Summary

Fitchburg, Wisconsin requires an electrical permit from the city building inspector before any electrical work begins. The city adopts the Wisconsin Electrical Code (Admin. Code SPS 316) by reference, so all wiring in this Dane County suburb must meet the state standard on top of the local permit rule.

Sec. 35-101. - Electrical, plumbing and heating permits. No person shall commence any electrical, plumbing or heating work covered by this article without first obtaining an electrical permit therefor from the building inspector. ... The provisions of the following state codes and subsequent amendments and recodifications thereto are hereby adopted by reference and incorporated in this article as if fully set forth. Violations of the provisions hereby adopted shall be deemed a violation of this chapter and subject to enforcement and abatement procedures as set forth in section 35-59. ... (1)Wis. Admin. Code SPS 316, Electrical Code.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 30).

Full Breakdown

Fitchburg City Code Sec. 35-101 bars anyone from commencing electrical work covered by chapter 35 without first getting an electrical permit from the building inspector. That permit requirement sits alongside Sec. 35-77, which adopts Wis. Admin. Code SPS 316 (the Electrical Code) by reference, along with subsequent amendments and recodifications, as if fully set forth in the city's own ordinance; a violation of the adopted state code is treated as a violation of the city chapter and enforced the same way. Applications follow the general building-permit process: a written application on the building inspector's form describing the work and identifying the contractor (Sec.

35-135), plans where required, and payment of the fee set under Wis. Admin. 31. Electrical installations get a rough inspection after wiring is run but before it is covered or concealed, and a final inspection before any part of the building is occupied (Sec. 35-220(4), (6)); work may not be enclosed until the building inspector has signed off, except where an inspection request has gone unanswered for more than two business days (Sec. 35-219). Sec. 35-78 makes clear that where the referenced code conflicts with or is less stringent than the city or state code, the more stringent standard controls, and the building inspector decides how to apply any topic the referenced code covers that the city code does not address.

Violations & Fines

Electrical work performed without a permit, or in violation of the adopted Electrical Code, is enforced under Sec. 35-59: the building inspector can issue a notice of violation and order, suspend or revoke the permit, and refer prosecution to the city attorney, including a chapter 18 citation imposing a forfeiture or a court injunction. Absent a specific schedule penalty, Sec. 1-21's general penalty applies, a forfeiture of $25.00 to $500.00 for a first offense and $50.00 to $1,000.00 for repeat offenses within a year, with each day of noncompliance a separate offense.

Frequently Asked Questions

Do I need a separate electrical permit in Fitchburg, WI?
Yes. Sec. 35-101 requires an electrical permit from the building inspector before any electrical work covered by chapter 35 begins, separate from a general building permit for the rest of the project.
What electrical code does Fitchburg use?
The city adopts Wis. Admin. Code SPS 316, the state Electrical Code, by reference under Sec. 35-77(1), including later amendments, so wiring must meet the current state standard as enforced through the city's own permit and inspection process.
Can I cover wiring before it is inspected?
No. Sec. 35-218 bars enclosing electrical work before the building inspector's rough inspection, unless the inspector fails to respond within two business days of a proper request under Sec. 35-219, in which case work may proceed.

Sources & Official References

Other rules in Fitchburg

All Fitchburg rules

Compare Fitchburg to another location·View the Wisconsin building safety overview

Get notified when Electrical Permits in Fitchburg, WI changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Electrical Permits in Nearby Cities

How other cities in Dane County handle electrical permits.

Madison, WI
Some Restrictions
Middleton, WI
Some Restrictions
Sun Prairie, WI
Some Restrictions