Key Facts

Adopted code
Wis. Admin. Code SPS 305 and SPS 316 (NEC)
Permit required
Before any electrical work begins
Homeowner exemption
Owner-occupied single-family home only
Permit lapse
6 months if work not started
Permit expiration
1 year from issuance once started
Late-start fee
Doubled if work starts before permit
Penalty
Forfeiture under § 25.04

Summary

No one may start electrical work in the City of Beloit without a permit under Beloit Code of Ordinances § 10.03. The city adopts Wis. Admin. Code SPS 305 and 316, including the National Electrical Code provisions SPS 316 incorporates, and lets a homeowner wire only their own owner-occupied single-family home.

The Wisconsin Administrative Code, Safety and Professional Services (SPS) chapters 305 and 316, and any future amendments thereto, are hereby adopted and incorporated into this chapter by reference in order to secure uniform statewide regulation and enforcement of law relating to electricity. Those portions of the National Electrical Code (NEC) which are adopted by §SPS 316, Wis. Admn. Code, and any future amendments thereto, are also adopted and incorporated into this chapter by reference. ... (1)PERMIT REQUIRED. No person shall commence electrical work in the City of Beloit until a permit is obtained in accordance with Wis. Admin. Code SPS §316.012(1)(a). Permits shall only be issued to an Electrical Contractor licensed by the State of Wisconsin, a person exempt under the provisions of §101.862(5) or (6), Wis. Stats., or to a homeowner as outlined below.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Update 01 - 05-2026).

Full Breakdown

Chapter 10 adopts the Wisconsin Administrative Code's Safety and Professional Services chapters 305 and 316, plus the National Electrical Code provisions SPS 316 incorporates, as the electrical standard for the City of Beloit (§ 10.01). Section 10.03(1) bars anyone from commencing electrical work until a permit is obtained under Wis. Admin. Code SPS § 316.012(1)(a); permits go only to a state-licensed Electrical Contractor, a person exempt under Wis. Stat. § 101.862(5) or (6), or a homeowner performing work in a house that person owns and occupies as a single-family residence. A homeowner permit requires submitting plans to the Electrical Inspector, satisfying the Inspector of the homeowner's ability to do the work, filing an application, and signing an affidavit that the homeowner will do the work personally and not hire anyone else.

The permit card must stay posted where the public can see it, no more than 15 feet above grade, for the whole job. Under § 10.03(4), an unstarted permit lapses after 6 months, and a permit for work that has begun expires one year from issuance unless renewed. Section 10.04 lets the city double the fee if work starts before a permit issues, and blocks new permits or inspections until any fee arrears are paid. The Electrical Inspector must inspect completed work within 2 business days of notice under § 10.08, and concealing wiring before that inspection is itself a violation.

Violations & Fines

Any person convicted of violating Chapter 10, including working without a permit, concealing wiring before inspection, or ignoring a correction order, is subject to a forfeiture under § 10.11, which points to the general penalty schedule at § 25.04 of the Municipal Code. Removing a posted stop-work order or continuing work after one is served is a separate violation under § 10.06(2), also punishable under § 25.04.

Frequently Asked Questions

Can I do my own electrical wiring in my Beloit home?
Yes, but only if you own the house and live in it as your single-family residence. Section 10.03(1)(b) requires you to submit plans to the Electrical Inspector, prove you can do the work safely, file a permit application, and sign an affidavit that you will not hire anyone else to help with the wiring.
What electrical code does the City of Beloit use?
Beloit adopts Wis. Admin. Code Safety and Professional Services chapters 305 and 316 by reference in § 10.01, along with whatever portions of the National Electrical Code those chapters incorporate. Any future state amendments to SPS 305 or 316 automatically become part of Beloit's electrical chapter without a separate city ordinance.
How long is a Beloit electrical permit good for?
Under § 10.03(4), the permit lapses if the work has not started within 6 months of issuance. Once work begins within that window, the permit is valid for one year from its issue date, and it can be renewed if the work is progressing with reasonable diligence.
What happens if I start electrical work before getting a permit?
Section 10.04(1)(a) doubles the normal permit fee for work started before a permit issues, on top of any penalty the city imposes for the underlying violation under § 10.11. Paying the doubled fee does not excuse the violation or block a separate forfeiture.

Sources & Official References

Other rules in Beloit

All Beloit rules

Compare Beloit to another location·View the Wisconsin building safety overview

Get notified when Electrical Permits in Beloit, WI changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Electrical Permits in Nearby Cities

How other cities in Rock County handle electrical permits.

Milton, WI
Some Restrictions