recently printed edition governs.
Why would Littleton delay issuing my building permit?
If off-site improvements like curb, gutter, sidewalk or drainage work in the adjacent right-of-way have not been approved, or if the street is not paved to within 25 feet of the building with an adequate base course, § 4-1-2 blocks permit issuance until those conditions are met or a bond guarantees completion.
How do I appeal a Littleton building official's decision?
File a written appeal on city forms within 10 days of the final decision under § 4-1-3. The building official schedules a hearing before the Appeals and Adjustment Commission, which has taken over the role the model code assigns to a board of appeals.
Does a government building need a permit in Littleton?
Yes. Section 4-1-4 exempts federal, state, school and county governmental units from paying building permit fees, but it explicitly does not excuse them from applying for a permit or from having the work inspected under the city's codes.

Sources & Official References

Other rules in Littleton

All Littleton rules

Compare Littleton to another location·View the Colorado building safety overview

Get notified when Building Permits in Littleton, CO changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Permits in Nearby Cities

How other cities in Arapahoe County handle building permits.

Aurora, CO
Some Restrictions
Centennial, CO
Some Restrictions